Putnam County, Florida Impact Fees

Impact fees in Putnam County depend on where you build. This page details the rates for unincorporated Putnam County: $15,771.00 per single-family unit as of July 18, 2026. Inside city limits, each city applies its own schedule and fees may be completely different. Pick your city below.

Putnam County impact fees by project type

Where in Putnam County are you building?

Each jurisdiction applies its own fee schedule. Pick yours. = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.

Unincorporated Putnam County: Single-Family Impact Fees

A new single-family home in unincorporated Putnam County pays $15,771.00 per unit in impact fees (rates sourced July 18, 2026). All of it is levied by Putnam County.

The largest line items are Wastewater Capacity Impact Fee (E. Putnam Regional Wastewater) ($5,455.00), Transportation Impact Fee (Putnam County) ($4,927.00) and Water Capacity Impact Fee (E. Putnam Regional Water) ($2,605.00).

View the full fee schedule
Water$2,605.00
  • Water Capacity Impact Fee (E. Putnam Regional Water)
    Putnam County (E. Putnam Regional Water/Wastewater)
    CONFIRMED (re-verified 7/14/2026 against Municode Ch. 24, version 'Feb 2, 2026 (current)'). Water and Wastewater Impact Fee Schedule for E. Putnam Regional Water/Wastewater, codified in Ch. 24: Meter Equivalent approach — 3/4-inch meter = 1.00 ME factor = $2,605 water. Larger meters scale (1-inch 1.67 ME = $4,340; 2-inch 5.33 ME = $13,890, etc.). Estimated-Flow alternative: avg daily flow (gal) × $8.68/gal; the fee due is the GREATER of the two. Applies in the E. Putnam Regional Water service area (unincorporated). Ord. 2025-015 / FY25-26 Fee Schedule Res. 2025-073. Dev Svcs (386) 329-0307.
    $2,605.00
Sewer$5,455.00
  • Wastewater Capacity Impact Fee (E. Putnam Regional Wastewater)
    Putnam County (E. Putnam Regional Water/Wastewater)
    CONFIRMED (re-verified 7/14/2026 against Municode Ch. 24, version 'Feb 2, 2026 (current)'). Water and Wastewater Impact Fee Schedule for E. Putnam Regional Water/Wastewater, codified in Ch. 24: Meter Equivalent approach — 3/4-inch meter = 1.00 ME factor = $5,455 wastewater. Estimated-Flow alternative: avg daily flow (gal) × $22.73/gal; the fee due is the GREATER of the two. Applies in the E. Putnam Regional Wastewater service area (unincorporated). Ord. 2025-015 / FY25-26 Fee Schedule Res. 2025-073. Dev Svcs (386) 329-0307.
    $5,455.00
City$0.00
County$7,711.00
Total (unincorporated Putnam County): $15,771.00
Sources last checked July 18, 2026Official fee schedules:Putnam County (E. Putnam Regional Water/Wastewater) Putnam County

Where in Putnam County are you building?

Each jurisdiction applies its own fee schedule. Pick yours. = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.

Unincorporated Putnam County: Multifamily Impact Fees

A new multifamily unit in unincorporated Putnam County pays $12,468.00 per unit in impact fees (rates sourced July 18, 2026). All of it is levied by Putnam County.

The largest line items are Transportation Impact Fee (Putnam County, MF Mid/High-Rise 4+ floors) ($2,199.00), General Government Buildings Impact Fee (Putnam County, MF) ($1,018.00) and Fire/Rescue Impact Fee (Putnam County, MF) ($738.00).

Wastewater Capacity Impact Fee (E. Putnam Regional Wastewater, MF) and Water Capacity Impact Fee (E. Putnam Regional Water, MF) are shown at the last published amount but have not been confirmed with the jurisdiction; they are included in the totals here. Verify before budgeting.

Some fees are tiered by unit size or building type; amounts reflect the representative tier noted in the schedule below.

