IMPACTFEES.ORG

Collier County, Florida Impact Fees

Impact fees in Collier County depend on where you build. This page details the rates for unincorporated Collier County: $35,931.97 per single-family unit as of . Inside city limits, each city applies its own schedule and fees may be completely different. Pick your city below.

Collier County impact fees by project type

Where in Collier County are you building?

Each jurisdiction applies its own fee schedule. Pick yours. = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.

Unincorporated Collier County: Single-Family Impact Fees

A new single-family home in unincorporated Collier County pays $35,931.97 per unit in impact fees (rates sourced August 13, 2026). All of it is levied by Collier County.

The largest line items are County Impact Fees (Collier County, SFR — Total excl. Fire & Water/Sewer) ($23,763.97), Water Impact Fee (Collier County Water-Sewer District, SFR) ($5,441.00) and Wastewater (Sewer) Impact Fee (Collier County Water-Sewer District, SFR) ($4,847.00).

Some fees are tiered by unit size or building type; amounts reflect the representative tier noted in the schedule below.

View the full Collier County impact fee schedule
Water$5,441.00
  • Water Impact Fee (Collier County Water-Sewer District, SFR)
    Collier County Water-Sewer District
    Collier County Water-Sewer District water impact fee for a single-family detached home, effective February 1, 2026: 1.0 ERU = $5,441. Applies to individually metered units up to 4,999 sq ft living space with no more than five toilets; master-metered buildings use a separate rate table.
    $5,441.00
Sewer$4,847.00
  • Wastewater (Sewer) Impact Fee (Collier County Water-Sewer District, SFR)
    Collier County Water-Sewer District
    Collier County Water-Sewer District wastewater (sewer) impact fee for a single-family detached home, effective February 1, 2026: 1.0 ERU = $4,847. Applies to individually metered units up to 4,999 sq ft living space with no more than five toilets; master-metered buildings use a separate rate table.
    $4,847.00
City$0.00
County$25,643.97
  • County Impact Fees (Collier County, SFR — Total excl. Fire & Water/Sewer)
    Single Family Detached <4,000 sf
    Collier County
    Collier County impact fees for a single-family detached home under 4,000 sq ft living area, effective May 1, 2026 (Phase 2): $23,763.97 total, combining EMS, jail, libraries, roads, schools, government buildings, law enforcement, community parks and regional parks. Excludes fire (charged separately by fire district) and county water/sewer (separate records). Homes 4,000 sq ft and larger pay $26,535.95. A Parks & Recreation impact-fee update takes effect January 2, 2027.
    $23,763.97
  • Fire Impact Fee (Collier County, SFR) — $0.94/sf × 2,000 sf
    Immokalee Fire District
    Collier County Fire Districts
    Collier County fire impact fee, effective May 1, 2026, charged per square foot under roof at a rate set by fire district. This is the highest of four districts — Immokalee Fire at $0.94/sq ft; the amount shown is for a 2,000 sq ft home ($1,880). Greater Naples is $0.60/sq ft and Ochopee $0.433/sq ft (separate records); North Collier charges a flat $476 per unit instead (separate record). The fee scales with actual under-roof area, which includes garage and lanai.
    $1,880.00
Total (unincorporated Collier County): $35,931.97
Sources last checked Official fee schedules:Collier County Water-Sewer District N/A Collier County Collier County Fire Districts

Where in Collier County are you building?

Each jurisdiction applies its own fee schedule. Pick yours. = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.

Unincorporated Collier County: Multifamily Impact Fees

A new multifamily unit in unincorporated Collier County pays $18,547.95 per unit in impact fees (rates sourced August 13, 2026). All of it is levied by Collier County.

The largest line items are Impact Fees - Multifamily Mid-Rise (4-10 floors) - Total excl. Fire ($10,716.95), Water Impact Fee - Multifamily (0.67 ERU, 751-1,500 sf) ($3,644.00) and Wastewater Impact Fee - Multifamily (0.67 ERU, 751-1,500 sf) ($3,247.00).

Some fees are tiered by unit size or building type; amounts reflect the representative tier noted in the schedule below.

