Mary Esther impact fees by project type
Mary Esther: Single-Family Impact Fees
A new single-family home in Mary Esther pays $1,600.00 per unit in impact fees (rates sourced August 4, 2026). All of it is levied by Okaloosa County.
Water & Sewer Impact Fee (City of Mary Esther) — $200/bedroom and Water Capacity Fee (Okaloosa County W&S, Mary Esther) are shown at the last published amount but have not been confirmed with the jurisdiction; they are included in the totals here. Verify before budgeting.
View the full fee schedule
- Water Capacity Fee (Okaloosa County W&S, Mary Esther)$1,000.00Requires confirmationOkaloosa County Water & Sewer⚠️ PROVIDER QUESTION (8/4/2026; Okaloosa family — Mary Esther runs its own WATER utility with a $200/bedroom development fee; this OCWS water capacity fee likely does NOT apply in the city). (850) 243-3566.
- Water & Sewer Impact Fee (City of Mary Esther) — $200/bedroom$600.00Requires confirmationOkaloosa County Water & SewerPROVIDER CORRECTED 8/3/2026: prior record assumed Okaloosa County W&S ($3,800/ERU) — WRONG. County's own Permit Guide for City of Mary Esther (myokaloosa.com Growth Mgmt forms): water & sewer tap fees for new construction are paid to the CITY OF MARY ESTHER, which runs its own utility. City Impact Fees schedule: Water and Sewer impact fee $200.00 PER BEDROOM — amount entered = representative 3BR SFR = $600. Same city schedule: Fire $337, Law Enf $323, Transportation $1,500, Parks $150, Stormwater $300 per SFD. STILL FLAGGED: city schedule is undated, and separate tap/connection fees live in the Utilities Handbook (Res. 22-03, image PDF, amounts not extractable online) — confirm currency + tap fees with the city.
- Municipal Impact Fees (City of Mary Esther — None Found)$0.00City of Mary Esther8/4/2026: Confirmed $0 — Municode full-text search of Mary Esther Code of Ordinances + Land Development Code finds no impact or mobility fee provisions (LDC Art. 18 covers administrative fees only; concurrency handled via proportionate fair-share). County mobility fee not assessed in city (no interlocal). City Hall 850-243-3566.
- County Mobility Fee (Okaloosa County — Not Assessed Inside Mary Esther)$0.00Okaloosa County8/4/2026: County ADOPTED a mobility fee (Ord. 2024-23, 12/3/2024; LDC Ch. 4 & Ch. 12) but it is NOT assessed on development inside municipalities unless the city opts in via interlocal agreement (LDC 4.03.04(9)). No mobility-fee interlocal found for the City of Mary Esther as of 8/4/2026, so the county fee is $0 here. County levies no other general impact fee; no school impact fee found. Growth Mgmt 850-651-7180.
Where in Okaloosa County are you building?
Each jurisdiction applies its own fee schedule. Pick yours. = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.
Mary Esther: Multifamily Impact Fees
A new multifamily unit in Mary Esther pays $4,200.00 per unit in impact fees (rates sourced August 4, 2026). All of it is levied by Okaloosa County.
The largest line items are Water Development Fee (City of Mary Esther, MF) — 2BR = 2 × $200/bedroom ($400.00).
Sewer Capacity Fee (Okaloosa County W&S, Mary Esther) (MF) is shown at the last published amount but has not been confirmed with the jurisdiction; it is included in the totals here. Verify before budgeting.
View the full fee schedule
- Water Development Fee (City of Mary Esther, MF) — 2BR = 2 × $200/bedroom$400.00Okaloosa County Water & SewerVERIFIED 8/4/2026 (Mary Esther family — the $200/bedroom water development fee was verified for the SFR sibling on the city's posted impact-fee sheet): canonical 2BR unit = 2 × $200 = $400 — bedroom basis is the published MF rule. (850) 243-3566.
- Sewer Capacity Fee (Okaloosa County W&S, Mary Esther) (MF)$3,800.00Requires confirmationOkaloosa County Water & Sewer⚠️ PROVIDER QUESTION (8/4/2026; Okaloosa family). Mary Esther runs its own water utility — whether OCWS provides its SEWER (and this $3,800 applies) is parcel-specific. (850) 243-3566 / OCWS (850) 651-7171.
