Huachuca City applies its own fee schedule. Cochise County does not currently add county-level impact fees inside city limits. A new single-family home pays $200.00 per unit (rates sourced ). The full breakdown is below.

Huachuca City Impact Fees by Project Type

Huachuca City: Single-Family Impact Fees

A new single-family home in Huachuca City pays $200.00 per unit in impact fees (rates sourced October 15, 2026). Every line item is levied at the municipal or utility level.

The largest line items are Sewer Connection Fee (Town of Huachuca City) ($200.00).

View the Full Huachuca City Impact Fee Schedule
Water$0.00
Sewer$200.00
City$0.00
County$0.00
Total (Huachuca City): $200.00
Sources last checked Official fee schedules:Town of Huachuca City Cochise County

Where in Cochise County Are You Building?

Each jurisdiction applies its own fee schedule. Pick yours. = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.

Huachuca City: Multifamily Impact Fees

A new multifamily unit in Huachuca City pays $200.00 per unit in impact fees (rates sourced October 15, 2026). Every line item is levied at the municipal or utility level.

The largest line items are Sewer Connection Fee (Town of Huachuca City, MF) ($200.00).

View the Full Huachuca City Impact Fee Schedule
Water$0.00
Sewer$200.00
City$0.00
County$0.00
Total (Huachuca City): $200.00
Sources last checked Official fee schedules:Town of Huachuca City Cochise County

Where in Cochise County Are You Building?

Each jurisdiction applies its own fee schedule. Pick yours. = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.

Huachuca City: Commercial Impact Fees

Commercial development in Huachuca City pays no per-square-foot impact fees, but owes $300.00 in one-time water and sewer connection fees (rates sourced October 15, 2026).

For a 50,000 sq ft building, that comes to about $300.00. The calculator below adjusts to your exact square footage.

The largest line items are Sewer Connection Fee (Town of Huachuca City) ($300.00 one-time).

View the Full Huachuca City Impact Fee Schedule
Water$0.00
  • Water Connection/Meter Fee (Town of Huachuca City)
    Town of Huachuca City
    Huachuca City charges no fixed water capacity or connection fee; a new meter and service line are billed at the Town's actual cost, plus a $50 labor charge when no new service line is needed.
    $0.00
Sewer$300.00 one-time
City$0.00
County$0.00
Total (Huachuca City): $300.00 one-time (≈ $300.00 at 50,000 sq ft)
Sources last checked Official fee schedules:Town of Huachuca City Cochise County

Where in Cochise County Are You Building?

Each jurisdiction applies its own fee schedule. Pick yours. Totals shown are for a 50,000 sq ft building, including one-time water/sewer fees (assuming a 1-inch meter). * = one-time water/sewer connection charges only; no per-sq-ft impact fee schedule sourced for that jurisdiction. = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.

Huachuca City: Industrial Impact Fees

Industrial development in Huachuca City pays no per-square-foot impact fees, but owes $300.00 in one-time water and sewer connection fees (rates sourced October 15, 2026).

For a 50,000 sq ft building, that comes to about $300.00. The calculator below adjusts to your exact square footage.

The largest line items are Sewer Connection Fee (Town of Huachuca City) ($300.00 one-time).

View the Full Huachuca City Impact Fee Schedule
Water$0.00
  • Water Connection/Meter Fee (Town of Huachuca City)
    Town of Huachuca City
    Huachuca City charges no fixed water capacity or connection fee; a new meter and service line are billed at the Town's actual cost, plus a $50 labor charge when no new service line is needed.
    $0.00
Sewer$300.00 one-time
City$0.00
County$0.00
Total (Huachuca City): $300.00 one-time (≈ $300.00 at 50,000 sq ft)
Sources last checked Official fee schedules:Town of Huachuca City Cochise County

Where in Cochise County Are You Building?

Each jurisdiction applies its own fee schedule. Pick yours. Totals shown are for a 50,000 sq ft building, including one-time water/sewer fees (assuming a 1-inch meter). * = one-time water/sewer connection charges only; no per-sq-ft impact fee schedule sourced for that jurisdiction. = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.

