Chester County Impact Fees by Project Type
Where in Chester County Are You Building?
Each jurisdiction applies its own fee schedule. Pick yours. = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.
Unincorporated Chester County: Single-Family Impact Fees
A new single-family home in unincorporated Chester County pays $10,987.56 per unit in impact fees (rates sourced November 4, 2026). Of that, Chester County-levied fees account for $7,567.56 and municipal or utility fees for $3,420.00.
The largest line items are Sewer Capital Recovery Fee (Chester County Wastewater Recovery) — LR Basin, 3/4" meter ($4,000.00), Sewer Tap Fee (Chester County Wastewater Recovery) ($3,567.56) and Water Capital Recovery Fee (Chester Metropolitan District) — 3/4" meter ($1,770.00).
Some fees are tiered by unit size or building type; amounts reflect the representative tier noted in the schedule below.
View the Full Chester County Impact Fee Schedule
- Water Capital Recovery Fee (Chester Metropolitan District) — 3/4" meter$1,770.00Chester Metropolitan DistrictEffective July 1, 2026. One-time water capital recovery fee by service size: 3/4-inch $1,770, 1-inch $2,955, 2-inch $9,431; meters 3 inches and larger pay peak water demand (gallons per day) x $5.90. A standard home uses a 3/4-inch service. Chester Metropolitan District serves the developed corridors of the unincorporated county; rural parcels may be on private wells. Separate from the water tap fee.
- Water Tap Fee (Chester Metropolitan District)$1,650.00Chester Metropolitan DistrictEffective July 1, 2026. $1,650 for a 1-inch-or-smaller simple installation; other installations are billed at cost. Chester Metropolitan District serves the developed corridors of the unincorporated county; rural parcels may be on private wells. Separate one-time charge from the water capital recovery fee.
- Sewer Capital Recovery Fee (Chester County Wastewater Recovery) — LR Basin, 3/4" meter$4,000.00Chester County Wastewater RecoveryEffective July 1, 2026. One-time sewer capital recovery fee by meter size, shown at the higher of Chester County Wastewater Recovery's two rate basins (LR); the RC/SR basin is lower and basin assignment depends on the parcel. A standard home uses a 3/4-inch meter. Meters larger than 2 inches pay per gallon per day ($16.00 LR, $7.14 RC/SR). Much of the rural county is on septic. Separate from the sewer tap fee.
- Sewer Tap Fee (Chester County Wastewater Recovery)$3,567.56Chester County Wastewater RecoveryEffective July 1, 2026. $3,567.56 is the minimum sewer tap fee where Chester County Wastewater Recovery sewer is available; much of the rural county is on septic. Separate one-time charge from the sewer capital recovery fee.
- Municipal Impact Fee (Not Applicable - Unincorporated)$0.00N/A - Unincorporated Chester CountyNo municipal impact fee applies in unincorporated Chester County.
- County Development Impact Fee (Chester County)$0.00Chester CountyChester County does not charge a development impact fee on new construction in the unincorporated county.
Where in Chester County Are You Building?
Each jurisdiction applies its own fee schedule. Pick yours. = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.
Unincorporated Chester County: Multifamily Impact Fees
A new multifamily unit in unincorporated Chester County pays $10,987.56 per unit in impact fees (rates sourced November 4, 2026). Of that, Chester County-levied fees account for $7,567.56 and municipal or utility fees for $3,420.00.
Sewer Tap Fee (Chester County Wastewater Recovery, MF), Sewer Capital Recovery Fee (Chester County Wastewater Recovery, MF) — LR Basin, 3/4" meter, Water Capital Recovery Fee (Chester Metropolitan District, MF) — 3/4" meter, and Water Tap Fee (Chester Metropolitan District, MF) are shown at the last published amount but have not been confirmed with the jurisdiction; they are included in the totals here. Verify before budgeting.
Some fees are tiered by unit size or building type; amounts reflect the representative tier noted in the schedule below.
View the Full Chester County Impact Fee Schedule
- Water Capital Recovery Fee (Chester Metropolitan District, MF) — 3/4" meter$1,770.00Requires confirmationChester Metropolitan DistrictEffective July 1, 2026. One-time water capital recovery fee by service size: 3/4-inch $1,770, 1-inch $2,955, 2-inch $9,431; meters 3 inches and larger pay peak water demand (gallons per day) x $5.90. Charged per service connection: a building on one connection pays once at its meter size. Rural parcels may be on private wells. Separate from the water tap fee.
