Santa Rosa County Impact Fees by Project Type
Where in Santa Rosa County Are You Building?
Each jurisdiction applies its own fee schedule. Pick yours. = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.
Unincorporated Santa Rosa County: Single-Family Impact Fees
A new single-family home in unincorporated Santa Rosa County pays $10,467.00 per unit in impact fees (rates sourced October 27, 2026). Of that, Santa Rosa County-levied fees account for $1,687.00 and municipal or utility fees for $8,780.00.
The largest line items are Sewer Capacity Fee (Unincorporated Santa Rosa County) — Pace Water System, 1 ERU × $5,500/ERU ($5,500.00), Water Capacity Fee (Unincorporated Santa Rosa County) — Pace Water System, 1 ERU × $2,200/ERU ($2,200.00) and Transportation Impact Fee (Santa Rosa County) ($1,687.00).
Some fees are tiered by unit size or building type; amounts reflect the representative tier noted in the schedule below.
View the Full Santa Rosa County Impact Fee Schedule
- Water Capacity Fee (Unincorporated Santa Rosa County) — Pace Water System, 1 ERU × $2,200/ERU$2,200.00Pace Water System, Inc.Pace Water System water tap fee: $2,200 per ERU (a single-family home is 1 ERU), unchanged since January 1, 2021 and listed in Pace's rates effective January 1, 2026. Pace is the largest water utility in unincorporated Santa Rosa County. Where water and sewer are both available, both taps are bought together, and a $500 reuse tap applies where reclaimed water is available. Pace notes that an additional location impact fee may apply in some service areas. Other unincorporated areas are served by Holley Navarre Water System and East Milton Water System (listed as options), by Midway, Point Baker, Bagdad-Garcon Point and the county's Navarre Beach utility, and by the City of Milton and Gulf Breeze Regional Water System at their in-city charges.
- Water Meter Installation Fee (Unincorporated Santa Rosa County) — Pace Water System, no separate charge$0.00Pace Water System, Inc.Pace Water System, the largest utility in unincorporated Santa Rosa County, publishes no separate meter installation charge; its one-time charge is the water tap fee shown with the capacity fees.
- Sewer Capacity Fee (Unincorporated Santa Rosa County) — Pace Water System, 1 ERU × $5,500/ERU$5,500.00Pace Water System, Inc.Pace Water System sewer tap fee: $5,500 per ERU (a single-family home is 1 ERU), unchanged since January 1, 2021 and listed in Pace's rates effective January 1, 2026. Pace is the largest sewer utility in unincorporated Santa Rosa County; only part of its area has central sewer, and homes on septic pay no sewer tap. Where water and sewer are both available, both taps are bought together. Pace notes that an additional location impact fee may apply in some service areas. Holley Navarre Water System sewer is listed as an option; the South Santa Rosa Utility area pays Gulf Breeze Regional Water System's $6,326 per ERU wastewater impact fee, and Navarre Beach is served by the county.
- Sewer Service Installation Fee (Unincorporated Santa Rosa County) — Pace Water System, no separate charge$0.00Pace Water System, Inc.Pace Water System, the largest utility in unincorporated Santa Rosa County, publishes no separate sewer service installation charge; its one-time charge is the sewer tap fee shown with the capacity fees.
- Municipal Impact Fee (Unincorporated Santa Rosa County)$0.00Santa Rosa CountyUnincorporated Santa Rosa County has no municipal (city) impact fee. The county transportation impact fee is the applicable overlay (listed separately).
- Transportation Impact Fee (Santa Rosa County)$1,687.00Santa Rosa CountySanta Rosa County Transportation Impact Fee: $1,687 per single-family detached dwelling (the category also covers a mobile home on a single-family lot), effective January 1, 2026 after a 3.1% CPI adjustment. The county code adjusts the fee each year by CPI, with at least 90 days of published notice before a new rate applies. Collected in the unincorporated county only, not inside Milton, Gulf Breeze or Jay. Revenue is spent in the road impact fee district where it is collected. Exempt: non-impacting accessory buildings, replacement buildings or dwellings, government property, and affordable housing as defined in F.S. 420.9071.
