Woodloch Impact Fees by Project Type
Woodloch: Single-Family Impact Fees
A new single-family home in Woodloch pays $2,000.00 per unit in impact fees (rates sourced October 20, 2026). Every line item is levied at the municipal or utility level.
Sewer Tap Fee (Town of Woodloch) — Short tap and Water Tap Fee (Town of Woodloch) — Short tap are shown at the last published amount but have not been confirmed with the jurisdiction; they are included in the totals here. Verify before budgeting.
Some fees are tiered by unit size or building type; amounts reflect the representative tier noted in the schedule below.
View the Full Woodloch Impact Fee Schedule
- Water Tap Fee (Town of Woodloch) — Short tap$1,000.00Requires confirmationTown of WoodlochThe Town of Woodloch runs its own water and sewer system. Residential water tap fee under Ordinance 2024-005, effective October 24, 2024: $1,000 for a short tap, $1,500 for a long tap.
- Sewer Tap Fee (Town of Woodloch) — Short tap$1,000.00Requires confirmationTown of WoodlochResidential sewer tap fee under Ordinance 2024-005, effective October 24, 2024: $1,000 for a short tap, $1,500 for a long tap.
- City Impact Fee (Town of Woodloch)$0.00Town of WoodlochNo municipal impact fee. Woodloch has adopted no Chapter 395 impact fee and no parkland dedication fee.
- County Impact Fee (Montgomery County)$0.00Montgomery CountyTexas counties do not charge development impact fees under Local Government Code Chapter 395, and Montgomery County has adopted no drainage impact fee.
Where in Montgomery County Are You Building?
Each jurisdiction applies its own fee schedule. Pick yours. = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.
Woodloch: Multifamily Impact Fees
Woodloch has no published impact fee amounts for a new multifamily unit (rates sourced October 20, 2026). The schedule below documents the status of each fee.
Water Tap Fee (Town of Woodloch, MF) and Sewer Tap Fee (Town of Woodloch, MF) are set by the utility and not published online. Contact the levying jurisdiction or utility to verify before budgeting; they are not included as dollar figures here.
View the Full Woodloch Impact Fee Schedule
- Water Tap Fee (Town of Woodloch, MF)Requires confirmationTown of WoodlochWoodloch publishes residential and commercial tap fees but no multifamily rule; a multifamily project's tap charges are set with the town.
- Sewer Tap Fee (Town of Woodloch, MF)Requires confirmationTown of WoodlochWoodloch publishes residential and commercial sewer tap fees but no multifamily rule; a multifamily project's tap charges are set with the town.
- City Impact Fee (Town of Woodloch, MF)$0.00Town of WoodlochNo municipal impact fee. Woodloch has adopted no Chapter 395 impact fee and no parkland dedication fee.
- County Impact Fee (Montgomery County, MF)$0.00Montgomery CountyTexas counties do not charge development impact fees under Local Government Code Chapter 395, and Montgomery County has adopted no drainage impact fee.
Where in Montgomery County Are You Building?
Each jurisdiction applies its own fee schedule. Pick yours. = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.
Woodloch: Commercial Impact Fees
Commercial development in Woodloch pays no per-square-foot impact fees, but owes $4,000.00 in one-time water and sewer connection fees (rates sourced October 20, 2026).
For a 50,000 sq ft building, that comes to about $4,000.00. The calculator below adjusts to your exact square footage.
Water and sewer connection fees assume a 1-inch meter; larger services pay more. See the meter-size tiers in the source schedules.
Water Tap Fee (Town of Woodloch) — Short tap and Sewer Tap Fee (Town of Woodloch) — Short tap are shown at the last published amount but have not been confirmed with the jurisdiction; they are included in the totals here. Verify before budgeting.
View the Full Woodloch Impact Fee Schedule
- Water Tap Fee (Town of Woodloch) — Short tap$2,000.00 one-timeRequires confirmationTown of WoodlochThe Town of Woodloch runs its own water and sewer system. Commercial water tap fee under Ordinance 2024-005, effective October 24, 2024: $2,000 for a short tap, $2,500 for a long tap. Where utility lines do not yet reach a commercial building, the town negotiates the installation price with the developer.
- Sewer Tap Fee (Town of Woodloch) — Short tap$2,000.00 one-timeRequires confirmationTown of WoodlochCommercial sewer tap fee under Ordinance 2024-005, effective October 24, 2024: $2,000 for a short tap, $2,500 for a long tap. Where utility lines do not yet reach a commercial building, the town negotiates the installation price with the developer.