- Municipal Impact Fees (City of Mary Esther — None Found) (MF)$0.00City of Mary Esther8/4/2026: Confirmed $0 — Municode full-text search of Mary Esther Code of Ordinances + Land Development Code finds no impact or mobility fee provisions (LDC Art. 18 covers administrative fees only; concurrency handled via proportionate fair-share). County mobility fee not assessed in city (no interlocal). City Hall 850-243-3566.
- County Mobility Fee (Okaloosa County — Not Assessed Inside Mary Esther) (MF)$0.00Okaloosa County8/4/2026: County ADOPTED a mobility fee (Ord. 2024-23, 12/3/2024; LDC Ch. 4 & Ch. 12) but it is NOT assessed on development inside municipalities unless the city opts in via interlocal agreement (LDC 4.03.04(9)). No mobility-fee interlocal found for the City of Mary Esther as of 8/4/2026, so the county fee is $0 here. County levies no other general impact fee; no school impact fee found. Growth Mgmt 850-651-7180.
Where in Okaloosa County are you building?
Each jurisdiction applies its own fee schedule. Pick yours. = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.
Mary Esther: Commercial Impact Fees
Commercial development in Mary Esther pays no per-square-foot impact fees, but owes $5,000.00 in one-time water and sewer connection fees (rates sourced August 4, 2026).
For a 50,000 sq ft building, that comes to at least $5,000.00. The calculator below adjusts to your exact square footage.
Water and sewer connection fees assume a 1-inch meter; larger services pay more. See the meter-size tiers in the source schedules.
Sewer Capacity Fee (Okaloosa County W&S, Mary Esther) — 4" outlet and Water Capacity Fee (Okaloosa County W&S, Mary Esther) — 1" meter are shown at the last published amount but have not been confirmed with the jurisdiction; they are included in the totals here. Verify before budgeting.
City Impact Fee Placeholder (Mary Esther, Commercial) is set by the city and has no published standard rate. Contact the levying jurisdiction or utility to verify before budgeting; it is not included as a dollar figure here.
View the full fee schedule
- Water Capacity Fee (Okaloosa County W&S, Mary Esther) — 1" meter$1,200.00 one-timeRequires confirmationOkaloosa County Water & Sewer[Audit 2026-07-17] City of Mary Esther operates its OWN water utility — Utilities Handbook adopted by Res. 22-03 sets city tap-in fees (commercial $2,500, incl. meter/curb stop/box/installation) and ready-to-serve rates; per the city's FAQ, OCWS serves only the area WEST of Hurlburt Field. Provider is therefore likely City of Mary Esther, not OCWS, and the OCWS Appendix A meter amounts here (1" $1,200) are placeholders. City's own capacity/system-development charge not yet traced (Utilities Handbook PDF would not render for either web_fetch or headless render). Unconfirmed — City Water Dept 850-243-3566.
- Sewer Capacity Fee (Okaloosa County W&S, Mary Esther) — 4" outlet$3,800.00 one-timeRequires confirmationOkaloosa County Water & Sewer[Audit 2026-07-17] Mary Esther runs its own water utility (Res. 22-03 Utilities Handbook); its sewer provider is unverified (city collection vs OCWS vs septic). OCWS 4" outlet $3,800 here is a placeholder. Unconfirmed — City 850-243-3566 / OCWS 850-651-7171.
- City Impact Fee Placeholder (Mary Esther, Commercial)Requires confirmationNo municipal development impact fee found for City of Mary Esther (pop ~3,980); no adopted fee resolution located online 2026-07-17. Unverified $0 — City Hall 850-243-3566.
- County Impact Fee Placeholder (Mary Esther, Commercial)$0.00Okaloosa County levies NO county-wide impact or mobility fee on nonresidential development. Confirmed 2026-07-17 against the county's adopted Inspection & Permitting Fee schedule (Growth Management) and 2024 Developers Help Guide — neither contains an impact fee; LDC Appendix E Ch. 12 holds a mobility-fee framework with no adopted rate schedule. School-district impact fee is residential-only (no nonres bearing). Growth Management 850-651-7180.
Where in Okaloosa County are you building?
Each jurisdiction applies its own fee schedule. Pick yours. Totals shown are for a 50,000 sq ft building, including one-time water/sewer fees (assuming a 1-inch meter). * = one-time water/sewer connection charges only; no per-sq-ft impact fee schedule sourced for that jurisdiction. = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.