View the full Collier County impact fee schedule
Water$3,644.00
  • Water Impact Fee - Multifamily (0.67 ERU, 751-1,500 sf)
    0.67 ERU (1-2BR)
    Collier County Water-Sewer District
    Collier County Water-Sewer District water impact fee for a multifamily unit, effective February 1, 2026. Individually metered units are tiered by living area: 0–750 sf = 0.33 ERU ($1,795), 751–1,500 sf = 0.67 ERU ($3,644, shown), 1,501+ sf = 1.0 ERU ($5,441). Master-metered buildings use a separate rate table.
    $3,644.00
Sewer$3,247.00
  • Wastewater Impact Fee - Multifamily (0.67 ERU, 751-1,500 sf)
    0.67 ERU (1-2BR)
    Collier County Water-Sewer District
    Collier County Water-Sewer District wastewater (sewer) impact fee for a multifamily unit, effective February 1, 2026. Individually metered units are tiered by living area: 0–750 sf = 0.33 ERU ($1,599), 751–1,500 sf = 0.67 ERU ($3,247, shown), 1,501+ sf = 1.0 ERU ($4,847). Master-metered buildings use a separate rate table.
    $3,247.00
City$0.00
County$11,656.95
  • Impact Fees - Multifamily Mid-Rise (4-10 floors) - Total excl. Fire
    Collier County
    Collier County impact fees for a mid-rise (4–10 floor) multifamily unit, effective May 1, 2026 (Phase 2): $10,716.95 per unit, combining EMS, jail, libraries, roads, schools, government buildings, law enforcement, community parks and regional parks. Excludes fire and county water/sewer (separate records). Low-rise (1–3 floors) units pay $12,547.95 and high-rise (>10 floors) $10,189.95. A Parks & Recreation impact-fee update takes effect January 2, 2027.
    $10,716.95
  • Fire Impact Fee (Collier County, MF) — $0.94/sf × 1,000 sf
    Immokalee Fire District
    Collier County Fire Districts
    Collier County fire impact fee for multifamily, effective May 1, 2026, charged per square foot under roof by fire district. This is the highest of four districts — Immokalee Fire at $0.94/sq ft; the amount shown is for a 1,000 sq ft unit ($940). Greater Naples is $0.60/sq ft and Ochopee $0.433/sq ft (separate records); North Collier charges a flat $357 per unit instead (separate record). The fee scales with actual under-roof area.
    $940.00
Total (unincorporated Collier County): $18,547.95
Sources last checked Official fee schedules:Collier County Water-Sewer District N/A Collier County Collier County Fire Districts

Where in Collier County are you building?

Each jurisdiction applies its own fee schedule. Pick yours. Totals shown are for a 50,000 sq ft building, including one-time water/sewer fees (assuming a 1-inch meter). = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.

Unincorporated Collier County: Commercial Impact Fees

Commercial development in unincorporated Collier County pays $17.93 per square foot in impact fees, plus $17,180.00 in one-time water and sewer connection fees (rates sourced August 13, 2026).

For a 50,000 sq ft building, that comes to about $913,680.00. The calculator below adjusts to your exact square footage.

The largest line items are Water Impact Fee (Collier County Water-Sewer District) — 1" meter ($9,085.00 one-time), Wastewater (Sewer) Impact Fee (Collier County Water-Sewer District) — 1" meter ($8,095.00 one-time) and County Impact Fees (Collier County, Commercial) ($16.87/sq ft).

Water and sewer connection fees assume a 1-inch meter; larger services pay more. See the meter-size tiers in the source schedules.

View the full Collier County impact fee schedule
Water$9,085.00 one-time
  • Water Impact Fee (Collier County Water-Sewer District) — 1" meter
    Collier County Water-Sewer District
    Collier County Water-Sewer District water impact fee by meter size, effective December 1, 2025. Meter size is determined by total fixture value per the Florida Plumbing Code; the County installs meters 2 inches or smaller. Meter and cross-connection-control-device installation charges are separate. For change-of-use, charged only if the meter is upsized.
    $9,085.00 one-time
Sewer$8,095.00 one-time
  • Wastewater (Sewer) Impact Fee (Collier County Water-Sewer District) — 1" meter
    Collier County Water-Sewer District
    Collier County Water-Sewer District wastewater impact fee by meter size, effective December 1, 2025. Meter size is determined by total fixture value per the Florida Plumbing Code; the County installs meters 2 inches or smaller. Meter and cross-connection-control-device installation charges are separate. For change-of-use, charged only if the meter is upsized.
    $8,095.00 one-time
City$0.00
County$17.93/sq ft
  • County Impact Fees (Collier County, Commercial)
    Retail 40,001-150,000 sq ft
    Collier County
    Effective May 1, 2026 (Phase 2 rates), per square foot of building area. Collier County impact fee covering EMS, Government Buildings, Jail, Law Enforcement and Road; Library, Parks and School are not assessed on nonresidential. Applies to retail 40,001–150,000 sq ft. Water, wastewater and fire impact fees are billed separately.
    $16.87/sq ft
  • Fire Impact Fee (Collier County Fire Districts, Commercial)
    North Collier Fire District
    Fire impact fee, per square foot under roof, effective May 1, 2026. Rate varies by fire district; this record shows the highest of Collier County's four fire districts — North Collier $1.06. The others are Greater Naples $0.433, Immokalee $0.60 and Ochopee $0.68. The applicable district depends on parcel location.
    $1.06/sq ft
Total (unincorporated Collier County): $17.93/sq ft + $17,180.00 one-time (≈ $913,680.00 at 50,000 sq ft)
Sources last checked Official fee schedules:Collier County Water-Sewer District N/A Collier County
Water/sewer connection fees assume a 1-inch meter; larger services pay more.

