Coward Impact Fees by Project Type
Coward: Single-Family Impact Fees
A new single-family home in Coward pays at least $2,500.00 per unit in impact fees (rates sourced November 11, 2026). Every line item is levied at the municipal or utility level.
The largest line items are Water Tap Fee (Town of Coward) — minimum ($1,600.00).
Sewer Tap Fee (City of Lake City, Coward service area) — 4" tap is shown at the last published amount but has not been confirmed with the jurisdiction; it is included in the totals here. Verify before budgeting.
Municipal Impact Fee (Town of Coward) is set by the city and has no published standard rate. Contact the levying jurisdiction or utility to verify before budgeting; it is not included as a dollar figure here.
View the Full Coward Impact Fee Schedule
- Water Tap Fee (Town of Coward) — minimum$1,600.00Town of Coward Water DepartmentThe Town of Coward runs its own water system and publishes a residential water tap fee with a minimum of $1,600; the actual charge can be higher depending on the installation.
- Sewer Tap Fee (City of Lake City, Coward service area) — 4" tap$900.00Requires confirmationCity of Lake City Water DepartmentSewer inside Coward is provided by the City of Lake City, which serves only part of the town; elsewhere homes use septic systems. Coward sewer customers pay Lake City's outside-city rates, and Lake City's FY2026-27 schedule sets a 4 inch outside-city sewer tap at $900, plus boring costs where needed.
- Municipal Impact Fee (Town of Coward)Requires confirmationTown of Coward
- County Impact Fee (Florence County)$0.00Florence CountyFlorence County has not adopted a development impact fee under the South Carolina Development Impact Fee Act, and its adopted budget carries no impact fee revenue.
Where in Florence County Are You Building?
Each jurisdiction applies its own fee schedule. Pick yours. = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.
Coward: Multifamily Impact Fees
A new multifamily unit in Coward pays at least $2,500.00 per unit in impact fees (rates sourced November 11, 2026). Every line item is levied at the municipal or utility level.
The largest line items are Water Tap Fee (Town of Coward, MF) — minimum ($1,600.00).
Sewer Tap Fee (City of Lake City, Coward service area, MF) — 4" tap is shown at the last published amount but has not been confirmed with the jurisdiction; it is included in the totals here. Verify before budgeting.
Municipal Impact Fee (Town of Coward, MF) is set by the city and has no published standard rate. Contact the levying jurisdiction or utility to verify before budgeting; it is not included as a dollar figure here.
View the Full Coward Impact Fee Schedule
- Water Tap Fee (Town of Coward, MF) — minimum$1,600.00Town of Coward Water DepartmentThe Town of Coward publishes one residential water tap fee, a minimum of $1,600 per tap, with no per-apartment rate. A building served by one connection pays the tap once, and the actual charge can be higher depending on the installation.
- Sewer Tap Fee (City of Lake City, Coward service area, MF) — 4" tap$900.00Requires confirmationCity of Lake City Water DepartmentSewer inside Coward is provided by the City of Lake City at its outside-city rates, and taps are priced by tap size rather than per apartment. A 4 inch outside-city tap is $900, and a building served by one connection pays it once; larger taps are billed at cost plus 25 percent.
- Municipal Impact Fee (Town of Coward, MF)Requires confirmationTown of Coward
- County Impact Fee (Florence County, MF)$0.00Florence CountyFlorence County has not adopted a development impact fee under the South Carolina Development Impact Fee Act, and its adopted budget carries no impact fee revenue.
Where in Florence County Are You Building?
Each jurisdiction applies its own fee schedule. Pick yours. = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.
Coward: Commercial Impact Fees
Commercial development in Coward pays no per-square-foot impact fees, but owes $2,500.00 in one-time water and sewer connection fees (rates sourced November 11, 2026).
For a 50,000 sq ft building, that comes to at least $2,500.00. The calculator below adjusts to your exact square footage.
The largest line items are Water Tap Fee (Town of Coward) ($1,600.00 one-time).
Water and sewer connection fees assume a 1-inch meter; larger services pay more. See the meter-size tiers in the source schedules.
Sewer Tap Fee (City of Lake City, Coward service area) — 4" gravity is shown at the last published amount but has not been confirmed with the jurisdiction; it is included in the totals here. Verify before budgeting.
City Impact Fee (Town of Coward, Commercial) is set by the city and has no published standard rate. Contact the levying jurisdiction or utility to verify before budgeting; it is not included as a dollar figure here.