- Water Tap Fee (Chester Metropolitan District, MF)$1,650.00Requires confirmationChester Metropolitan DistrictEffective July 1, 2026. $1,650 for a 1-inch-or-smaller simple installation; other installations are billed at cost. Charged per service connection: a building on one connection pays once. Separate from the water capital recovery fee.
- Sewer Capital Recovery Fee (Chester County Wastewater Recovery, MF) — LR Basin, 3/4" meter$4,000.00Requires confirmationChester County Wastewater RecoveryEffective July 1, 2026. One-time sewer capital recovery fee by meter size, shown at the higher of Chester County Wastewater Recovery's two rate basins (LR); the RC/SR basin is lower and basin assignment depends on the parcel. Charged per meter: an individually metered unit pays the 3/4-inch fee, while a building on one master meter pays once at its meter size (larger than 2 inches: $16.00 LR or $7.14 RC/SR per gallon per day). Separate from the sewer tap fee.
- Sewer Tap Fee (Chester County Wastewater Recovery, MF)$3,567.56Requires confirmationChester County Wastewater RecoveryEffective July 1, 2026. $3,567.56 is the minimum sewer tap fee where Chester County Wastewater Recovery sewer is available. Charged per sewer connection: a building on one connection pays once. Separate from the sewer capital recovery fee.
- Municipal Impact Fee (Not Applicable - Unincorporated, MF)$0.00N/A - Unincorporated Chester CountyNo municipal impact fee applies in unincorporated Chester County.
- County Development Impact Fee (Chester County, MF)$0.00Chester CountyChester County does not charge a development impact fee on new construction in the unincorporated county.
Where in Chester County Are You Building?
Each jurisdiction applies its own fee schedule. Pick yours. Totals shown are for a 50,000 sq ft building, including one-time water/sewer fees (assuming a 1-inch meter). * = one-time water/sewer connection charges only; no per-sq-ft impact fee schedule sourced for that jurisdiction. = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.
Unincorporated Chester County: Commercial Impact Fees
Commercial development in unincorporated Chester County pays no per-square-foot impact fees, but owes $14,852.56 in one-time water and sewer connection fees (rates sourced November 4, 2026).
For a 50,000 sq ft building, that comes to about $14,852.56. The calculator below adjusts to your exact square footage.
The largest line items are Sewer Capital Recovery Fee (Chester County Wastewater Recovery) — LR Basin, 1" meter ($6,680.00 one-time), Sewer Tap Fee (Chester County Wastewater Recovery) ($3,567.56 one-time) and Water Capital Recovery Fee (Chester Metropolitan District) — 1" meter ($2,955.00 one-time).
Water and sewer connection fees assume a 1-inch meter; larger services pay more. See the meter-size tiers in the source schedules.
View the Full Chester County Impact Fee Schedule
- Water Capital Recovery Fee (Chester Metropolitan District) — 1" meter$2,955.00 one-timeChester Metropolitan DistrictEffective July 1, 2026. One-time water capital recovery fee by meter size: 3/4 inch $1,770, 1 inch $2,955, 2 inch $9,431; meters 3 to 10 inches are charged peak water demand (gallons/day) x $5.90. Separate from the water tap fee.
- Water Tap Fee (Chester Metropolitan District)$1,650.00 one-timeEffective July 1, 2026. $1,650 for a 1-inch-or-smaller simple installation; larger connections billed at cost of installation. Chester Metropolitan District serves the served areas of the unincorporated county; rural areas may be on private wells. Separate one-time charge from the water capital recovery fee.
- Sewer Capital Recovery Fee (Chester County Wastewater Recovery) — LR Basin, 1" meter$6,680.00 one-timeEffective July 1, 2026. Highest of 2 rate basins (RC/SR and LR); basin assignment is parcel-specific. Meters larger than 2 inches billed per gallon/day ($7.14 RC/SR, $16.00 LR). Separate from the sewer tap fee.
- Sewer Tap Fee (Chester County Wastewater Recovery)$3,567.56 one-timeEffective July 1, 2026. $3,567.56 minimum tap fee. Chester County Wastewater Recovery serves the sewered areas of the unincorporated county; much of the rural county is on septic. Separate one-time charge from the sewer capital recovery fee.
- City Development Impact Fee (Unincorporated Chester County, Commercial)$0.00Unincorporated Chester County has no municipal government, so no city impact fee applies.
- County Development Impact Fee (Chester County, Commercial) — Unincorporated$0.00Chester County levies no development impact fee on new construction.
Where in Chester County Are You Building?