View the full fee schedule
Water$2,605.00
  • Water Capacity Impact Fee (E. Putnam Regional Water, MF)
    Putnam County (E. Putnam Regional Water/Wastewater)
    AMOUNT SHOWN IS THE 3/4-INCH-METER FIGURE, NOT A PER-UNIT MF RATE. Ch. 24 W/W Impact Fee Schedule (Municode current 2-2-2026) is METER-EQUIVALENT based: 3/4-inch = 1.00 ME = $2,605 water; 1-inch 1.67 ME = $4,340; 2-inch 5.33 ME = $13,890; 3-inch 10.67 ME = $27,785. Alternative Estimated-Flow approach: avg daily flow (gal) × $8.68/gal — the fee due is the GREATER of the two. A master-metered MF project pays by its service-meter size (or flow), so this row does NOT represent a true per-unit rate. UNCONFIRMED: get the county's per-unit / ERU convention for multifamily from Dev Svcs (386) 329-0307.
    $2,605.00Requires confirmation
Sewer$5,455.00
  • Wastewater Capacity Impact Fee (E. Putnam Regional Wastewater, MF)
    Putnam County (E. Putnam Regional Water/Wastewater)
    AMOUNT SHOWN IS THE 3/4-INCH-METER FIGURE, NOT A PER-UNIT MF RATE. Ch. 24 W/W Impact Fee Schedule (Municode current 2-2-2026) is METER-EQUIVALENT based: 3/4-inch = 1.00 ME = $5,455 wastewater; 1-inch 1.67 ME = $9,090; 2-inch 5.33 ME = $29,090. Alternative Estimated-Flow approach: avg daily flow (gal) × $22.73/gal — the fee due is the GREATER of the two. A master-metered MF project pays by its service-meter size (or flow), so this row does NOT represent a true per-unit rate. UNCONFIRMED: get the county's per-unit / ERU convention for multifamily from Dev Svcs (386) 329-0307.
    $5,455.00Requires confirmation
City$0.00
County$4,408.00
Total (unincorporated Putnam County): $12,468.00
Sources last checked July 18, 2026Official fee schedules:Putnam County (E. Putnam Regional Water/Wastewater) Putnam County
Amounts flagged "Requires confirmation" are the last published figures, included in the totals. Confirm them with the jurisdiction or utility before budgeting.

Where in Putnam County are you building?

Each jurisdiction applies its own fee schedule. Pick yours. Totals shown are for a 50,000 sq ft building, including one-time water/sewer fees (assuming a 1-inch meter). * = one-time water/sewer connection charges only; no per-sq-ft impact fee schedule sourced for that jurisdiction. = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.

Unincorporated Putnam County: Commercial Impact Fees

Commercial development in unincorporated Putnam County pays $9.22 per square foot in impact fees, plus $13,430.00 in one-time water and sewer connection fees (rates sourced July 18, 2026).

For a 50,000 sq ft building, that comes to about $474,530.00. The calculator below adjusts to your exact square footage.

The largest line items are Wastewater Capacity Impact Fee (E. Putnam Regional Wastewater) — 1" meter ($9,090.00 one-time), Water Capacity Impact Fee (E. Putnam Regional Water) — 1" meter ($4,340.00 one-time) and Transportation Impact Fee (Putnam County, Commercial) ($4.65/sq ft).

Water and sewer connection fees assume a 1-inch meter; larger services pay more. See the meter-size tiers in the source schedules.

View the full fee schedule
Water$4,340.00 one-time
  • Water Capacity Impact Fee (E. Putnam Regional Water) — 1" meter
    E. Putnam Regional Water (Putnam County)
    Table 24-2, Putnam County Code Ch. 24 (Ord. 2025-015 / FY25-26 Fee Schedule Res. 2025-073, eff 6-10-2025; Municode 2-2-2026). E. Putnam Regional Water, Meter Equivalent Approach; 1" = 1.67 ME factor. Canonical nonres default. Fee due = GREATER of this meter-equivalent amount OR estimated-flow ($8.68/gal of avg daily flow). Same ME schedule for all customer classes; applies in E. Putnam Regional Water service area (unincorporated). Dev Svcs (386) 329-0307.
    $4,340.00 one-time
Sewer$9,090.00 one-time
  • Wastewater Capacity Impact Fee (E. Putnam Regional Wastewater) — 1" meter
    E. Putnam Regional Wastewater (Putnam County)
    Table 24-2, Putnam County Code Ch. 24 (Ord. 2025-015 / Res. 2025-073, eff 6-10-2025). E. Putnam Regional Wastewater, Meter Equivalent Approach; 1" = 1.67 ME. Canonical nonres default. Fee due = GREATER of this ME amount OR estimated-flow ($22.73/gal of avg daily flow). Same ME schedule all customer classes; unincorporated service area. Dev Svcs (386) 329-0307.
    $9,090.00 one-time
City$0.00
County$9.22/sq ft
Total (unincorporated Putnam County): $9.22/sq ft + $13,430.00 one-time (≈ $474,530.00 at 50,000 sq ft)
Water/sewer connection fees assume a 1-inch meter; larger services pay more.

