IMPACTFEES.ORG

Gadsden County, Florida Impact Fees

Impact fees in Gadsden County depend on where you build. This page details the rates for unincorporated Gadsden County: $9,200.00 per single-family unit as of July 12, 2026. Inside city limits, each city applies its own schedule and fees may be completely different. Pick your city below.

Gadsden County impact fees by project type

Where in Gadsden County are you building?

Each jurisdiction applies its own fee schedule. Pick yours. = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.

Unincorporated Gadsden County: Single-Family Impact Fees

A new single-family home in unincorporated Gadsden County pays $9,200.00 per unit in impact fees (rates sourced July 12, 2026). Every line item is levied at the municipal or utility level.

The largest line items are Sewer System Capacity Charge (Talquin — Gadsden Co. Unincorporated) ($8,300.00) and Water System Capacity Charge (Talquin — Gadsden Co. Unincorporated) ($900.00).

View the full fee schedule
Water$900.00
  • Water System Capacity Charge (Talquin — Gadsden Co. Unincorporated)
    Talquin Electric Cooperative
    Talquin Electric Cooperative (Gadsden County Regional Water System), Rate Schedule W, eff. May 1, 2025. $900 System Capacity Charge for 0.75-inch meter (standard SFR) PLUS $600 New Metered Service Connection Fee (greater of $600 or actual cost to construct/connect/meter). Serves unincorporated areas where water service is established; remainder of county on private wells. Contact Talquin Water Services (850) 562-2115.
    $900.00
Sewer$8,300.00
  • Sewer System Capacity Charge (Talquin — Gadsden Co. Unincorporated)
    Talquin Electric Cooperative
    Talquin Electric Cooperative, Rate Schedule S (Wastewater), eff. May 1, 2025. $8,300 System Capacity Charge for 0.75-inch meter (standard SFR) PLUS $600 New Metered Service Connection Fee. Available only where wastewater service established; much of unincorporated Gadsden County on private septic. Contact Talquin Water Services (850) 562-2115.
    $8,300.00
City$0.00
County$0.00
  • County Impact Fees (Gadsden County)
    Gadsden County
    Gadsden County has NO development impact fee program. County Code of Ordinances (Supp. 16, codified through Ord. 2023-07) contains no Impact Fees chapter and no county utility chapter — full chapter list reviewed (Ch. 1–78). No county-collected school/transportation/parks impact fee found. Small rural county (~43,000 pop). Confirm with Growth Management (850) 875-8665.
    $0.00
Total (unincorporated Gadsden County): $9,200.00
Sources last checked July 12, 2026Official fee schedules:Talquin Electric Cooperative Gadsden County

Where in Gadsden County are you building?

Each jurisdiction applies its own fee schedule. Pick yours. = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.

Unincorporated Gadsden County: Multifamily Impact Fees

A new multifamily unit in unincorporated Gadsden County pays $9,200.00 per unit in impact fees (rates sourced July 12, 2026). Every line item is levied at the municipal or utility level.

Water System Capacity Charge (Talquin — Gadsden Co. Unincorporated, MF) and Sewer System Capacity Charge (Talquin — Gadsden Co. Unincorporated, MF) are shown at the last published amount but have not been confirmed with the jurisdiction; they are included in the totals here. Verify before budgeting.