Mary Esther: Industrial Impact Fees
Industrial development in Mary Esther pays no per-square-foot impact fees, but owes $5,000.00 in one-time water and sewer connection fees (rates sourced August 4, 2026).
For a 50,000 sq ft building, that comes to at least $5,000.00. The calculator below adjusts to your exact square footage.
Water and sewer connection fees assume a 1-inch meter; larger services pay more. See the meter-size tiers in the source schedules.
Sewer Capacity Fee (Okaloosa County W&S, Mary Esther) — 4" outlet and Water Capacity Fee (Okaloosa County W&S, Mary Esther) — 1" meter are shown at the last published amount but have not been confirmed with the jurisdiction; they are included in the totals here. Verify before budgeting.
City Impact Fee Placeholder (Mary Esther, Industrial) is set by the city and has no published standard rate. Contact the levying jurisdiction or utility to verify before budgeting; it is not included as a dollar figure here.
View the full fee schedule
- Water Capacity Fee (Okaloosa County W&S, Mary Esther) — 1" meter$1,200.00 one-timeRequires confirmationOkaloosa County Water & Sewer[Audit 2026-07-17] City of Mary Esther operates its OWN water utility — Utilities Handbook adopted by Res. 22-03 sets city tap-in fees (commercial $2,500, incl. meter/curb stop/box/installation) and ready-to-serve rates; per the city's FAQ, OCWS serves only the area WEST of Hurlburt Field. Provider is therefore likely City of Mary Esther, not OCWS, and the OCWS Appendix A meter amounts here (1" $1,200) are placeholders. City's own capacity/system-development charge not yet traced (Utilities Handbook PDF would not render for either web_fetch or headless render). Unconfirmed — City Water Dept 850-243-3566.
- Sewer Capacity Fee (Okaloosa County W&S, Mary Esther) — 4" outlet$3,800.00 one-timeRequires confirmationOkaloosa County Water & Sewer[Audit 2026-07-17] Mary Esther runs its own water utility (Res. 22-03 Utilities Handbook); its sewer provider is unverified (city collection vs OCWS vs septic). OCWS 4" outlet $3,800 here is a placeholder. Unconfirmed — City 850-243-3566 / OCWS 850-651-7171.
- City Impact Fee Placeholder (Mary Esther, Industrial)Requires confirmationNo municipal development impact fee found for City of Mary Esther (pop ~3,980); no adopted fee resolution located online 2026-07-17. Unverified $0 — City Hall 850-243-3566.
- County Impact Fee Placeholder (Mary Esther, Industrial)$0.00Okaloosa County levies NO county-wide impact or mobility fee on nonresidential development. Confirmed 2026-07-17 against the county's adopted Inspection & Permitting Fee schedule (Growth Management) and 2024 Developers Help Guide — neither contains an impact fee; LDC Appendix E Ch. 12 holds a mobility-fee framework with no adopted rate schedule. School-district impact fee is residential-only (no nonres bearing). Growth Management 850-651-7180.
Where in Okaloosa County are you building?
Each jurisdiction applies its own fee schedule. Pick yours. Totals shown are for a 50,000 sq ft building, including one-time water/sewer fees (assuming a 1-inch meter). * = one-time water/sewer connection charges only; no per-sq-ft impact fee schedule sourced for that jurisdiction. = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.
Mary Esther: Office Impact Fees
Office development in Mary Esther pays no per-square-foot impact fees, but owes $5,000.00 in one-time water and sewer connection fees (rates sourced August 4, 2026).
For a 25,000 sq ft building, that comes to at least $5,000.00. The calculator below adjusts to your exact square footage.
Water and sewer connection fees assume a 1-inch meter; larger services pay more. See the meter-size tiers in the source schedules.
Sewer Capacity Fee (Okaloosa County W&S, Mary Esther) — 4" outlet and Water Capacity Fee (Okaloosa County W&S, Mary Esther) — 1" meter are shown at the last published amount but have not been confirmed with the jurisdiction; they are included in the totals here. Verify before budgeting.
City Impact Fee Placeholder (Mary Esther, Office) is set by the city and has no published standard rate. Contact the levying jurisdiction or utility to verify before budgeting; it is not included as a dollar figure here.