- City Impact Fee (Town of Woodloch, Commercial)$0.00Town of WoodlochNo municipal impact fee. Woodloch has adopted no Chapter 395 roadway, drainage, water or wastewater impact fee.
- County Impact Fee (Montgomery County, Commercial)$0.00Montgomery CountyTexas counties do not charge development impact fees under Local Government Code Chapter 395, and Montgomery County has adopted no drainage impact fee.
Where in Montgomery County Are You Building?
Each jurisdiction applies its own fee schedule. Pick yours. Totals shown are for a 50,000 sq ft building, including water/sewer fees (one-time connection fees assume a 1-inch meter). * = one-time water/sewer connection charges only; no per-sq-ft impact fee schedule sourced for that jurisdiction. = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.
Woodloch: Industrial Impact Fees
Industrial development in Woodloch pays no per-square-foot impact fees, but owes $4,000.00 in one-time water and sewer connection fees (rates sourced October 20, 2026).
For a 50,000 sq ft building, that comes to about $4,000.00. The calculator below adjusts to your exact square footage.
Water and sewer connection fees assume a 1-inch meter; larger services pay more. See the meter-size tiers in the source schedules.
Water Tap Fee (Town of Woodloch) — Short tap and Sewer Tap Fee (Town of Woodloch) — Short tap are shown at the last published amount but have not been confirmed with the jurisdiction; they are included in the totals here. Verify before budgeting.
View the Full Woodloch Impact Fee Schedule
- Water Tap Fee (Town of Woodloch) — Short tap$2,000.00 one-timeRequires confirmationTown of WoodlochThe Town of Woodloch runs its own water and sewer system. Commercial water tap fee under Ordinance 2024-005, effective October 24, 2024: $2,000 for a short tap, $2,500 for a long tap. Where utility lines do not yet reach a commercial building, the town negotiates the installation price with the developer.
- Sewer Tap Fee (Town of Woodloch) — Short tap$2,000.00 one-timeRequires confirmationTown of WoodlochCommercial sewer tap fee under Ordinance 2024-005, effective October 24, 2024: $2,000 for a short tap, $2,500 for a long tap. Where utility lines do not yet reach a commercial building, the town negotiates the installation price with the developer.
- City Impact Fee (Town of Woodloch, Industrial)$0.00Town of WoodlochNo municipal impact fee. Woodloch has adopted no Chapter 395 roadway, drainage, water or wastewater impact fee.
- County Impact Fee (Montgomery County, Industrial)$0.00Montgomery CountyTexas counties do not charge development impact fees under Local Government Code Chapter 395, and Montgomery County has adopted no drainage impact fee.
Where in Montgomery County Are You Building?
Each jurisdiction applies its own fee schedule. Pick yours. Totals shown are for a 50,000 sq ft building, including water/sewer fees (one-time connection fees assume a 1-inch meter). * = one-time water/sewer connection charges only; no per-sq-ft impact fee schedule sourced for that jurisdiction. = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.
Woodloch: Office Impact Fees
Office development in Woodloch pays no per-square-foot impact fees, but owes $4,000.00 in one-time water and sewer connection fees (rates sourced October 20, 2026).
For a 25,000 sq ft building, that comes to about $4,000.00. The calculator below adjusts to your exact square footage.
Water and sewer connection fees assume a 1-inch meter; larger services pay more. See the meter-size tiers in the source schedules.
Water Tap Fee (Town of Woodloch) — Short tap and Sewer Tap Fee (Town of Woodloch) — Short tap are shown at the last published amount but have not been confirmed with the jurisdiction; they are included in the totals here. Verify before budgeting.
View the Full Woodloch Impact Fee Schedule
- Water Tap Fee (Town of Woodloch) — Short tap$2,000.00 one-timeRequires confirmationTown of WoodlochThe Town of Woodloch runs its own water and sewer system. Commercial water tap fee under Ordinance 2024-005, effective October 24, 2024: $2,000 for a short tap, $2,500 for a long tap. Where utility lines do not yet reach a commercial building, the town negotiates the installation price with the developer.
- Sewer Tap Fee (Town of Woodloch) — Short tap$2,000.00 one-timeRequires confirmationTown of WoodlochCommercial sewer tap fee under Ordinance 2024-005, effective October 24, 2024: $2,000 for a short tap, $2,500 for a long tap. Where utility lines do not yet reach a commercial building, the town negotiates the installation price with the developer.
- City Impact Fee (Town of Woodloch, Office)$0.00Town of WoodlochNo municipal impact fee. Woodloch has adopted no Chapter 395 roadway, drainage, water or wastewater impact fee.