Huachuca City: Office Impact Fees

Office development in Huachuca City pays no per-square-foot impact fees, but owes $300.00 in one-time water and sewer connection fees (rates sourced October 15, 2026).

For a 25,000 sq ft building, that comes to about $300.00. The calculator below adjusts to your exact square footage.

The largest line items are Sewer Connection Fee (Town of Huachuca City) ($300.00 one-time).

View the Full Huachuca City Impact Fee Schedule
Water$0.00
  • Water Connection/Meter Fee (Town of Huachuca City)
    Town of Huachuca City
    Huachuca City charges no fixed water capacity or connection fee; a new meter and service line are billed at the Town's actual cost, plus a $50 labor charge when no new service line is needed.
    $0.00
Sewer$300.00 one-time
City$0.00
County$0.00
Total (Huachuca City): $300.00 one-time (≈ $300.00 at 25,000 sq ft)
Sources last checked Official fee schedules:Town of Huachuca City Cochise County

Where in Cochise County Are You Building?

Each jurisdiction applies its own fee schedule. Pick yours. Totals shown are for a 25,000 sq ft building, including one-time water/sewer fees (assuming a 1-inch meter). * = one-time water/sewer connection charges only; no per-sq-ft impact fee schedule sourced for that jurisdiction. = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.

Huachuca City Impact Fee Calculator

Estimate impact fees for your project. Set to single-family. Drop a pin or search an address for site-specific fees.

Location

Select a location to begin

Once you select an address or drop a pin, we'll identify the responsible city and county and generate a fee breakdown.

Water & Sewer
Transportation
Parks
Schools
Fire & Police
General

How Development Impact Fees Work in Arizona

Arizona cities and towns assess development impact fees (the statute calls them development fees) under A.R.S. 9-463.05 and counties under A.R.S. 11-1102. A fee can only be adopted after the governing body adopts land use assumptions and an infrastructure improvements plan for the service area, with public notice and hearings, and the plan projects demand for no more than ten years.

Fees are limited to necessary public services the statute lists: water, wastewater, stormwater and drainage, streets, fire and police facilities, neighborhood parks of up to 30 acres and, for cities, small libraries. Each fee must be proportionate to the new development's share of the cost, kept in a separate account for that service category and service area, and never used for operations, maintenance or a higher level of service for existing development.

Developers earn credits for facilities they build or dedicate, and a fee that goes unspent for ten years (fifteen for water or wastewater) is refundable with interest on request. For a residential unit the fee is due when the building permit issues unless a development agreement defers it, and a new or increased fee cannot be applied to an approved plat or site plan for 24 months.

Counties and cities each adopt their own schedules. County development fees apply in the county's service areas; inside city limits, development pays the city's fees plus any utility connection charges, which is why totals differ between a city and the unincorporated county around it.

For a primer on how impact fees work, see our plain-English guide.

Summary current as of October 2026. This is an editorial summary, not legal advice; see the official statute text and our terms of use.

Huachuca City Impact Fee FAQs

What are the total impact fees for a single-family home in Huachuca City, Arizona?

A new single-family home in Huachuca City pays $200.00 per unit in combined impact fees (rates sourced October 15, 2026).

How much are commercial impact fees in Huachuca City?

Commercial development in Huachuca City pays no per-square-foot impact fees, but owes $300.00 in one-time water and sewer connection fees.

Does Huachuca City charge its own impact fees?

Yes. Huachuca City levies its own municipal impact or utility fees. Cochise County does not currently add county-level impact fees inside Huachuca City. The schedule on this page shows every fee that applies to development in Huachuca City.

Can Arizona development impact fees increase at any time?

No. Under A.R.S. 9-463.05 and 11-1102 a new or increased fee cannot be adopted on an emergency basis, takes effect only after public notice and hearings (75 days after adoption for a city, 90 for a county), and cannot be applied to a development with an approved final plat or site plan for 24 months unless the plan changes to add service units.

Fee amounts on this page are compiled from official published schedules and are provided for planning purposes only. Rates change, and project specifics (unit size, meter size, location within special districts) can alter what applies. Always verify current fees with the jurisdiction and utility before relying on them.

Compare unincorporated rates and every other city on the Cochise County impact fees page.