Port Royal applies its own fee schedule: municipal fees plus the Beaufort County-levied fees that apply inside city limits. Combined, a new single-family home pays $20,295.43 per unit (rates sourced ). This figure includes amounts that have not been confirmed with the jurisdiction; verify before budgeting. The full breakdown is below.

Port Royal Impact Fees by Project Type

Port Royal: Single-Family Impact Fees

A new single-family home in Port Royal pays $20,295.43 per unit in impact fees (rates sourced October 29, 2026). Of that, Beaufort County-levied fees account for $4,017.00 and municipal or utility fees for $16,278.43.

The largest line items are Sewer Capacity Fee (BJWSA) ($11,583.00), Water Capacity Fee (BJWSA) ($3,440.00) and Water Meter & Box Fee (BJWSA) — 3/4" meter ($950.00).

County Road Impact Fee (Beaufort County), County Library Impact Fee (Beaufort County), and County Parks & Recreation Impact Fee (Beaufort County) are shown at the last published amount but have not been confirmed with the jurisdiction; they are included in the totals here. Verify before budgeting.

Some fees are tiered by unit size or building type; amounts reflect the representative tier noted in the schedule below.

View the Full Port Royal Impact Fee Schedule
Water$4,390.00
  • Water Capacity Fee (BJWSA)
    Beaufort-Jasper Water & Sewer Authority
    Beaufort-Jasper Water and Sewer Authority (BJWSA) charges a one-time water capacity fee per single-family home, effective July 1, 2026 to June 30, 2027, after a phase-in from $2,752 (February 1, 2025) and $3,100 (July 1, 2025). A meter and box assembly fee is charged separately.
    $3,440.00
  • Water Meter & Box Fee (BJWSA) — 3/4" meter
    Beaufort-Jasper Water & Sewer Authority
    BJWSA charges a one-time meter and box assembly fee when it sets the meter, separate from the water and wastewater capacity fees. The fee depends on meter size; a standard home uses the 3/4 inch meter.
    $950.00
Sewer$11,583.00
  • Sewer Capacity Fee (BJWSA)
    Beaufort-Jasper Water & Sewer Authority
    BJWSA charges a one-time wastewater capacity fee per single-family home, effective July 1, 2026 to June 30, 2027, after a phase-in from $9,000 (February 1, 2025) and $10,500 (July 1, 2025).
    $11,583.00
City$305.43
County$4,017.00
  • County Road Impact Fee (Beaufort County)
    North Service Area, 1,751–2,000 sf
    Beaufort County
    Beaufort County road impact fee per dwelling unit, by heated floor area in ten brackets, north service area. The Town of Port Royal's budget records county parks and library impact fee receipts but no county road fee line. Amounts are the 2023 table; the ordinance adjusts them each year by the ENR Construction Cost Index.
    $2,748.00Requires confirmation
  • County Parks & Recreation Impact Fee (Beaufort County)
    North Service Area, 1,751–2,000 sf
    Beaufort County
    Beaufort County parks and recreation impact fee per dwelling unit, by heated floor area in ten brackets, north service area, collected in the Town of Port Royal since 2023. Amounts are the 2023 table; the ordinance adjusts them each year by the ENR Construction Cost Index.
    $868.00Requires confirmation
  • County Library Impact Fee (Beaufort County)
    North Service Area, 1,751–2,000 sf
    Beaufort County
    Beaufort County library impact fee per dwelling unit, by heated floor area in ten brackets, north service area, collected in the Town of Port Royal since 2023. Amounts are the 2023 table; the ordinance adjusts them each year by the ENR Construction Cost Index.
    $401.00Requires confirmation
Total (Port Royal): $20,295.43
Sources last checked Official fee schedules:Beaufort-Jasper Water & Sewer Authority Town of Port Royal Beaufort County
Amounts flagged "Requires confirmation" are the last published figures, included in the totals. Confirm them with the jurisdiction or utility before budgeting.