- County Impact Fee (Montgomery County, Office)$0.00Montgomery CountyTexas counties do not charge development impact fees under Local Government Code Chapter 395, and Montgomery County has adopted no drainage impact fee.
Where in Montgomery County Are You Building?
Each jurisdiction applies its own fee schedule. Pick yours. Totals shown are for a 25,000 sq ft building, including water/sewer fees (one-time connection fees assume a 1-inch meter). * = one-time water/sewer connection charges only; no per-sq-ft impact fee schedule sourced for that jurisdiction. = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.
Woodloch Impact Fee Calculator
Estimate impact fees for your project. Set to single-family. Drop a pin or search an address for site-specific fees.
Location
Select a location to begin
Once you select an address or drop a pin, we'll identify the responsible city and county and generate a fee breakdown.
How Impact Fees Work in Texas
Texas cities, and certain special districts and authorities, assess impact fees under Chapter 395 of the Local Government Code and, with narrow exceptions, may charge one only by following it. A fee rests on adopted land use assumptions and a capital improvements plan, and imposing one takes the votes of two-thirds of the governing body's members.
Impact fees may fund only water supply, treatment and distribution; wastewater collection and treatment; storm water, drainage and flood control; and roadway facilities. Parks, schools, police and fire facilities are not on the chapter's list. The chapter does not treat park land dedication, or a payment in its place, as an impact fee, so a city can require that separately. The fee per service unit is capped at the plan's growth-related cost, less a required credit, divided by the projected service units. Counties generally cannot charge impact fees: the chapter gives that authority only to counties of 3.3 million or more people and the counties bordering them, and only for storm water, drainage and flood control. Since September 2025 a city also may not charge an impact fee where an office, retail or warehouse building at least five years old is converted to multifamily or mixed-use residential use (at least 65 percent of the building and of each usable floor), unless the land was already subject to an impact fee before the conversion's building permit was filed (Section 218.204).
For land platted after a fee is adopted, the fee is assessed no later than when the plat is recorded, which fixes the most that can be charged per service unit. Where water and wastewater capacity is available, it is generally collected when the building permit is issued, or when a water or wastewater meter connection is applied for on land outside city limits or where the entity charging the fee issues no building permits. A fee not spent as the chapter allows within 10 years of payment must generally be refunded with interest, and the land use assumptions and capital improvements plan are updated at least every five years unless the governing body formally determines that no update is needed.
A city may charge water, wastewater and drainage impact fees in its extraterritorial jurisdiction as well as inside its limits, but roadway impact fees stop at the city limits. Where a utility district or another provider supplies water or sewer instead of the city, its charges are separate from the city's, so the total can differ between a city, its neighbors and the unincorporated land around it.
For a primer on how impact fees work, see our plain-English guide.
Summary current as of November 2026. This is an editorial summary, not legal advice; see the official statute text and our terms of use.
Woodloch Impact Fee FAQs
What are the total impact fees for a single-family home in Woodloch, Texas?
A new single-family home in Woodloch pays $2,000.00 per unit in combined impact fees (rates sourced October 20, 2026). This figure includes amounts that have not been confirmed with the jurisdiction; verify before budgeting.
How much are commercial impact fees in Woodloch?
Commercial development in Woodloch pays no per-square-foot impact fees, but owes $4,000.00 in one-time water and sewer connection fees (assuming a 1-inch meter). This figure includes amounts that have not been confirmed with the jurisdiction; verify before budgeting.
Does Woodloch charge its own impact fees?
Yes. Woodloch levies its own municipal impact or utility fees. Montgomery County does not currently add county-level impact fees inside Woodloch. The schedule on this page shows every fee that applies to development in Woodloch.
Can a Texas impact fee increase at any time?
No. Under Section 395.0515 of the Local Government Code, added in 2025, a city or district may not increase an impact fee for three years from the later of the date the fee was adopted or last increased, although it may phase in collection up to the adopted maximum over no more than ten years. An increase also needs an independent financial audit and a public hearing on its results first (Section 395.059), and the measure approving it cannot be adopted as an emergency measure (Section 395.057). Once a fee is assessed on a tract, it cannot be raised for that tract unless the number of service units increases (Section 395.017). Charges set by a separate water or sewer provider may follow different rules.
Fee amounts on this page are compiled from official published schedules and are provided for planning purposes only. Rates change, and project specifics (unit size, meter size, location within special districts) can alter what applies. Always verify current fees with the jurisdiction and utility before relying on them.
Compare unincorporated rates and every other city on the Montgomery County impact fees page.