- Fire Impact Fee (Unincorporated Santa Rosa County) — Midway Fire District$1,080.00Midway Fire DistrictEach new home in unincorporated Santa Rosa County pays a fire impact fee set by the independent fire district serving the parcel. This row carries the highest of 5 rate districts, Midway Fire District, at $1,080 per dwelling unit (Resolution 25-01, adopted September 9, 2025), paid to the district before the county building permit. The others: Holley-Navarre $762, Navarre Beach $500, Pace $493 and Avalon Beach-Mulat $281.25 per unit. Areas served by the county volunteer fire departments (Allentown, Bagdad, Berrydale, East Milton, Harold, Jay, Munson and Skyline) pay no fire impact fee. Separate from the county transportation impact fee.
- Educational Facilities Impact Fee (Santa Rosa County)$0.00Santa Rosa County School DistrictSanta Rosa County adopted an educational facilities impact fee in January 2020 at $5,000 per single-family unit, but a court ruled the ordinance invalid and permanently enjoined the county from collecting it in January 2022. No educational facilities impact fee is currently charged. The only impact fee the county now collects is a transportation impact fee, which began applying to applications submitted on or after May 5, 2025 and rose 3.1 percent on January 1, 2026. The school district has been updating its educational facilities impact fee study.
Where in Santa Rosa County Are You Building?
Each jurisdiction applies its own fee schedule. Pick yours. = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.
Unincorporated Santa Rosa County: Multifamily Impact Fees
A new multifamily unit in unincorporated Santa Rosa County pays $9,593.00 per unit in impact fees (rates sourced October 27, 2026). Of that, Santa Rosa County-levied fees account for $813.00 and municipal or utility fees for $8,780.00.
The largest line items are Sewer Capacity Fee (Unincorporated Santa Rosa County, MF) — Pace Water System, 1 ERU × $5,500/ERU ($5,500.00), Water Capacity Fee (Unincorporated Santa Rosa County, MF) — Pace Water System, 1 ERU × $2,200/ERU ($2,200.00) and Fire Impact Fee (Unincorporated Santa Rosa County, MF) — Midway Fire District ($1,080.00).
Some fees are tiered by unit size or building type; amounts reflect the representative tier noted in the schedule below.
View the Full Santa Rosa County Impact Fee Schedule
- Water Capacity Fee (Unincorporated Santa Rosa County, MF) — Pace Water System, 1 ERU × $2,200/ERU$2,200.00Pace Water System, Inc.Pace Water System water tap fee: $2,200 per ERU, unchanged since January 1, 2021 (rates effective January 1, 2026). Pace publishes no multifamily ERU rule, so one ERU per unit is shown; a building served by one tap pays by its ERU count. A $500 reuse tap applies where reclaimed water is available, and Pace notes that an additional location impact fee may apply in some service areas. Holley Navarre Water System and East Milton Water System are listed as options; Midway, Point Baker, Bagdad-Garcon Point, Navarre Beach, the City of Milton and Gulf Breeze Regional Water System serve other areas.
- Water Meter Installation Fee (Unincorporated Santa Rosa County, MF) — Pace Water System, no separate charge$0.00Pace Water System, Inc.Pace Water System, the largest utility in unincorporated Santa Rosa County, publishes no separate meter installation charge; its one-time charge is the water tap fee shown with the capacity fees. Modeled per unit with its own meter; a building on one meter pays once.
- Sewer Capacity Fee (Unincorporated Santa Rosa County, MF) — Pace Water System, 1 ERU × $5,500/ERU$5,500.00Pace Water System, Inc.Pace Water System sewer tap fee: $5,500 per ERU, unchanged since January 1, 2021 (rates effective January 1, 2026). Pace publishes no multifamily ERU rule, so one ERU per unit is shown; a building served by one tap pays by its ERU count. Pace notes that an additional location impact fee may apply in some service areas. Holley Navarre Water System sewer is listed as an option; the South Santa Rosa Utility area pays Gulf Breeze Regional Water System's wastewater impact fee, and Navarre Beach is served by the county.
- Sewer Service Installation Fee (Unincorporated Santa Rosa County, MF) — Pace Water System, no separate charge$0.00Pace Water System, Inc.Pace Water System, the largest utility in unincorporated Santa Rosa County, publishes no separate sewer service installation charge; its one-time charge is the sewer tap fee shown with the capacity fees. Modeled per unit with its own meter; a building on one meter pays once.
- Municipal Impact Fee (Unincorporated Santa Rosa County, MF)$0.00Santa Rosa CountyUnincorporated Santa Rosa County has no municipal (city) impact fee. The county transportation impact fee is the applicable overlay (listed separately).