View the full fee schedule
Water$900.00
  • Water System Capacity Charge (Talquin — Gadsden Co. Unincorporated, MF)
    Talquin Electric Cooperative
    Talquin Electric Cooperative (Gadsden County Regional Water System), Rate Schedule W. Re-verified 7/12/2026 — schedule still effective May 1, 2025, amounts unchanged. Base $900 System Capacity Charge for a 0.75-inch meter + $600 New Metered Service Connection Fee (greater of $600 or actual cost to construct/connect/meter). MF is assessed by MASTER-METER size (1-inch $1,765; 1.5-inch $3,525; 2-inch $6,000; 3-inch $11,290), so the true per-unit rate varies with project size — the $900 entered is the 0.75-inch base, not a confirmed per-unit MF rate. UNCONFIRMED — Talquin Water Services (850) 562-2115.
    $900.00Requires confirmation
Sewer$8,300.00
  • Sewer System Capacity Charge (Talquin — Gadsden Co. Unincorporated, MF)
    Talquin Electric Cooperative
    Talquin Electric Cooperative, Rate Schedule S (Wastewater). Re-verified 7/12/2026 — schedule still effective May 1, 2025, amounts unchanged. Base $8,300 System Capacity Charge for a 0.75-inch meter + $600 connection fee. MF is assessed by MASTER-METER size (1-inch $20,750; 1.5-inch $41,500; 2-inch $66,400), so the per-unit rate varies — the $8,300 entered is the 0.75-inch base, not a confirmed per-unit MF rate. UNCONFIRMED — Talquin Water Services (850) 562-2115.
    $8,300.00Requires confirmation
City$0.00
County$0.00
  • County Impact Fees (Gadsden County, MF)
    Gadsden County
    Gadsden County has NO development impact fee program. County Code (Supp. 16, through Ord. 2023-07) has no Impact Fees chapter and no county utility — full chapter list reviewed (Ch. 1–78). No school/transportation impact fee found. Growth Management (850) 875-8665.
    $0.00
Total (unincorporated Gadsden County): $9,200.00
Sources last checked July 12, 2026Official fee schedules:Talquin Electric Cooperative Gadsden County
Amounts flagged "Requires confirmation" are the last published figures, included in the totals. Confirm them with the jurisdiction or utility before budgeting.

Where in Gadsden County are you building?

Each jurisdiction applies its own fee schedule. Pick yours. Totals shown are for a 50,000 sq ft building, including one-time water/sewer fees (assuming a 1-inch meter). * = one-time water/sewer connection charges only; no per-sq-ft impact fee schedule sourced for that jurisdiction. = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.

Unincorporated Gadsden County: Commercial Impact Fees

Commercial development in unincorporated Gadsden County pays no per-square-foot impact fees, but owes $22,515.00 in one-time water and sewer connection fees (rates sourced July 12, 2026).

For a 50,000 sq ft building, that comes to about $22,515.00. The calculator below adjusts to your exact square footage.

The largest line items are Sewer System Capacity Charge (Talquin — Gadsden Co. Unincorporated) — 1" meter ($20,750.00 one-time) and Water System Capacity Charge (Talquin — Gadsden Co. Unincorporated) — 1" meter ($1,765.00 one-time).

View the full fee schedule
Water$1,765.00 one-time
  • Water System Capacity Charge (Talquin — Gadsden Co. Unincorporated) — 1" meter
    Talquin Electric Cooperative
    CANONICAL DEFAULT (1" meter). Talquin Electric Cooperative, Rate Schedule W — Water, eff. May 1, 2025. One meter-size schedule applies to all customer classes (no separate commercial table). IN ADDITION: New Metered Service Connection Fee = greater of $600 or total cost to construct, connect and meter the lateral — not included. Talquin Water Services (850) 562-2115.
    $1,765.00 one-time
Sewer$20,750.00 one-time
  • Sewer System Capacity Charge (Talquin — Gadsden Co. Unincorporated) — 1" meter
    Talquin Electric Cooperative
    CANONICAL DEFAULT (1" meter). Talquin Rate Schedule S — Wastewater, eff. May 1, 2025. Capacity charge set by water meter size; one schedule for all customer classes. Plus New Metered Service Connection Fee (greater of $600 or cost to construct/connect/meter), not included. Talquin Water Services (850) 562-2115.
    $20,750.00 one-time
City$0.00
County$0.00
  • County Impact Fees (Gadsden County, Commercial)
    Gadsden County
    Gadsden County levies NO development impact fees of any kind. County Code of Ordinances (Municode) contains no impact-fee chapter — full chapter list reviewed; no transportation, parks, fire/EMS, law-enforcement or school impact fee is imposed, and Growth Management posts no separate development-fee schedule. Confirmed 7/12/2026 for nonresidential (Commercial/Office/Industrial). Documented $0 — the fee does not exist. Gadsden County Growth Management (850) 875-8665.
    $0.00
Total (unincorporated Gadsden County): $22,515.00 one-time (≈ $22,515.00 at 50,000 sq ft)
Sources last checked July 12, 2026Official fee schedules:Talquin Electric Cooperative N/A — unincorporated area Gadsden County

Where in Gadsden County are you building?