Where in Beaufort County Are You Building?

Each jurisdiction applies its own fee schedule. Pick yours. = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.

Port Royal: Multifamily Impact Fees

A new multifamily unit in Port Royal pays $13,433.43 per unit in impact fees (rates sourced October 29, 2026). Of that, Beaufort County-levied fees account for $2,220.00 and municipal or utility fees for $11,213.43.

The largest line items are Sewer Capacity Fee (BJWSA, MF) — 200 GPD × $38.61/GPD ($7,722.00), Water Capacity Fee (BJWSA, MF) — 260 GPD × $8.60/GPD ($2,236.00) and Water Meter & Box Fee (BJWSA, MF) — 3/4" meter ($950.00).

County Parks & Recreation Impact Fee (Beaufort County, MF), County Road Impact Fee (Beaufort County, MF), and County Library Impact Fee (Beaufort County, MF) are shown at the last published amount but have not been confirmed with the jurisdiction; they are included in the totals here. Verify before budgeting.

Some fees are tiered by unit size or building type; amounts reflect the representative tier noted in the schedule below.

View the Full Port Royal Impact Fee Schedule
Water$3,186.00
  • Water Capacity Fee (BJWSA, MF) — 260 GPD × $8.60/GPD
    Beaufort-Jasper Water & Sewer Authority
    BJWSA charges multifamily water capacity at $8.60 per gallon per day, sized at 1.3 times the unit's wastewater loading (1 bedroom 150, 2 bedrooms 200, 3 bedrooms 250 gallons per day). The amount shown is a 2-bedroom unit (260 gallons per day), effective July 1, 2026 to June 30, 2027.
    $2,236.00
  • Water Meter & Box Fee (BJWSA, MF) — 3/4" meter
    Beaufort-Jasper Water & Sewer Authority
    BJWSA charges a one-time meter and box assembly fee per meter, separate from the capacity fees. The default shown is the smallest (3/4 inch) meter; the fee rises with meter size, BJWSA quotes meters over 2 inches individually, and a building served by one master meter pays the fee once.
    $950.00
Sewer$7,722.00
  • Sewer Capacity Fee (BJWSA, MF) — 200 GPD × $38.61/GPD
    Beaufort-Jasper Water & Sewer Authority
    BJWSA charges multifamily wastewater capacity at $38.61 per gallon per day, using loadings of 150 (1 bedroom), 200 (2 bedrooms) and 250 (3 bedrooms) gallons per day per unit. The amount shown is a 2-bedroom unit, effective July 1, 2026 to June 30, 2027.
    $7,722.00
City$305.43
County$2,220.00
  • County Road Impact Fee (Beaufort County, MF)
    North Service Area, 1,000 sf or less
    Beaufort County
    Beaufort County road impact fee per dwelling unit, by the unit's heated floor area in ten brackets (the default is a 1,000 sf unit), north service area. The Town of Port Royal's budget records county parks and library impact fee receipts but no county road fee line. Amounts are the 2023 table; the ordinance adjusts them each year by the ENR Construction Cost Index.
    $1,509.00Requires confirmation
  • County Parks & Recreation Impact Fee (Beaufort County, MF)
    North Service Area, 1,000 sf or less
    Beaufort County
    Beaufort County parks and recreation impact fee per dwelling unit, by the unit's heated floor area in ten brackets (the default is a 1,000 sf unit), north service area, collected in the Town of Port Royal since 2023. Amounts are the 2023 table; the ordinance adjusts them each year by the ENR Construction Cost Index.
    $486.00Requires confirmation
  • County Library Impact Fee (Beaufort County, MF)
    North Service Area, 1,000 sf or less
    Beaufort County
    Beaufort County library impact fee per dwelling unit, by the unit's heated floor area in ten brackets (the default is a 1,000 sf unit), north service area, collected in the Town of Port Royal since 2023. Amounts are the 2023 table; the ordinance adjusts them each year by the ENR Construction Cost Index.
    $225.00Requires confirmation
Total (Port Royal): $13,433.43
Sources last checked Official fee schedules:Beaufort-Jasper Water & Sewer Authority Town of Port Royal Beaufort County
Amounts flagged "Requires confirmation" are the last published figures, included in the totals. Confirm them with the jurisdiction or utility before budgeting.