Where in Putnam County are you building?

Each jurisdiction applies its own fee schedule. Pick yours. Totals shown are for a 50,000 sq ft building, including one-time water/sewer fees (assuming a 1-inch meter). * = one-time water/sewer connection charges only; no per-sq-ft impact fee schedule sourced for that jurisdiction. = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.

Unincorporated Putnam County: Industrial Impact Fees

Industrial development in unincorporated Putnam County pays $2.90 per square foot in impact fees, plus $13,430.00 in one-time water and sewer connection fees (rates sourced July 18, 2026).

For a 50,000 sq ft building, that comes to about $158,230.00. The calculator below adjusts to your exact square footage.

The largest line items are Wastewater Capacity Impact Fee (E. Putnam Regional Wastewater) — 1" meter ($9,090.00 one-time), Water Capacity Impact Fee (E. Putnam Regional Water) — 1" meter ($4,340.00 one-time) and Transportation Impact Fee (Putnam County, Industrial) ($2.15/sq ft).

Water and sewer connection fees assume a 1-inch meter; larger services pay more. See the meter-size tiers in the source schedules.

View the full fee schedule
Water$4,340.00 one-time
  • Water Capacity Impact Fee (E. Putnam Regional Water) — 1" meter
    E. Putnam Regional Water (Putnam County)
    Table 24-2, Putnam County Code Ch. 24 (Ord. 2025-015 / FY25-26 Fee Schedule Res. 2025-073, eff 6-10-2025; Municode 2-2-2026). E. Putnam Regional Water, Meter Equivalent Approach; 1" = 1.67 ME factor. Canonical nonres default. Fee due = GREATER of this meter-equivalent amount OR estimated-flow ($8.68/gal of avg daily flow). Same ME schedule for all customer classes; applies in E. Putnam Regional Water service area (unincorporated). Dev Svcs (386) 329-0307.
    $4,340.00 one-time
Sewer$9,090.00 one-time
  • Wastewater Capacity Impact Fee (E. Putnam Regional Wastewater) — 1" meter
    E. Putnam Regional Wastewater (Putnam County)
    Table 24-2, Putnam County Code Ch. 24 (Ord. 2025-015 / Res. 2025-073, eff 6-10-2025). E. Putnam Regional Wastewater, Meter Equivalent Approach; 1" = 1.67 ME. Canonical nonres default. Fee due = GREATER of this ME amount OR estimated-flow ($22.73/gal of avg daily flow). Same ME schedule all customer classes; unincorporated service area. Dev Svcs (386) 329-0307.
    $9,090.00 one-time
City$0.00
County$2.90/sq ft
Total (unincorporated Putnam County): $2.90/sq ft + $13,430.00 one-time (≈ $158,230.00 at 50,000 sq ft)
Water/sewer connection fees assume a 1-inch meter; larger services pay more.

Where in Putnam County are you building?

Each jurisdiction applies its own fee schedule. Pick yours. Totals shown are for a 25,000 sq ft building, including one-time water/sewer fees (assuming a 1-inch meter). * = one-time water/sewer connection charges only; no per-sq-ft impact fee schedule sourced for that jurisdiction. = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.

Unincorporated Putnam County: Office Impact Fees

Office development in unincorporated Putnam County pays $6.38 per square foot in impact fees, plus $13,430.00 in one-time water and sewer connection fees (rates sourced July 18, 2026).

For a 25,000 sq ft building, that comes to about $173,005.00. The calculator below adjusts to your exact square footage.

The largest line items are Wastewater Capacity Impact Fee (E. Putnam Regional Wastewater) — 1" meter ($9,090.00 one-time), Water Capacity Impact Fee (E. Putnam Regional Water) — 1" meter ($4,340.00 one-time) and Transportation Impact Fee (Putnam County, Office) ($4.80/sq ft).

Water and sewer connection fees assume a 1-inch meter; larger services pay more. See the meter-size tiers in the source schedules.