Where in Collier County are you building?

Each jurisdiction applies its own fee schedule. Pick yours. Totals shown are for a 50,000 sq ft building, including one-time water/sewer fees (assuming a 1-inch meter). = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.

Unincorporated Collier County: Industrial Impact Fees

Industrial development in unincorporated Collier County pays $5.03 per square foot in impact fees, plus $17,180.00 in one-time water and sewer connection fees (rates sourced August 13, 2026).

For a 50,000 sq ft building, that comes to about $268,680.00. The calculator below adjusts to your exact square footage.

The largest line items are Water Impact Fee (Collier County Water-Sewer District) — 1" meter ($9,085.00 one-time), Wastewater (Sewer) Impact Fee (Collier County Water-Sewer District) — 1" meter ($8,095.00 one-time) and County Impact Fees (Collier County, Industrial) ($3.97/sq ft).

Water and sewer connection fees assume a 1-inch meter; larger services pay more. See the meter-size tiers in the source schedules.

View the full Collier County impact fee schedule
Water$9,085.00 one-time
  • Water Impact Fee (Collier County Water-Sewer District) — 1" meter
    Collier County Water-Sewer District
    Collier County Water-Sewer District water impact fee by meter size, effective December 1, 2025. Meter size is determined by total fixture value per the Florida Plumbing Code; the County installs meters 2 inches or smaller. Meter and cross-connection-control-device installation charges are separate. For change-of-use, charged only if the meter is upsized.
    $9,085.00 one-time
Sewer$8,095.00 one-time
  • Wastewater (Sewer) Impact Fee (Collier County Water-Sewer District) — 1" meter
    Collier County Water-Sewer District
    Collier County Water-Sewer District wastewater impact fee by meter size, effective December 1, 2025. Meter size is determined by total fixture value per the Florida Plumbing Code; the County installs meters 2 inches or smaller. Meter and cross-connection-control-device installation charges are separate. For change-of-use, charged only if the meter is upsized.
    $8,095.00 one-time
City$0.00
County$5.03/sq ft
  • County Impact Fees (Collier County, Industrial)
    Collier County
    Effective May 1, 2026 (Phase 2 rates), per square foot of building area. Collier County general light industrial impact fee covering EMS, Government Buildings, Jail, Law Enforcement and Road; Library, Parks and School are not assessed on nonresidential. Water, wastewater and fire impact fees are billed separately.
    $3.97/sq ft
  • Fire Impact Fee (Collier County Fire Districts, Industrial)
    North Collier Fire District
    Fire impact fee, per square foot under roof, effective May 1, 2026. Rate varies by fire district; this record shows the highest of Collier County's four fire districts — North Collier $1.06. The others are Greater Naples $0.433, Immokalee $0.60 and Ochopee $0.68. The applicable district depends on parcel location.
    $1.06/sq ft
Total (unincorporated Collier County): $5.03/sq ft + $17,180.00 one-time (≈ $268,680.00 at 50,000 sq ft)
Sources last checked Official fee schedules:Collier County Water-Sewer District N/A Collier County
Water/sewer connection fees assume a 1-inch meter; larger services pay more.

Where in Collier County are you building?

Each jurisdiction applies its own fee schedule. Pick yours. Totals shown are for a 25,000 sq ft building, including one-time water/sewer fees (assuming a 1-inch meter). = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.

Unincorporated Collier County: Office Impact Fees

Office development in unincorporated Collier County pays $9.36 per square foot in impact fees, plus $17,180.00 in one-time water and sewer connection fees (rates sourced August 13, 2026).

For a 25,000 sq ft building, that comes to about $251,180.00. The calculator below adjusts to your exact square footage.

The largest line items are Water Impact Fee (Collier County Water-Sewer District) — 1" meter ($9,085.00 one-time), Wastewater (Sewer) Impact Fee (Collier County Water-Sewer District) — 1" meter ($8,095.00 one-time) and County Impact Fees (Collier County, Office) ($8.30/sq ft).

Water and sewer connection fees assume a 1-inch meter; larger services pay more. See the meter-size tiers in the source schedules.

