IMPACTFEES.ORG

Mary Esther, Florida Impact Fees

Mary Esther applies its own fee schedule: municipal fees plus the Okaloosa County-levied fees that apply inside city limits. Combined, a new single-family home pays at least $4,800.00 per unit (rates sourced July 17, 2026). This figure includes amounts that have not been confirmed and excludes fees with no published standard amount, so the full cost may be higher; verify before budgeting. The full breakdown is below.

Mary Esther impact fees by project type

Mary Esther: Single-Family Impact Fees

A new single-family home in Mary Esther pays at least $4,800.00 per unit in impact fees (rates sourced July 17, 2026). All of it is levied by Okaloosa County.

Sewer Capacity Fee (Okaloosa County W&S, Mary Esther) and Water Capacity Fee (Okaloosa County W&S, Mary Esther) are shown at the last published amount but have not been confirmed with the jurisdiction; they are included in the totals here. Verify before budgeting.

County Impact/Mobility Fee (Okaloosa County — None Adopted) is set by the county and has no published standard rate. Municipal Impact Fees (City of Mary Esther — None Found) is set by the city and has no published standard rate. Contact the levying jurisdiction or utility to verify before budgeting; they are not included as dollar figures here.

View the full fee schedule
Water$1,000.00
Sewer$3,800.00
City$0.00
County$0.00
Total (Mary Esther): $4,800.00
Sources last checked July 17, 2026Official fee schedules:Okaloosa County Water & Sewer City of Mary Esther Okaloosa County
Amounts flagged "Requires confirmation" are the last published figures, included in the totals. Confirm them with the jurisdiction or utility before budgeting.

Mary Esther: Multifamily Impact Fees

A new multifamily unit in Mary Esther pays at least $4,800.00 per unit in impact fees (rates sourced July 17, 2026). All of it is levied by Okaloosa County.

Water Capacity Fee (Okaloosa County W&S, Mary Esther) (MF) and Sewer Capacity Fee (Okaloosa County W&S, Mary Esther) (MF) are shown at the last published amount but have not been confirmed with the jurisdiction; they are included in the totals here. Verify before budgeting.

County Impact/Mobility Fee (Okaloosa County — None Adopted) (MF) is set by the county and has no published standard rate. Municipal Impact Fees (City of Mary Esther — None Found) (MF) is set by the city and has no published standard rate. Contact the levying jurisdiction or utility to verify before budgeting; they are not included as dollar figures here.

View the full fee schedule
Water$1,000.00
  • Water Capacity Fee (Okaloosa County W&S, Mary Esther) (MF)
    Okaloosa County Water & Sewer
    Provider assumed Okaloosa County W&S. County Water Capacity Expansion Charge $1,000/ERU, 1 ERU/dwelling unit — Appendix A, rates eff. Oct 1, 2025. Amount updated 7/12/2026 from expired $900 schedule. UNCONFIRMED: verify provider — OCWS 850-651-7171.
    $1,000.00Requires confirmation
Sewer$3,800.00
  • Sewer Capacity Fee (Okaloosa County W&S, Mary Esther) (MF)
    Okaloosa County Water & Sewer
    Provider assumed Okaloosa County W&S. County Sewer Capacity Expansion Charge $3,800/ERU, 1 ERU/dwelling unit — Appendix A, rates eff. Oct 1, 2025. Amount updated 7/12/2026 from expired $3,500 schedule. UNCONFIRMED: verify provider — OCWS 850-651-7171.
    $3,800.00Requires confirmation
City$0.00
County$0.00
  • County Impact/Mobility Fee (Okaloosa County — None Adopted) (MF)
    Okaloosa County
    Okaloosa County levies no county-wide impact/mobility fee; re-confirmed 7/12/2026 against the county's adopted permitting fee schedule and 2024 Developers Help Guide. OPEN: possible school-district impact fee — unverified. 850-651-7180.
    Requires confirmation
Total (Mary Esther): $4,800.00
Sources last checked July 17, 2026Official fee schedules:Okaloosa County Water & Sewer City of Mary Esther Okaloosa County
Amounts flagged "Requires confirmation" are the last published figures, included in the totals. Confirm them with the jurisdiction or utility before budgeting.