Where in Beaufort County Are You Building?

Each jurisdiction applies its own fee schedule. Pick yours. = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.

Port Royal: Commercial Impact Fees

Commercial development in Port Royal pays $6.21 per square foot in impact fees, plus $1,450.00 in one-time water and sewer connection fees (rates sourced October 29, 2026).

For a 50,000 sq ft building, that comes to at least $311,805.00. The calculator below adjusts to your exact square footage.

The largest line items are Water Meter Fee (BJWSA) — 1" meter ($1,450.00 one-time) and Fire Services Development Impact Fee (Town of Port Royal, Commercial) ($1.69/sq ft).

Water and sewer connection fees assume a 1-inch meter; larger services pay more. See the meter-size tiers in the source schedules.

County Road Impact Fee (Beaufort County, Commercial) is shown at the last published amount but has not been confirmed with the jurisdiction; it is included in the totals here. Verify before budgeting.

Water Capacity Fee (BJWSA) — per gallon per day and Sewer Capacity Fee (BJWSA) — per gallon per day are set by the utility and not published online. Contact the levying jurisdiction or utility to verify before budgeting; they are not included as dollar figures here.

View the Full Port Royal Impact Fee Schedule
Water$1,450.00 one-time
  • Water Meter Fee (BJWSA) — 1" meter
    Beaufort-Jasper Water and Sewer Authority
    BJWSA commercial meter fee for a 1 inch meter with box assembly (fiscal year July 1, 2026 to June 30, 2027). BJWSA prints prices for 3/4 and 1 inch meters; meters larger than 2 inches are quoted on the flow required.
    $1,450.00 one-time
  • Water Capacity Fee (BJWSA) — per gallon per day
    Beaufort-Jasper Water and Sewer Authority
    BJWSA water capacity fee for commercial development, fiscal year July 1, 2026 to June 30, 2027: $8.60 per gallon per day of capacity, with water demand taken as 1.3 times the project's wastewater loading (restaurants: 20 gallons per day per seat). BJWSA publishes no minimum, so the total depends on the project's approved demand and is not added to the estimate. A separate meter fee applies.
    Contact jurisdiction/utility to verify
Sewer$0.00
  • Sewer Capacity Fee (BJWSA) — per gallon per day
    Beaufort-Jasper Water and Sewer Authority
    BJWSA wastewater capacity fee for commercial development, fiscal year July 1, 2026 to June 30, 2027: $38.61 per gallon per day of projected wastewater flow (restaurants: 20 gallons per day per seat). BJWSA publishes no minimum, so the total depends on the project's approved flow and is not added to the estimate. A $100 sewer inspection fee also applies.
    Contact jurisdiction/utility to verify
City$1.69/sq ft
County$4.51/sq ft
  • County Road Impact Fee (Beaufort County, Commercial)
    Beaufort County
    Beaufort County road impact fee for retail and other commercial development in the North service area, per 1,000 sq ft of floor area. The county collects it inside a town only under a participation agreement; the Town of Port Royal's budget records county parks and library impact fee receipts but no county road fee line. Amounts are the county's 2023 schedule, adjusted each year by the ENR Construction Cost Index.
    $4.51/sq ftRequires confirmation
Total (Port Royal): $6.21/sq ft + $1,450.00 one-time (≈ $311,805.00 at 50,000 sq ft)
Sources last checked Official fee schedules:Beaufort-Jasper Water and Sewer Authority Beaufort County
Amounts flagged "Requires confirmation" are the last published figures, included in the totals. Confirm them with the jurisdiction or utility before budgeting.
Water/sewer connection fees assume a 1-inch meter; larger services pay more.