View the full fee schedule
Water$4,340.00 one-time
  • Water Capacity Impact Fee (E. Putnam Regional Water) — 1" meter
    E. Putnam Regional Water (Putnam County)
    Table 24-2, Putnam County Code Ch. 24 (Ord. 2025-015 / FY25-26 Fee Schedule Res. 2025-073, eff 6-10-2025; Municode 2-2-2026). E. Putnam Regional Water, Meter Equivalent Approach; 1" = 1.67 ME factor. Canonical nonres default. Fee due = GREATER of this meter-equivalent amount OR estimated-flow ($8.68/gal of avg daily flow). Same ME schedule for all customer classes; applies in E. Putnam Regional Water service area (unincorporated). Dev Svcs (386) 329-0307.
    $4,340.00 one-time
Sewer$9,090.00 one-time
  • Wastewater Capacity Impact Fee (E. Putnam Regional Wastewater) — 1" meter
    E. Putnam Regional Wastewater (Putnam County)
    Table 24-2, Putnam County Code Ch. 24 (Ord. 2025-015 / Res. 2025-073, eff 6-10-2025). E. Putnam Regional Wastewater, Meter Equivalent Approach; 1" = 1.67 ME. Canonical nonres default. Fee due = GREATER of this ME amount OR estimated-flow ($22.73/gal of avg daily flow). Same ME schedule all customer classes; unincorporated service area. Dev Svcs (386) 329-0307.
    $9,090.00 one-time
City$0.00
County$6.38/sq ft
Total (unincorporated Putnam County): $6.38/sq ft + $13,430.00 one-time (≈ $173,005.00 at 25,000 sq ft)
Water/sewer connection fees assume a 1-inch meter; larger services pay more.

Estimate your project in Putnam County

Set to single-family. Drop a pin or search an address for site-specific fees.

Location

Loading map…
Search an address or click anywhere on the map to begin.

Select a location to begin

Once you select an address or drop a pin, we'll identify the responsible city and county and generate a fee breakdown.

Water & Sewer
Transportation
Parks
Schools
Fire & Police
General

How impact fees work in Florida

Florida impact fees are one-time charges on new development, governed by Section 163.31801, Florida Statutes (the Florida Impact Fee Act). The statute requires fees to be based on the most recent and localized data, spent on the infrastructure category they were collected for, and adopted by ordinance.

Since 2021, the law also limits how fast fees can rise: increases up to 25% phase in over two years, increases of 25–50% phase in over four years, and increases above 50% are allowed only with a demonstrated extraordinary-circumstances study and at least a two-thirds vote of the governing body.

Counties and cities can both levy impact fees. Inside an incorporated city, a project typically pays the county's countywide fees plus any municipal fees the city has adopted, which is why totals differ between a city and the unincorporated county around it.

Frequently asked questions

What are single-family impact fees in Putnam County, Florida?

A new single-family home in unincorporated Putnam County pays $15,771.00 per unit in impact fees (rates sourced July 18, 2026). Inside city limits, fees are set by each city's own schedule and may be completely different. See the city pages for their rates.

How much are multifamily impact fees in Putnam County?

Multifamily development in unincorporated Putnam County pays $12,468.00 per unit in impact fees (rates sourced July 18, 2026). This figure includes amounts that have not been confirmed with the jurisdiction; verify before budgeting. Rates inside city limits depend on the municipality. Pick your city on this page.

How much are commercial impact fees in Putnam County?

Commercial development in unincorporated Putnam County pays $9.22 per square foot in impact fees, plus $13,430.00 in one-time water and sewer connection fees (assuming a 1-inch meter), about $474,530.00 for a 50,000 sq ft building.

Do cities in Putnam County charge their own impact fees?

Yes. Every incorporated city applies its own fee schedule. 4 of 5 cities in Putnam County levy municipal impact or utility fees; each city page shows the full schedule that applies inside its limits.

Can Florida impact fees increase at any time?

No. Section 163.31801, Florida Statutes limits increases to 50% at most, phased in over two to four years, unless the local government makes extraordinary-circumstances findings and approves the increase by at least a two-thirds vote.

Fee amounts on this page are compiled from official published schedules and are provided for planning purposes only. Rates change, and project specifics (unit size, meter size, location within special districts) can alter what applies. Always verify current fees with the jurisdiction and utility before relying on them.

Missing a jurisdiction? Get in touch.

Request coverage for a city or county, report an issue, ask about enterprise access, or inquire about sponsorship opportunities. We typically reply within one business day.

0/1000