Each jurisdiction applies its own fee schedule. Pick yours. Totals shown are for a 50,000 sq ft building, including one-time water/sewer fees (assuming a 1-inch meter). * = one-time water/sewer connection charges only; no per-sq-ft impact fee schedule sourced for that jurisdiction. = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.

Unincorporated Gadsden County: Industrial Impact Fees

Industrial development in unincorporated Gadsden County pays no per-square-foot impact fees, but owes $22,515.00 in one-time water and sewer connection fees (rates sourced July 12, 2026).

For a 50,000 sq ft building, that comes to about $22,515.00. The calculator below adjusts to your exact square footage.

The largest line items are Sewer System Capacity Charge (Talquin — Gadsden Co. Unincorporated) — 1" meter ($20,750.00 one-time) and Water System Capacity Charge (Talquin — Gadsden Co. Unincorporated) — 1" meter ($1,765.00 one-time).

View the full fee schedule
Water$1,765.00 one-time
  • Water System Capacity Charge (Talquin — Gadsden Co. Unincorporated) — 1" meter
    Talquin Electric Cooperative
    CANONICAL DEFAULT (1" meter). Talquin Electric Cooperative, Rate Schedule W — Water, eff. May 1, 2025. One meter-size schedule applies to all customer classes (no separate commercial table). IN ADDITION: New Metered Service Connection Fee = greater of $600 or total cost to construct, connect and meter the lateral — not included. Talquin Water Services (850) 562-2115.
    $1,765.00 one-time
Sewer$20,750.00 one-time
  • Sewer System Capacity Charge (Talquin — Gadsden Co. Unincorporated) — 1" meter
    Talquin Electric Cooperative
    CANONICAL DEFAULT (1" meter). Talquin Rate Schedule S — Wastewater, eff. May 1, 2025. Capacity charge set by water meter size; one schedule for all customer classes. Plus New Metered Service Connection Fee (greater of $600 or cost to construct/connect/meter), not included. Talquin Water Services (850) 562-2115.
    $20,750.00 one-time
City$0.00
County$0.00
  • County Impact Fees (Gadsden County, Industrial)
    Gadsden County
    Gadsden County levies NO development impact fees of any kind. County Code of Ordinances (Municode) contains no impact-fee chapter — full chapter list reviewed; no transportation, parks, fire/EMS, law-enforcement or school impact fee is imposed, and Growth Management posts no separate development-fee schedule. Confirmed 7/12/2026 for nonresidential (Commercial/Office/Industrial). Documented $0 — the fee does not exist. Gadsden County Growth Management (850) 875-8665.
    $0.00
Total (unincorporated Gadsden County): $22,515.00 one-time (≈ $22,515.00 at 50,000 sq ft)
Sources last checked July 12, 2026Official fee schedules:Talquin Electric Cooperative N/A — unincorporated area Gadsden County

Where in Gadsden County are you building?

Each jurisdiction applies its own fee schedule. Pick yours. Totals shown are for a 25,000 sq ft building, including one-time water/sewer fees (assuming a 1-inch meter). * = one-time water/sewer connection charges only; no per-sq-ft impact fee schedule sourced for that jurisdiction. = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.

Unincorporated Gadsden County: Office Impact Fees

Office development in unincorporated Gadsden County pays no per-square-foot impact fees, but owes $22,515.00 in one-time water and sewer connection fees (rates sourced July 12, 2026).

For a 25,000 sq ft building, that comes to about $22,515.00. The calculator below adjusts to your exact square footage.

The largest line items are Sewer System Capacity Charge (Talquin — Gadsden Co. Unincorporated) — 1" meter ($20,750.00 one-time) and Water System Capacity Charge (Talquin — Gadsden Co. Unincorporated) — 1" meter ($1,765.00 one-time).