Where in Beaufort County Are You Building?

Each jurisdiction applies its own fee schedule. Pick yours. Totals shown are for a 50,000 sq ft building, including one-time water/sewer fees (assuming a 1-inch meter). * = one-time water/sewer connection charges only; no per-sq-ft impact fee schedule sourced for that jurisdiction. = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.

Port Royal: Industrial Impact Fees

Industrial development in Port Royal pays $2.27 per square foot in impact fees, plus $1,450.00 in one-time water and sewer connection fees (rates sourced October 29, 2026).

For a 50,000 sq ft building, that comes to at least $115,115.50. The calculator below adjusts to your exact square footage.

The largest line items are Water Meter Fee (BJWSA) — 1" meter ($1,450.00 one-time) and Fire Services Development Impact Fee (Town of Port Royal, Industrial) ($1.37/sq ft).

Water and sewer connection fees assume a 1-inch meter; larger services pay more. See the meter-size tiers in the source schedules.

County Road Impact Fee (Beaufort County, Industrial) is shown at the last published amount but has not been confirmed with the jurisdiction; it is included in the totals here. Verify before budgeting.

Water Capacity Fee (BJWSA) — per gallon per day and Sewer Capacity Fee (BJWSA) — per gallon per day are set by the utility and not published online. Contact the levying jurisdiction or utility to verify before budgeting; they are not included as dollar figures here.

View the Full Port Royal Impact Fee Schedule
Water$1,450.00 one-time
  • Water Meter Fee (BJWSA) — 1" meter
    Beaufort-Jasper Water and Sewer Authority
    BJWSA commercial meter fee for a 1 inch meter with box assembly (fiscal year July 1, 2026 to June 30, 2027). BJWSA prints prices for 3/4 and 1 inch meters; meters larger than 2 inches are quoted on the flow required.
    $1,450.00 one-time
  • Water Capacity Fee (BJWSA) — per gallon per day
    Beaufort-Jasper Water and Sewer Authority
    BJWSA water capacity fee for commercial development, fiscal year July 1, 2026 to June 30, 2027: $8.60 per gallon per day of capacity, with water demand taken as 1.3 times the project's wastewater loading (restaurants: 20 gallons per day per seat). BJWSA publishes no minimum, so the total depends on the project's approved demand and is not added to the estimate. A separate meter fee applies.
    Contact jurisdiction/utility to verify
Sewer$0.00
  • Sewer Capacity Fee (BJWSA) — per gallon per day
    Beaufort-Jasper Water and Sewer Authority
    BJWSA wastewater capacity fee for commercial development, fiscal year July 1, 2026 to June 30, 2027: $38.61 per gallon per day of projected wastewater flow (restaurants: 20 gallons per day per seat). BJWSA publishes no minimum, so the total depends on the project's approved flow and is not added to the estimate. A $100 sewer inspection fee also applies.
    Contact jurisdiction/utility to verify
City$1.37/sq ft
County$0.91/sq ft
  • County Road Impact Fee (Beaufort County, Industrial)
    Beaufort County
    Beaufort County road impact fee for industrial development in the North service area, per 1,000 sq ft of floor area. The county collects it inside a town only under a participation agreement; the Town of Port Royal's budget records county parks and library impact fee receipts but no county road fee line. Amounts are the county's 2023 schedule, adjusted each year by the ENR Construction Cost Index.
    $0.91/sq ftRequires confirmation
Total (Port Royal): $2.27/sq ft + $1,450.00 one-time (≈ $115,115.50 at 50,000 sq ft)
Sources last checked Official fee schedules:Beaufort-Jasper Water and Sewer Authority Beaufort County
Amounts flagged "Requires confirmation" are the last published figures, included in the totals. Confirm them with the jurisdiction or utility before budgeting.
Water/sewer connection fees assume a 1-inch meter; larger services pay more.