Each jurisdiction applies its own fee schedule. Pick yours. Totals shown are for a 50,000 sq ft building, including one-time water/sewer fees (assuming a 1-inch meter). * = one-time water/sewer connection charges only; no per-sq-ft impact fee schedule sourced for that jurisdiction. = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.
Unincorporated Chester County: Industrial Impact Fees
Industrial development in unincorporated Chester County pays no per-square-foot impact fees, but owes $14,852.56 in one-time water and sewer connection fees (rates sourced November 4, 2026).
For a 50,000 sq ft building, that comes to about $14,852.56. The calculator below adjusts to your exact square footage.
The largest line items are Sewer Capital Recovery Fee (Chester County Wastewater Recovery) — LR Basin, 1" meter ($6,680.00 one-time), Sewer Tap Fee (Chester County Wastewater Recovery) ($3,567.56 one-time) and Water Capital Recovery Fee (Chester Metropolitan District) — 1" meter ($2,955.00 one-time).
Water and sewer connection fees assume a 1-inch meter; larger services pay more. See the meter-size tiers in the source schedules.
View the Full Chester County Impact Fee Schedule
- Water Capital Recovery Fee (Chester Metropolitan District) — 1" meter$2,955.00 one-timeChester Metropolitan DistrictEffective July 1, 2026. One-time water capital recovery fee by meter size: 3/4 inch $1,770, 1 inch $2,955, 2 inch $9,431; meters 3 to 10 inches are charged peak water demand (gallons/day) x $5.90. Separate from the water tap fee.
- Water Tap Fee (Chester Metropolitan District)$1,650.00 one-timeEffective July 1, 2026. $1,650 for a 1-inch-or-smaller simple installation; larger connections billed at cost of installation. Chester Metropolitan District serves the served areas of the unincorporated county; rural areas may be on private wells. Separate one-time charge from the water capital recovery fee.
- Sewer Capital Recovery Fee (Chester County Wastewater Recovery) — LR Basin, 1" meter$6,680.00 one-timeEffective July 1, 2026. Highest of 2 rate basins (RC/SR and LR); basin assignment is parcel-specific. Meters larger than 2 inches billed per gallon/day ($7.14 RC/SR, $16.00 LR). Separate from the sewer tap fee.
- Sewer Tap Fee (Chester County Wastewater Recovery)$3,567.56 one-timeEffective July 1, 2026. $3,567.56 minimum tap fee. Chester County Wastewater Recovery serves the sewered areas of the unincorporated county; much of the rural county is on septic. Separate one-time charge from the sewer capital recovery fee.
- City Development Impact Fee (Unincorporated Chester County, Industrial)$0.00Unincorporated Chester County has no municipal government, so no city impact fee applies.
- County Development Impact Fee (Chester County, Industrial) — Unincorporated$0.00Chester County levies no development impact fee on new construction.
Where in Chester County Are You Building?
Each jurisdiction applies its own fee schedule. Pick yours. Totals shown are for a 25,000 sq ft building, including one-time water/sewer fees (assuming a 1-inch meter). * = one-time water/sewer connection charges only; no per-sq-ft impact fee schedule sourced for that jurisdiction. = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.
Unincorporated Chester County: Office Impact Fees
Office development in unincorporated Chester County pays no per-square-foot impact fees, but owes $14,852.56 in one-time water and sewer connection fees (rates sourced November 4, 2026).
For a 25,000 sq ft building, that comes to about $14,852.56. The calculator below adjusts to your exact square footage.
The largest line items are Sewer Capital Recovery Fee (Chester County Wastewater Recovery) — LR Basin, 1" meter ($6,680.00 one-time), Sewer Tap Fee (Chester County Wastewater Recovery) ($3,567.56 one-time) and Water Capital Recovery Fee (Chester Metropolitan District) — 1" meter ($2,955.00 one-time).
Water and sewer connection fees assume a 1-inch meter; larger services pay more. See the meter-size tiers in the source schedules.
View the Full Chester County Impact Fee Schedule
- Water Capital Recovery Fee (Chester Metropolitan District) — 1" meter$2,955.00 one-timeChester Metropolitan DistrictEffective July 1, 2026. One-time water capital recovery fee by meter size: 3/4 inch $1,770, 1 inch $2,955, 2 inch $9,431; meters 3 to 10 inches are charged peak water demand (gallons/day) x $5.90. Separate from the water tap fee.
- Water Tap Fee (Chester Metropolitan District)$1,650.00 one-timeEffective July 1, 2026. $1,650 for a 1-inch-or-smaller simple installation; larger connections billed at cost of installation. Chester Metropolitan District serves the served areas of the unincorporated county; rural areas may be on private wells. Separate one-time charge from the water capital recovery fee.