View the full Collier County impact fee schedule
Water$9,085.00 one-time
  • Water Impact Fee (Collier County Water-Sewer District) — 1" meter
    Collier County Water-Sewer District
    Collier County Water-Sewer District water impact fee by meter size, effective December 1, 2025. Meter size is determined by total fixture value per the Florida Plumbing Code; the County installs meters 2 inches or smaller. Meter and cross-connection-control-device installation charges are separate. For change-of-use, charged only if the meter is upsized.
    $9,085.00 one-time
Sewer$8,095.00 one-time
  • Wastewater (Sewer) Impact Fee (Collier County Water-Sewer District) — 1" meter
    Collier County Water-Sewer District
    Collier County Water-Sewer District wastewater impact fee by meter size, effective December 1, 2025. Meter size is determined by total fixture value per the Florida Plumbing Code; the County installs meters 2 inches or smaller. Meter and cross-connection-control-device installation charges are separate. For change-of-use, charged only if the meter is upsized.
    $8,095.00 one-time
City$0.00
County$9.36/sq ft
  • County Impact Fees (Collier County, Office)
    Collier County
    Effective May 1, 2026 (Phase 2 rates), per square foot of building area. Collier County general office impact fee covering EMS, Government Buildings, Jail, Law Enforcement and Road; Library, Parks and School are not assessed on nonresidential. Water, wastewater and fire impact fees are billed separately.
    $8.30/sq ft
  • Fire Impact Fee (Collier County Fire Districts, Office)
    North Collier Fire District
    Fire impact fee, per square foot under roof, effective May 1, 2026. Rate varies by fire district; this record shows the highest of Collier County's four fire districts — North Collier $1.06. The others are Greater Naples $0.433, Immokalee $0.60 and Ochopee $0.68. The applicable district depends on parcel location.
    $1.06/sq ft
Total (unincorporated Collier County): $9.36/sq ft + $17,180.00 one-time (≈ $251,180.00 at 25,000 sq ft)
Sources last checked Official fee schedules:Collier County Water-Sewer District N/A Collier County
Water/sewer connection fees assume a 1-inch meter; larger services pay more.

Collier County impact fee calculator

Estimate impact fees for your project. Set to single-family. Drop a pin or search an address for site-specific fees.

Location

Select a location to begin

Once you select an address or drop a pin, we'll identify the responsible city and county and generate a fee breakdown.

Water & Sewer
Transportation
Parks
Schools
Fire & Police
General

How impact fees work in Florida

Florida impact fees are one-time charges on new development, governed by Section 163.31801, Florida Statutes (the Florida Impact Fee Act). The statute requires fees to be based on the most recent and localized data, spent on the infrastructure category they were collected for, and adopted by ordinance.

Since 2021, the law also limits how fast fees can rise: increases up to 25% phase in over two years, increases of 25–50% phase in over four years, and increases above 50% are allowed only with a demonstrated extraordinary-circumstances study and at least a two-thirds vote of the governing body.

Counties and cities can both levy impact fees. Inside an incorporated city, a project typically pays the county's countywide fees plus any municipal fees the city has adopted, which is why totals differ between a city and the unincorporated county around it.

If you're still asking what are impact fees, start with our guide to the definition, common categories, and legal basis.

Collier County impact fee FAQs

What are single-family impact fees in Collier County, Florida?

A new single-family home in unincorporated Collier County pays $35,931.97 per unit in impact fees (rates sourced August 13, 2026). Inside city limits, fees are set by each city's own schedule and may be completely different. See the city pages for their rates.

How much are multifamily impact fees in Collier County?

Multifamily development in unincorporated Collier County pays $18,547.95 per unit in impact fees (rates sourced August 13, 2026). Rates inside city limits depend on the municipality. Pick your city on this page.

How much are commercial impact fees in Collier County?

Commercial development in unincorporated Collier County pays $17.93 per square foot in impact fees, plus $17,180.00 in one-time water and sewer connection fees (assuming a 1-inch meter), about $913,680.00 for a 50,000 sq ft building.

Do cities in Collier County charge their own impact fees?

Yes. Every incorporated city applies its own fee schedule. 3 of 3 cities in Collier County levy municipal impact or utility fees; each city page shows the full schedule that applies inside its limits.

Can Florida impact fees increase at any time?

No. Section 163.31801, Florida Statutes limits increases to 50% at most, phased in over two to four years, unless the local government makes extraordinary-circumstances findings and approves the increase by at least a two-thirds vote.

Fee amounts on this page are compiled from official published schedules and are provided for planning purposes only. Rates change, and project specifics (unit size, meter size, location within special districts) can alter what applies. Always verify current fees with the jurisdiction and utility before relying on them.

Missing a jurisdiction? Get in touch.

Request coverage for a city or county, report an issue, ask about enterprise access, or inquire about sponsorship opportunities. We typically reply within one business day.

0/1000