Where in Beaufort County Are You Building?

Each jurisdiction applies its own fee schedule. Pick yours. Totals shown are for a 50,000 sq ft building, including one-time water/sewer fees (assuming a 1-inch meter). * = one-time water/sewer connection charges only; no per-sq-ft impact fee schedule sourced for that jurisdiction. = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.

Port Royal: Office Impact Fees

Office development in Port Royal pays $4.70 per square foot in impact fees, plus $1,450.00 in one-time water and sewer connection fees (rates sourced October 29, 2026).

For a 25,000 sq ft building, that comes to at least $118,832.50. The calculator below adjusts to your exact square footage.

The largest line items are Water Meter Fee (BJWSA) — 1" meter ($1,450.00 one-time) and Fire Services Development Impact Fee (Town of Port Royal, Office) ($2.45/sq ft).

Water and sewer connection fees assume a 1-inch meter; larger services pay more. See the meter-size tiers in the source schedules.

County Road Impact Fee (Beaufort County, Office) is shown at the last published amount but has not been confirmed with the jurisdiction; it is included in the totals here. Verify before budgeting.

Water Capacity Fee (BJWSA) — per gallon per day and Sewer Capacity Fee (BJWSA) — per gallon per day are set by the utility and not published online. Contact the levying jurisdiction or utility to verify before budgeting; they are not included as dollar figures here.

View the Full Port Royal Impact Fee Schedule
Water$1,450.00 one-time
  • Water Meter Fee (BJWSA) — 1" meter
    Beaufort-Jasper Water and Sewer Authority
    BJWSA commercial meter fee for a 1 inch meter with box assembly (fiscal year July 1, 2026 to June 30, 2027). BJWSA prints prices for 3/4 and 1 inch meters; meters larger than 2 inches are quoted on the flow required.
    $1,450.00 one-time
  • Water Capacity Fee (BJWSA) — per gallon per day
    Beaufort-Jasper Water and Sewer Authority
    BJWSA water capacity fee for commercial development, fiscal year July 1, 2026 to June 30, 2027: $8.60 per gallon per day of capacity, with water demand taken as 1.3 times the project's wastewater loading (restaurants: 20 gallons per day per seat). BJWSA publishes no minimum, so the total depends on the project's approved demand and is not added to the estimate. A separate meter fee applies.
    Contact jurisdiction/utility to verify
Sewer$0.00
  • Sewer Capacity Fee (BJWSA) — per gallon per day
    Beaufort-Jasper Water and Sewer Authority
    BJWSA wastewater capacity fee for commercial development, fiscal year July 1, 2026 to June 30, 2027: $38.61 per gallon per day of projected wastewater flow (restaurants: 20 gallons per day per seat). BJWSA publishes no minimum, so the total depends on the project's approved flow and is not added to the estimate. A $100 sewer inspection fee also applies.
    Contact jurisdiction/utility to verify
City$2.45/sq ft
County$2.24/sq ft
  • County Road Impact Fee (Beaufort County, Office)
    Beaufort County
    Beaufort County road impact fee for office and service development in the North service area, per 1,000 sq ft of floor area. The county collects it inside a town only under a participation agreement; the Town of Port Royal's budget records county parks and library impact fee receipts but no county road fee line. Amounts are the county's 2023 schedule, adjusted each year by the ENR Construction Cost Index.
    $2.24/sq ftRequires confirmation
Total (Port Royal): $4.70/sq ft + $1,450.00 one-time (≈ $118,832.50 at 25,000 sq ft)
Sources last checked Official fee schedules:Beaufort-Jasper Water and Sewer Authority Beaufort County
Amounts flagged "Requires confirmation" are the last published figures, included in the totals. Confirm them with the jurisdiction or utility before budgeting.
Water/sewer connection fees assume a 1-inch meter; larger services pay more.

Where in Beaufort County Are You Building?