- Fire Impact Fee (Unincorporated Santa Rosa County, MF) — Midway Fire District$1,080.00Midway Fire DistrictEach new multifamily unit in unincorporated Santa Rosa County pays a fire impact fee set by the independent fire district serving the parcel. This row carries the highest of 5 rate districts, Midway Fire District, at $1,080 per residential unit (Resolution 25-01, adopted September 9, 2025), paid to the district before the county building permit. The others: Navarre Beach $500, Holley-Navarre $625, Pace $493 and Avalon Beach-Mulat $281.25 per unit. Areas served by the county volunteer fire departments (Allentown, Bagdad, Berrydale, East Milton, Harold, Jay, Munson and Skyline) pay no fire impact fee. Separate from the county transportation impact fee.
- Transportation Impact Fee (Santa Rosa County, MF)$813.00Multi-family, high riseSanta Rosa CountySanta Rosa County Transportation Impact Fee, multifamily high-rise (a building of more than two stories): $813 per dwelling unit, effective January 1, 2026 after a 3.1% CPI adjustment, adjusted by CPI each year. Collected in the unincorporated county only. Low-rise multifamily (two stories or less) is $1,207 per unit, and a mobile home park or RV park space is $1,275.
- Educational Facilities Impact Fee (Santa Rosa County, MF)$0.00Santa Rosa County School DistrictSanta Rosa County adopted an educational facilities impact fee in January 2020, but a court ruled the ordinance invalid and permanently enjoined the county from collecting it in January 2022. No educational facilities impact fee is currently charged on multifamily units. The only impact fee the county now collects is a transportation impact fee, which began applying to applications submitted on or after May 5, 2025 and rose 3.1 percent on January 1, 2026.
Where in Santa Rosa County Are You Building?
Each jurisdiction applies its own fee schedule. Pick yours. Totals shown are for a 50,000 sq ft building, including one-time water/sewer fees (assuming a 1-inch meter). * = one-time water/sewer connection charges only; no per-sq-ft impact fee schedule sourced for that jurisdiction. = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.
Unincorporated Santa Rosa County: Commercial Impact Fees
Commercial development in unincorporated Santa Rosa County pays $4.20 per square foot in impact fees, plus $7,700.00 in one-time water and sewer connection fees (rates sourced October 27, 2026).
For a 50,000 sq ft building, that comes to about $217,900.00. The calculator below adjusts to your exact square footage.
The largest line items are Sewer Capacity Fee (Unincorporated Santa Rosa County) — Pace Water System, 1 ERU × $5,500/ERU ($5,500.00 one-time), Water Capacity Fee (Unincorporated Santa Rosa County) — Pace Water System, 1 ERU × $2,200/ERU ($2,200.00 one-time) and Transportation Impact Fee (Santa Rosa County, Commercial) ($2.86/sq ft).
Water and sewer connection fees assume a 1-inch meter; larger services pay more. See the meter-size tiers in the source schedules.
View the Full Santa Rosa County Impact Fee Schedule
- Water Capacity Fee (Unincorporated Santa Rosa County) — Pace Water System, 1 ERU × $2,200/ERU$2,200.00 one-timePace Water System, Inc.Pace Water System water tap fee: $2,200 per ERU, shown at 1 ERU, unchanged since January 1, 2021 and listed in Pace's rates effective January 1, 2026. Pace publishes no nonresidential ERU method, so the ERU count for a larger project is set by Pace. Pace notes that an additional location impact fee may apply in some service areas. Pace is the largest water utility in unincorporated Santa Rosa County. Other unincorporated areas are served by Holley Navarre Water System (listed as an option), by East Milton Water System (its commercial impact fee is based on consumption and not published), by Midway, Point Baker, Bagdad-Garcon Point and the county's Navarre Beach utility, and by the City of Milton and Gulf Breeze Regional Water System.
- Sewer Capacity Fee (Unincorporated Santa Rosa County) — Pace Water System, 1 ERU × $5,500/ERU$5,500.00 one-timePace Water System, Inc.Pace Water System sewer tap fee: $5,500 per ERU, shown at 1 ERU, unchanged since January 1, 2021 and listed in Pace's rates effective January 1, 2026. Pace publishes no nonresidential ERU method, so the ERU count for a larger project is set by Pace. Pace notes that an additional location impact fee may apply in some service areas. Pace is the largest sewer utility in unincorporated Santa Rosa County. Other sewered areas are served by Holley Navarre Water System (listed as an option), by Gulf Breeze Regional Water System in the South Santa Rosa area, by the City of Milton and Sundial, and by the county's Navarre Beach utility; many rural parcels use septic systems.