View the full fee schedule
- Water Capacity Fee (Okaloosa County W&S, Mary Esther) — 1" meter$1,200.00 one-timeRequires confirmationOkaloosa County Water & Sewer[Audit 2026-07-17] City of Mary Esther operates its OWN water utility — Utilities Handbook adopted by Res. 22-03 sets city tap-in fees (commercial $2,500, incl. meter/curb stop/box/installation) and ready-to-serve rates; per the city's FAQ, OCWS serves only the area WEST of Hurlburt Field. Provider is therefore likely City of Mary Esther, not OCWS, and the OCWS Appendix A meter amounts here (1" $1,200) are placeholders. City's own capacity/system-development charge not yet traced (Utilities Handbook PDF would not render for either web_fetch or headless render). Unconfirmed — City Water Dept 850-243-3566.
- Sewer Capacity Fee (Okaloosa County W&S, Mary Esther) — 4" outlet$3,800.00 one-timeRequires confirmationOkaloosa County Water & Sewer[Audit 2026-07-17] Mary Esther runs its own water utility (Res. 22-03 Utilities Handbook); its sewer provider is unverified (city collection vs OCWS vs septic). OCWS 4" outlet $3,800 here is a placeholder. Unconfirmed — City 850-243-3566 / OCWS 850-651-7171.
- City Impact Fee Placeholder (Mary Esther, Office)Requires confirmationNo municipal development impact fee found for City of Mary Esther (pop ~3,980); no adopted fee resolution located online 2026-07-17. Unverified $0 — City Hall 850-243-3566.
- County Impact Fee Placeholder (Mary Esther, Office)$0.00Okaloosa County levies NO county-wide impact or mobility fee on nonresidential development. Confirmed 2026-07-17 against the county's adopted Inspection & Permitting Fee schedule (Growth Management) and 2024 Developers Help Guide — neither contains an impact fee; LDC Appendix E Ch. 12 holds a mobility-fee framework with no adopted rate schedule. School-district impact fee is residential-only (no nonres bearing). Growth Management 850-651-7180.
Where in Okaloosa County are you building?
Each jurisdiction applies its own fee schedule. Pick yours. Totals shown are for a 25,000 sq ft building, including one-time water/sewer fees (assuming a 1-inch meter). * = one-time water/sewer connection charges only; no per-sq-ft impact fee schedule sourced for that jurisdiction. = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.
Estimate your project in Mary Esther
Set to single-family. Drop a pin or search an address for site-specific fees.
Location
Select a location to begin
Once you select an address or drop a pin, we'll identify the responsible city and county and generate a fee breakdown.
How impact fees work in Florida
Florida impact fees are one-time charges on new development, governed by Section 163.31801, Florida Statutes (the Florida Impact Fee Act). The statute requires fees to be based on the most recent and localized data, spent on the infrastructure category they were collected for, and adopted by ordinance.
Since 2021, the law also limits how fast fees can rise: increases up to 25% phase in over two years, increases of 25–50% phase in over four years, and increases above 50% are allowed only with a demonstrated extraordinary-circumstances study and at least a two-thirds vote of the governing body.
Counties and cities can both levy impact fees. Inside an incorporated city, a project typically pays the county's countywide fees plus any municipal fees the city has adopted, which is why totals differ between a city and the unincorporated county around it.
Frequently asked questions
What are the total impact fees for a single-family home in Mary Esther, Florida?
A new single-family home in Mary Esther pays $1,600.00 per unit in combined impact fees (rates sourced August 4, 2026). This figure includes amounts that have not been confirmed with the jurisdiction; verify before budgeting.
How much are commercial impact fees in Mary Esther?
Commercial development in Mary Esther pays no per-square-foot impact fees, but owes $5,000.00 in one-time water and sewer connection fees (assuming a 1-inch meter). This figure includes amounts that have not been confirmed and excludes fees with no published standard amount, so the full cost may be higher; verify before budgeting.
Does Mary Esther charge its own impact fees?
Yes. Mary Esther levies its own municipal impact or utility fees, and county-levied fees also apply inside city limits. The schedule on this page shows every fee that applies to development in Mary Esther, with the combined total.
Can Florida impact fees increase at any time?
No. Section 163.31801, Florida Statutes limits increases to 50% at most, phased in over two to four years, unless the local government makes extraordinary-circumstances findings and approves the increase by at least a two-thirds vote.
Fee amounts on this page are compiled from official published schedules and are provided for planning purposes only. Rates change, and project specifics (unit size, meter size, location within special districts) can alter what applies. Always verify current fees with the jurisdiction and utility before relying on them.
Compare unincorporated rates and every other city on the Okaloosa County impact fees page.