- Sewer Capital Recovery Fee (Chester County Wastewater Recovery) — LR Basin, 1" meter$6,680.00 one-timeEffective July 1, 2026. Highest of 2 rate basins (RC/SR and LR); basin assignment is parcel-specific. Meters larger than 2 inches billed per gallon/day ($7.14 RC/SR, $16.00 LR). Separate from the sewer tap fee.
- Sewer Tap Fee (Chester County Wastewater Recovery)$3,567.56 one-timeEffective July 1, 2026. $3,567.56 minimum tap fee. Chester County Wastewater Recovery serves the sewered areas of the unincorporated county; much of the rural county is on septic. Separate one-time charge from the sewer capital recovery fee.
- City Development Impact Fee (Unincorporated Chester County, Office)$0.00Unincorporated Chester County has no municipal government, so no city impact fee applies.
- County Development Impact Fee (Chester County, Office) — Unincorporated$0.00Chester County levies no development impact fee on new construction.
Chester County Impact Fee Calculator
Estimate impact fees for your project. Set to single-family. Drop a pin or search an address for site-specific fees.
Location
Select a location to begin
Once you select an address or drop a pin, we'll identify the responsible city and county and generate a fee breakdown.
How Development Impact Fees Work in South Carolina
South Carolina counties and municipalities assess development impact fees under the Development Impact Fee Act (S.C. Code 6-1-910 et seq.). Only a government with a comprehensive plan (or a capital improvements plan that substantially complies with the Act) may impose one, by an ordinance approved by a positive majority, and before charging residential units it must report how the fee affects the availability of affordable housing.
Fees may fund only the public facilities the Act lists: water and wastewater, solid waste, roads and bridges, stormwater and flood control, public safety (law enforcement, fire, emergency medical and street lighting), capital equipment and vehicles of at least $100,000 a unit, parks, libraries and recreation, and, since 2016, K-12 public school facilities. A fee may not exceed the development's proportionate share of the cost, after credits for land, money or improvements the developer contributes and for other funding sources.
Fee revenue is kept in interest-bearing accounts by category and service area and spent only on that category in that area. A fee not spent within three years of the date it was scheduled to be spent, or paid on a building permit that is denied, is refunded with its share of interest. The fee is due no earlier than the building permit (or the development permit where no building permit is needed).
Water and sewer charges usually come from the utility that serves a parcel: the Act's definition of an impact fee excludes connection or hookup charges, and a water or wastewater provider meeting the conditions of 6-1-1080 sets its impact fees outside the Act. That is why totals differ between a city, its neighbors and the unincorporated county around it.
If you're still asking what are impact fees, start with our guide to the definition, common categories, and legal basis.
Summary current as of November 2026. This is an editorial summary, not legal advice; see the official statute text and our terms of use.
Chester County Impact Fee FAQs
What are single-family impact fees in Chester County, South Carolina?
A new single-family home in unincorporated Chester County pays $10,987.56 per unit in impact fees (rates sourced November 4, 2026). Inside city limits, fees are set by each city's own schedule and may be completely different. See the city pages for their rates.
How much are multifamily impact fees in Chester County?
Multifamily development in unincorporated Chester County pays $10,987.56 per unit in impact fees (rates sourced November 4, 2026). This figure includes amounts that have not been confirmed with the jurisdiction; verify before budgeting. Rates inside city limits depend on the municipality. Pick your city on this page.
How much are commercial impact fees in Chester County?
Commercial development in unincorporated Chester County pays no per-square-foot impact fees, but owes $14,852.56 in one-time water and sewer connection fees (assuming a 1-inch meter).
Do cities in Chester County charge their own impact fees?
Yes. Every incorporated city applies its own fee schedule. 5 of 5 cities in Chester County levy municipal impact or utility fees; each city page shows the full schedule that applies inside its limits.
Can a South Carolina impact fee be raised after it is adopted?
Only through a new ordinance. Under S.C. Code 6-1-940 the government is bound by the amount its impact fee ordinance sets for each unit of development and may not charge higher or additional impact fees for the same purpose unless the project's service units increase or its scope changes, and then only for the added share. Water and sewer capacity and tap fees set by utilities follow each provider's own rate process.
Fee amounts on this page are compiled from official published schedules and are provided for planning purposes only. Rates change, and project specifics (unit size, meter size, location within special districts) can alter what applies. Always verify current fees with the jurisdiction and utility before relying on them.