View the full fee schedule
Water$1,765.00 one-time
  • Water System Capacity Charge (Talquin — Gadsden Co. Unincorporated) — 1" meter
    Talquin Electric Cooperative
    CANONICAL DEFAULT (1" meter). Talquin Electric Cooperative, Rate Schedule W — Water, eff. May 1, 2025. One meter-size schedule applies to all customer classes (no separate commercial table). IN ADDITION: New Metered Service Connection Fee = greater of $600 or total cost to construct, connect and meter the lateral — not included. Talquin Water Services (850) 562-2115.
    $1,765.00 one-time
Sewer$20,750.00 one-time
  • Sewer System Capacity Charge (Talquin — Gadsden Co. Unincorporated) — 1" meter
    Talquin Electric Cooperative
    CANONICAL DEFAULT (1" meter). Talquin Rate Schedule S — Wastewater, eff. May 1, 2025. Capacity charge set by water meter size; one schedule for all customer classes. Plus New Metered Service Connection Fee (greater of $600 or cost to construct/connect/meter), not included. Talquin Water Services (850) 562-2115.
    $20,750.00 one-time
City$0.00
County$0.00
  • County Impact Fees (Gadsden County, Office)
    Gadsden County
    Gadsden County levies NO development impact fees of any kind. County Code of Ordinances (Municode) contains no impact-fee chapter — full chapter list reviewed; no transportation, parks, fire/EMS, law-enforcement or school impact fee is imposed, and Growth Management posts no separate development-fee schedule. Confirmed 7/12/2026 for nonresidential (Commercial/Office/Industrial). Documented $0 — the fee does not exist. Gadsden County Growth Management (850) 875-8665.
    $0.00
Total (unincorporated Gadsden County): $22,515.00 one-time (≈ $22,515.00 at 25,000 sq ft)
Sources last checked July 12, 2026Official fee schedules:Talquin Electric Cooperative N/A — unincorporated area Gadsden County

Estimate your project in Gadsden County

Set to single-family. Drop a pin or search an address for site-specific fees.

Location

Loading map…
Search an address or click anywhere on the map to begin.

Select a location to begin

Once you select an address or drop a pin, we'll identify the responsible city and county and generate a fee breakdown.

Water & Sewer
Transportation
Parks
Schools
Fire & Police
General

How impact fees work in Florida

Florida impact fees are one-time charges on new development, governed by Section 163.31801, Florida Statutes (the Florida Impact Fee Act). The statute requires fees to be based on the most recent and localized data, spent on the infrastructure category they were collected for, and adopted by ordinance.

Since 2021, the law also limits how fast fees can rise: increases up to 25% phase in over two years, increases of 25–50% phase in over four years, and increases above 50% are allowed only with a demonstrated extraordinary-circumstances study and at least a two-thirds vote of the governing body.

Counties and cities can both levy impact fees. Inside an incorporated city, a project typically pays the county's countywide fees plus any municipal fees the city has adopted, which is why totals differ between a city and the unincorporated county around it.

Frequently asked questions

What are single-family impact fees in Gadsden County, Florida?

A new single-family home in unincorporated Gadsden County pays $9,200.00 per unit in impact fees (rates sourced July 12, 2026). Inside city limits, fees are set by each city's own schedule and may be completely different. See the city pages for their rates.

How much are multifamily impact fees in Gadsden County?

Multifamily development in unincorporated Gadsden County pays $9,200.00 per unit in impact fees (rates sourced July 12, 2026). This figure includes amounts that have not been confirmed with the jurisdiction; verify before budgeting. Rates inside city limits depend on the municipality. Pick your city on this page.

How much are commercial impact fees in Gadsden County?

Commercial development in unincorporated Gadsden County pays no per-square-foot impact fees, but owes $22,515.00 in one-time water and sewer connection fees.

Do cities in Gadsden County charge their own impact fees?

Yes. Every incorporated city applies its own fee schedule. 3 of 6 cities in Gadsden County levy municipal impact or utility fees; each city page shows the full schedule that applies inside its limits.

Can Florida impact fees increase at any time?

No. Section 163.31801, Florida Statutes limits increases to 50% at most, phased in over two to four years, unless the local government makes extraordinary-circumstances findings and approves the increase by at least a two-thirds vote.

Fee amounts on this page are compiled from official published schedules and are provided for planning purposes only. Rates change, and project specifics (unit size, meter size, location within special districts) can alter what applies. Always verify current fees with the jurisdiction and utility before relying on them.

Missing a jurisdiction? Get in touch.

Request coverage for a city or county, report an issue, ask about enterprise access, or inquire about sponsorship opportunities. We typically reply within one business day.