Mary Esther: Commercial Impact Fees

Commercial development in Mary Esther pays no per-square-foot impact fees, but owes $5,000.00 in one-time water and sewer connection fees (rates sourced July 17, 2026).

For a 50,000 sq ft building, that comes to at least $5,000.00. The calculator below adjusts to your exact square footage.

Sewer Capacity Fee (Okaloosa County W&S, Mary Esther) — 4" outlet and Water Capacity Fee (Okaloosa County W&S, Mary Esther) — 1" meter are shown at the last published amount but have not been confirmed with the jurisdiction; they are included in the totals here. Verify before budgeting.

City Impact Fee Placeholder (Mary Esther, Commercial) is set by the city and has no published standard rate. Contact the levying jurisdiction or utility to verify before budgeting; it is not included as a dollar figure here.

View the full fee schedule
Water$1,200.00 one-time
  • Water Capacity Fee (Okaloosa County W&S, Mary Esther) — 1" meter
    Okaloosa County Water & Sewer
    [Audit 2026-07-17] City of Mary Esther operates its OWN water utility — Utilities Handbook adopted by Res. 22-03 sets city tap-in fees (commercial $2,500, incl. meter/curb stop/box/installation) and ready-to-serve rates; per the city's FAQ, OCWS serves only the area WEST of Hurlburt Field. Provider is therefore likely City of Mary Esther, not OCWS, and the OCWS Appendix A meter amounts here (1" $1,200) are placeholders. City's own capacity/system-development charge not yet traced (Utilities Handbook PDF would not render for either web_fetch or headless render). Unconfirmed — City Water Dept 850-243-3566.
    $1,200.00 one-timeRequires confirmation
Sewer$3,800.00 one-time
  • Sewer Capacity Fee (Okaloosa County W&S, Mary Esther) — 4" outlet
    Okaloosa County Water & Sewer
    [Audit 2026-07-17] Mary Esther runs its own water utility (Res. 22-03 Utilities Handbook); its sewer provider is unverified (city collection vs OCWS vs septic). OCWS 4" outlet $3,800 here is a placeholder. Unconfirmed — City 850-243-3566 / OCWS 850-651-7171.
    $3,800.00 one-timeRequires confirmation
City$0.00
County$0.00
  • County Impact Fee Placeholder (Mary Esther, Commercial)
    Okaloosa County levies NO county-wide impact or mobility fee on nonresidential development. Confirmed 2026-07-17 against the county's adopted Inspection & Permitting Fee schedule (Growth Management) and 2024 Developers Help Guide — neither contains an impact fee; LDC Appendix E Ch. 12 holds a mobility-fee framework with no adopted rate schedule. School-district impact fee is residential-only (no nonres bearing). Growth Management 850-651-7180.
    $0.00
Total (Mary Esther): $5,000.00 one-time (≈ $5,000.00 at 50,000 sq ft)
Sources last checked July 17, 2026Official fee schedule:Okaloosa County Water & Sewer
Amounts flagged "Requires confirmation" are the last published figures, included in the totals. Confirm them with the jurisdiction or utility before budgeting.

Where in Okaloosa County are you building?

Each jurisdiction applies its own fee schedule. Pick yours. Totals shown are for a 50,000 sq ft building, including one-time water/sewer fees (assuming a 1-inch meter). * = one-time water/sewer connection charges only; no per-sq-ft impact fee schedule sourced for that jurisdiction. = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.

Mary Esther: Industrial Impact Fees

Industrial development in Mary Esther pays no per-square-foot impact fees, but owes $5,000.00 in one-time water and sewer connection fees (rates sourced July 17, 2026).

For a 50,000 sq ft building, that comes to at least $5,000.00. The calculator below adjusts to your exact square footage.

Sewer Capacity Fee (Okaloosa County W&S, Mary Esther) — 4" outlet and Water Capacity Fee (Okaloosa County W&S, Mary Esther) — 1" meter are shown at the last published amount but have not been confirmed with the jurisdiction; they are included in the totals here. Verify before budgeting.

City Impact Fee Placeholder (Mary Esther, Industrial) is set by the city and has no published standard rate. Contact the levying jurisdiction or utility to verify before budgeting; it is not included as a dollar figure here.