Each jurisdiction applies its own fee schedule. Pick yours. Totals shown are for a 25,000 sq ft building, including one-time water/sewer fees (assuming a 1-inch meter). * = one-time water/sewer connection charges only; no per-sq-ft impact fee schedule sourced for that jurisdiction. = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.

Port Royal Impact Fee Calculator

Estimate impact fees for your project. Set to single-family. Drop a pin or search an address for site-specific fees.

Location

Select a location to begin

Once you select an address or drop a pin, we'll identify the responsible city and county and generate a fee breakdown.

Water & Sewer
Transportation
Parks
Schools
Fire & Police
General

How Development Impact Fees Work in South Carolina

South Carolina counties and municipalities assess development impact fees under the Development Impact Fee Act (S.C. Code 6-1-910 et seq.). Only a government with a comprehensive plan (or a capital improvements plan that substantially complies with the Act) may impose one, by an ordinance approved by a positive majority, and before charging residential units it must report how the fee affects the availability of affordable housing.

Fees may fund only the public facilities the Act lists: water and wastewater, solid waste, roads and bridges, stormwater and flood control, public safety (law enforcement, fire, emergency medical and street lighting), capital equipment and vehicles of at least $100,000 a unit, parks, libraries and recreation, and, since 2016, K-12 public school facilities. A fee may not exceed the development's proportionate share of the cost, after credits for land, money or improvements the developer contributes and for other funding sources.

Fee revenue is kept in interest-bearing accounts by category and service area and spent only on that category in that area. A fee not spent within three years of the date it was scheduled to be spent, or paid on a building permit that is denied, is refunded with its share of interest. The fee is due no earlier than the building permit (or the development permit where no building permit is needed).

Water and sewer charges usually come from the utility that serves a parcel: the Act's definition of an impact fee excludes connection or hookup charges, and a water or wastewater provider meeting the conditions of 6-1-1080 sets its impact fees outside the Act. That is why totals differ between a city, its neighbors and the unincorporated county around it.

Brush up on impact fee basics before you budget your next project.

Summary current as of November 2026. This is an editorial summary, not legal advice; see the official statute text and our terms of use.

Port Royal Impact Fee FAQs

What are the total impact fees for a single-family home in Port Royal, South Carolina?

A new single-family home in Port Royal pays $20,295.43 per unit in combined impact fees (rates sourced October 29, 2026). This figure includes amounts that have not been confirmed with the jurisdiction; verify before budgeting.

How much are commercial impact fees in Port Royal?

Commercial development in Port Royal pays $6.21 per square foot in impact fees, plus $1,450.00 in one-time water and sewer connection fees (assuming a 1-inch meter), at least $311,805.00 for a 50,000 sq ft building. This figure includes amounts that have not been confirmed and excludes fees with no published standard amount, so the full cost may be higher; verify before budgeting.

Does Port Royal charge its own impact fees?

Yes. Port Royal levies its own municipal impact or utility fees, and county-levied fees also apply inside city limits. The schedule on this page shows every fee that applies to development in Port Royal, with the combined total.

Can a South Carolina impact fee be raised after it is adopted?

Only through a new ordinance. Under S.C. Code 6-1-940 the government is bound by the amount its impact fee ordinance sets for each unit of development and may not charge higher or additional impact fees for the same purpose unless the project's service units increase or its scope changes, and then only for the added share. Water and sewer capacity and tap fees set by utilities follow each provider's own rate process.

Fee amounts on this page are compiled from official published schedules and are provided for planning purposes only. Rates change, and project specifics (unit size, meter size, location within special districts) can alter what applies. Always verify current fees with the jurisdiction and utility before relying on them.

Compare unincorporated rates and every other city on the Beaufort County impact fees page.

Missing a jurisdiction? Get in touch.

Request coverage for a city or county, report an issue, ask about enterprise access, or inquire about sponsorship opportunities. We typically reply within one business day.

0/1000