View the Full Coward Impact Fee Schedule
- Water Tap Fee (Town of Coward)$1,600.00 one-timeTown of Coward Water DepartmentThe Town of Coward charges a minimum water tap fee of $1,600 for a new connection; larger commercial taps can cost more.
- Sewer Tap Fee (City of Lake City, Coward service area) — 4" gravity$900.00 one-timeRequires confirmationCity of Lake CityThe City of Lake City owns the sewer serving a small part of Coward and charges its outside-city rates: a 4 inch gravity tap costs $900 plus any boring cost, and 6 inch and larger taps are priced at cost plus 25 percent. Most of Coward uses septic systems.
- City Impact Fee (Town of Coward, Commercial)Requires confirmationTown of CowardThe Town of Coward publishes no code of ordinances or development fee schedule, and no South Carolina Development Impact Fee Act adoption by the town is known.
- County Impact Fee (Florence County, Commercial)$0.00Florence CountyFlorence County has not adopted a development impact fee under the South Carolina Development Impact Fee Act, and its adopted budget carries no impact fee revenue.
Where in Florence County Are You Building?
Each jurisdiction applies its own fee schedule. Pick yours. Totals shown are for a 50,000 sq ft building, including one-time water/sewer fees (assuming a 1-inch meter). * = one-time water/sewer connection charges only; no per-sq-ft impact fee schedule sourced for that jurisdiction. = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.
Coward: Industrial Impact Fees
Industrial development in Coward pays no per-square-foot impact fees, but owes $2,500.00 in one-time water and sewer connection fees (rates sourced November 11, 2026).
For a 50,000 sq ft building, that comes to at least $2,500.00. The calculator below adjusts to your exact square footage.
The largest line items are Water Tap Fee (Town of Coward) ($1,600.00 one-time).
Water and sewer connection fees assume a 1-inch meter; larger services pay more. See the meter-size tiers in the source schedules.
Sewer Tap Fee (City of Lake City, Coward service area) — 4" gravity is shown at the last published amount but has not been confirmed with the jurisdiction; it is included in the totals here. Verify before budgeting.
City Impact Fee (Town of Coward, Industrial) is set by the city and has no published standard rate. Contact the levying jurisdiction or utility to verify before budgeting; it is not included as a dollar figure here.
View the Full Coward Impact Fee Schedule
- Water Tap Fee (Town of Coward)$1,600.00 one-timeTown of Coward Water DepartmentThe Town of Coward charges a minimum water tap fee of $1,600 for a new connection; larger commercial taps can cost more.
- Sewer Tap Fee (City of Lake City, Coward service area) — 4" gravity$900.00 one-timeRequires confirmationCity of Lake CityThe City of Lake City owns the sewer serving a small part of Coward and charges its outside-city rates: a 4 inch gravity tap costs $900 plus any boring cost, and 6 inch and larger taps are priced at cost plus 25 percent. Most of Coward uses septic systems.
- City Impact Fee (Town of Coward, Industrial)Requires confirmationTown of CowardThe Town of Coward publishes no code of ordinances or development fee schedule, and no South Carolina Development Impact Fee Act adoption by the town is known.
- County Impact Fee (Florence County, Industrial)$0.00Florence CountyFlorence County has not adopted a development impact fee under the South Carolina Development Impact Fee Act, and its adopted budget carries no impact fee revenue.
Where in Florence County Are You Building?
Each jurisdiction applies its own fee schedule. Pick yours. Totals shown are for a 50,000 sq ft building, including one-time water/sewer fees (assuming a 1-inch meter). * = one-time water/sewer connection charges only; no per-sq-ft impact fee schedule sourced for that jurisdiction. = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.
Coward: Office Impact Fees
Office development in Coward pays no per-square-foot impact fees, but owes $2,500.00 in one-time water and sewer connection fees (rates sourced November 11, 2026).
For a 25,000 sq ft building, that comes to at least $2,500.00. The calculator below adjusts to your exact square footage.
The largest line items are Water Tap Fee (Town of Coward) ($1,600.00 one-time).
Water and sewer connection fees assume a 1-inch meter; larger services pay more. See the meter-size tiers in the source schedules.
Sewer Tap Fee (City of Lake City, Coward service area) — 4" gravity is shown at the last published amount but has not been confirmed with the jurisdiction; it is included in the totals here. Verify before budgeting.
City Impact Fee (Town of Coward, Office) is set by the city and has no published standard rate. Contact the levying jurisdiction or utility to verify before budgeting; it is not included as a dollar figure here.