View the full fee schedule
Water$1,200.00 one-time
  • Water Capacity Fee (Okaloosa County W&S, Mary Esther) — 1" meter
    Okaloosa County Water & Sewer
    [Audit 2026-07-17] City of Mary Esther operates its OWN water utility — Utilities Handbook adopted by Res. 22-03 sets city tap-in fees (commercial $2,500, incl. meter/curb stop/box/installation) and ready-to-serve rates; per the city's FAQ, OCWS serves only the area WEST of Hurlburt Field. Provider is therefore likely City of Mary Esther, not OCWS, and the OCWS Appendix A meter amounts here (1" $1,200) are placeholders. City's own capacity/system-development charge not yet traced (Utilities Handbook PDF would not render for either web_fetch or headless render). Unconfirmed — City Water Dept 850-243-3566.
    $1,200.00 one-timeRequires confirmation
Sewer$3,800.00 one-time
  • Sewer Capacity Fee (Okaloosa County W&S, Mary Esther) — 4" outlet
    Okaloosa County Water & Sewer
    [Audit 2026-07-17] Mary Esther runs its own water utility (Res. 22-03 Utilities Handbook); its sewer provider is unverified (city collection vs OCWS vs septic). OCWS 4" outlet $3,800 here is a placeholder. Unconfirmed — City 850-243-3566 / OCWS 850-651-7171.
    $3,800.00 one-timeRequires confirmation
City$0.00
County$0.00
  • County Impact Fee Placeholder (Mary Esther, Industrial)
    Okaloosa County levies NO county-wide impact or mobility fee on nonresidential development. Confirmed 2026-07-17 against the county's adopted Inspection & Permitting Fee schedule (Growth Management) and 2024 Developers Help Guide — neither contains an impact fee; LDC Appendix E Ch. 12 holds a mobility-fee framework with no adopted rate schedule. School-district impact fee is residential-only (no nonres bearing). Growth Management 850-651-7180.
    $0.00
Total (Mary Esther): $5,000.00 one-time (≈ $5,000.00 at 50,000 sq ft)
Sources last checked July 17, 2026Official fee schedule:Okaloosa County Water & Sewer
Amounts flagged "Requires confirmation" are the last published figures, included in the totals. Confirm them with the jurisdiction or utility before budgeting.

Where in Okaloosa County are you building?

Each jurisdiction applies its own fee schedule. Pick yours. Totals shown are for a 50,000 sq ft building, including one-time water/sewer fees (assuming a 1-inch meter). * = one-time water/sewer connection charges only; no per-sq-ft impact fee schedule sourced for that jurisdiction. = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.

Mary Esther: Office Impact Fees

Office development in Mary Esther pays no per-square-foot impact fees, but owes $5,000.00 in one-time water and sewer connection fees (rates sourced July 17, 2026).

For a 25,000 sq ft building, that comes to at least $5,000.00. The calculator below adjusts to your exact square footage.

Sewer Capacity Fee (Okaloosa County W&S, Mary Esther) — 4" outlet and Water Capacity Fee (Okaloosa County W&S, Mary Esther) — 1" meter are shown at the last published amount but have not been confirmed with the jurisdiction; they are included in the totals here. Verify before budgeting.

City Impact Fee Placeholder (Mary Esther, Office) is set by the city and has no published standard rate. Contact the levying jurisdiction or utility to verify before budgeting; it is not included as a dollar figure here.