View the Full Coward Impact Fee Schedule
- Water Tap Fee (Town of Coward)$1,600.00 one-timeTown of Coward Water DepartmentThe Town of Coward charges a minimum water tap fee of $1,600 for a new connection; larger commercial taps can cost more.
- Sewer Tap Fee (City of Lake City, Coward service area) — 4" gravity$900.00 one-timeRequires confirmationCity of Lake CityThe City of Lake City owns the sewer serving a small part of Coward and charges its outside-city rates: a 4 inch gravity tap costs $900 plus any boring cost, and 6 inch and larger taps are priced at cost plus 25 percent. Most of Coward uses septic systems.
- City Impact Fee (Town of Coward, Office)Requires confirmationTown of CowardThe Town of Coward publishes no code of ordinances or development fee schedule, and no South Carolina Development Impact Fee Act adoption by the town is known.
- County Impact Fee (Florence County, Office)$0.00Florence CountyFlorence County has not adopted a development impact fee under the South Carolina Development Impact Fee Act, and its adopted budget carries no impact fee revenue.
Where in Florence County Are You Building?
Each jurisdiction applies its own fee schedule. Pick yours. Totals shown are for a 25,000 sq ft building, including one-time water/sewer fees (assuming a 1-inch meter). * = one-time water/sewer connection charges only; no per-sq-ft impact fee schedule sourced for that jurisdiction. = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.
Coward Impact Fee Calculator
Estimate impact fees for your project. Set to single-family. Drop a pin or search an address for site-specific fees.
Location
Select a location to begin
Once you select an address or drop a pin, we'll identify the responsible city and county and generate a fee breakdown.
How Development Impact Fees Work in South Carolina
South Carolina counties and municipalities assess development impact fees under the Development Impact Fee Act (S.C. Code 6-1-910 et seq.). Only a government with a comprehensive plan (or a capital improvements plan that substantially complies with the Act) may impose one, by an ordinance approved by a positive majority, and before charging residential units it must report how the fee affects the availability of affordable housing.
Fees may fund only the public facilities the Act lists: water and wastewater, solid waste, roads and bridges, stormwater and flood control, public safety (law enforcement, fire, emergency medical and street lighting), capital equipment and vehicles of at least $100,000 a unit, parks, libraries and recreation, and, since 2016, K-12 public school facilities. A fee may not exceed the development's proportionate share of the cost, after credits for land, money or improvements the developer contributes and for other funding sources.
Fee revenue is kept in interest-bearing accounts by category and service area and spent only on that category in that area. A fee not spent within three years of the date it was scheduled to be spent, or paid on a building permit that is denied, is refunded with its share of interest. The fee is due no earlier than the building permit (or the development permit where no building permit is needed).
Water and sewer charges usually come from the utility that serves a parcel: the Act's definition of an impact fee excludes connection or hookup charges, and a water or wastewater provider meeting the conditions of 6-1-1080 sets its impact fees outside the Act. That is why totals differ between a city, its neighbors and the unincorporated county around it.
For a primer on how impact fees work, see our plain-English guide.
Summary current as of November 2026. This is an editorial summary, not legal advice; see the official statute text and our terms of use.
Coward Impact Fee FAQs
What are the total impact fees for a single-family home in Coward, South Carolina?
A new single-family home in Coward pays at least $2,500.00 per unit in combined impact fees (rates sourced November 11, 2026). This figure includes amounts that have not been confirmed and excludes fees with no published standard amount, so the full cost may be higher; verify before budgeting.
How much are commercial impact fees in Coward?
Commercial development in Coward pays no per-square-foot impact fees, but owes $2,500.00 in one-time water and sewer connection fees (assuming a 1-inch meter). This figure includes amounts that have not been confirmed and excludes fees with no published standard amount, so the full cost may be higher; verify before budgeting.
Does Coward charge its own impact fees?
Yes. Coward levies its own municipal impact or utility fees. Florence County does not currently add county-level impact fees inside Coward. The schedule on this page shows every fee that applies to development in Coward.
Can a South Carolina impact fee be raised after it is adopted?
Only through a new ordinance. Under S.C. Code 6-1-940 the government is bound by the amount its impact fee ordinance sets for each unit of development and may not charge higher or additional impact fees for the same purpose unless the project's service units increase or its scope changes, and then only for the added share. Water and sewer capacity and tap fees set by utilities follow each provider's own rate process.
Fee amounts on this page are compiled from official published schedules and are provided for planning purposes only. Rates change, and project specifics (unit size, meter size, location within special districts) can alter what applies. Always verify current fees with the jurisdiction and utility before relying on them.
Compare unincorporated rates and every other city on the Florence County impact fees page.