View the full fee schedule
Water$1,200.00 one-time
  • Water Capacity Fee (Okaloosa County W&S, Mary Esther) — 1" meter
    Okaloosa County Water & Sewer
    [Audit 2026-07-17] City of Mary Esther operates its OWN water utility — Utilities Handbook adopted by Res. 22-03 sets city tap-in fees (commercial $2,500, incl. meter/curb stop/box/installation) and ready-to-serve rates; per the city's FAQ, OCWS serves only the area WEST of Hurlburt Field. Provider is therefore likely City of Mary Esther, not OCWS, and the OCWS Appendix A meter amounts here (1" $1,200) are placeholders. City's own capacity/system-development charge not yet traced (Utilities Handbook PDF would not render for either web_fetch or headless render). Unconfirmed — City Water Dept 850-243-3566.
    $1,200.00 one-timeRequires confirmation
Sewer$3,800.00 one-time
  • Sewer Capacity Fee (Okaloosa County W&S, Mary Esther) — 4" outlet
    Okaloosa County Water & Sewer
    [Audit 2026-07-17] Mary Esther runs its own water utility (Res. 22-03 Utilities Handbook); its sewer provider is unverified (city collection vs OCWS vs septic). OCWS 4" outlet $3,800 here is a placeholder. Unconfirmed — City 850-243-3566 / OCWS 850-651-7171.
    $3,800.00 one-timeRequires confirmation
City$0.00
County$0.00
  • County Impact Fee Placeholder (Mary Esther, Office)
    Okaloosa County levies NO county-wide impact or mobility fee on nonresidential development. Confirmed 2026-07-17 against the county's adopted Inspection & Permitting Fee schedule (Growth Management) and 2024 Developers Help Guide — neither contains an impact fee; LDC Appendix E Ch. 12 holds a mobility-fee framework with no adopted rate schedule. School-district impact fee is residential-only (no nonres bearing). Growth Management 850-651-7180.
    $0.00
Total (Mary Esther): $5,000.00 one-time (≈ $5,000.00 at 25,000 sq ft)
Sources last checked July 17, 2026Official fee schedule:Okaloosa County Water & Sewer
Amounts flagged "Requires confirmation" are the last published figures, included in the totals. Confirm them with the jurisdiction or utility before budgeting.

Where in Okaloosa County are you building?

Each jurisdiction applies its own fee schedule. Pick yours. Totals shown are for a 25,000 sq ft building, including one-time water/sewer fees (assuming a 1-inch meter). * = one-time water/sewer connection charges only; no per-sq-ft impact fee schedule sourced for that jurisdiction. = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.

Estimate your project in Mary Esther

Set to single-family. Drop a pin or search an address for site-specific fees.

Location

Loading map…
Search an address or click anywhere on the map to begin.

Select a location to begin

Once you select an address or drop a pin, we'll identify the responsible city and county and generate a fee breakdown.

Water & Sewer
Transportation
Parks
Schools
Fire & Police
General

How impact fees work in Florida

Florida impact fees are one-time charges on new development, governed by Section 163.31801, Florida Statutes (the Florida Impact Fee Act). The statute requires fees to be based on the most recent and localized data, spent on the infrastructure category they were collected for, and adopted by ordinance.

Since 2021, the law also limits how fast fees can rise: increases up to 25% phase in over two years, increases of 25–50% phase in over four years, and increases above 50% are allowed only with a demonstrated extraordinary-circumstances study and at least a two-thirds vote of the governing body.

Counties and cities can both levy impact fees. Inside an incorporated city, a project typically pays the county's countywide fees plus any municipal fees the city has adopted, which is why totals differ between a city and the unincorporated county around it.

Frequently asked questions

What are the total impact fees for a single-family home in Mary Esther, Florida?

A new single-family home in Mary Esther pays at least $4,800.00 per unit in combined impact fees (rates sourced July 17, 2026). This figure includes amounts that have not been confirmed and excludes fees with no published standard amount, so the full cost may be higher; verify before budgeting.

How much are commercial impact fees in Mary Esther?

Commercial development in Mary Esther pays no per-square-foot impact fees, but owes $5,000.00 in one-time water and sewer connection fees. This figure includes amounts that have not been confirmed and excludes fees with no published standard amount, so the full cost may be higher; verify before budgeting.

Does Mary Esther charge its own impact fees?

Yes. Mary Esther levies its own municipal impact or utility fees, and county-levied fees also apply inside city limits. The schedule on this page shows every fee that applies to development in Mary Esther, with the combined total.

Can Florida impact fees increase at any time?

No. Section 163.31801, Florida Statutes limits increases to 50% at most, phased in over two to four years, unless the local government makes extraordinary-circumstances findings and approves the increase by at least a two-thirds vote.

Fee amounts on this page are compiled from official published schedules and are provided for planning purposes only. Rates change, and project specifics (unit size, meter size, location within special districts) can alter what applies. Always verify current fees with the jurisdiction and utility before relying on them.

Compare unincorporated rates and every other city on the Okaloosa County impact fees page.

Missing a jurisdiction? Get in touch.

Request coverage for a city or county, report an issue, ask about enterprise access, or inquire about sponsorship opportunities. We typically reply within one business day.

0/1000