- Municipal Impact Fee (Unincorporated Santa Rosa County, Commercial)$0.00No municipal impact fee applies in unincorporated Santa Rosa County; the applicable overlay is the county transportation impact fee.
- Transportation Impact Fee (Santa Rosa County, Commercial)$2.86/sq ftSanta Rosa CountyApplies to development in the unincorporated areas of Santa Rosa County only. Quoted per 1,000 sq ft of retail/commercial floor area. Rate reflects the annual CPI adjustment effective January 1, 2026; the next annual adjustment takes effect January 1, 2027.
- Fire Impact Fee (Unincorporated Santa Rosa County, Commercial) — Midway Fire District$1.34/sq ftMidway Fire DistrictNonresidential development in unincorporated Santa Rosa County pays a fire impact fee set by the independent fire district serving the parcel, paid to the district before the county building permit. This row carries the highest of 5 rate districts for retail and commercial space, Midway Fire District, at $1,344 per 1,000 sq ft (general retail and restaurants; Resolution 25-01, adopted September 9, 2025). The others: Holley-Navarre $769 per 1,000 sq ft, Avalon Beach-Mulat $0.5175 per sq ft, Pace $0.46 per sq ft and Navarre Beach $0.41 per sq ft. Areas served by the county volunteer fire departments pay no fire impact fee. Separate from the county transportation impact fee.
Where in Santa Rosa County Are You Building?
Each jurisdiction applies its own fee schedule. Pick yours. Totals shown are for a 50,000 sq ft building, including one-time water/sewer fees (assuming a 1-inch meter). * = one-time water/sewer connection charges only; no per-sq-ft impact fee schedule sourced for that jurisdiction. = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.
Unincorporated Santa Rosa County: Industrial Impact Fees
Industrial development in unincorporated Santa Rosa County pays $1.22 per square foot in impact fees, plus $7,700.00 in one-time water and sewer connection fees (rates sourced October 27, 2026).
For a 50,000 sq ft building, that comes to about $68,475.00. The calculator below adjusts to your exact square footage.
The largest line items are Sewer Capacity Fee (Unincorporated Santa Rosa County) — Pace Water System, 1 ERU × $5,500/ERU ($5,500.00 one-time), Water Capacity Fee (Unincorporated Santa Rosa County) — Pace Water System, 1 ERU × $2,200/ERU ($2,200.00 one-time) and Transportation Impact Fee (Santa Rosa County, Industrial) ($0.70/sq ft).
Water and sewer connection fees assume a 1-inch meter; larger services pay more. See the meter-size tiers in the source schedules.
View the Full Santa Rosa County Impact Fee Schedule
- Water Capacity Fee (Unincorporated Santa Rosa County) — Pace Water System, 1 ERU × $2,200/ERU$2,200.00 one-timePace Water System, Inc.Pace Water System water tap fee: $2,200 per ERU, shown at 1 ERU, unchanged since January 1, 2021 and listed in Pace's rates effective January 1, 2026. Pace publishes no nonresidential ERU method, so the ERU count for a larger project is set by Pace. Pace notes that an additional location impact fee may apply in some service areas. Pace is the largest water utility in unincorporated Santa Rosa County. Other unincorporated areas are served by Holley Navarre Water System (listed as an option), by East Milton Water System (its commercial impact fee is based on consumption and not published), by Midway, Point Baker, Bagdad-Garcon Point and the county's Navarre Beach utility, and by the City of Milton and Gulf Breeze Regional Water System.
- Sewer Capacity Fee (Unincorporated Santa Rosa County) — Pace Water System, 1 ERU × $5,500/ERU$5,500.00 one-timePace Water System, Inc.Pace Water System sewer tap fee: $5,500 per ERU, shown at 1 ERU, unchanged since January 1, 2021 and listed in Pace's rates effective January 1, 2026. Pace publishes no nonresidential ERU method, so the ERU count for a larger project is set by Pace. Pace notes that an additional location impact fee may apply in some service areas. Pace is the largest sewer utility in unincorporated Santa Rosa County. Other sewered areas are served by Holley Navarre Water System (listed as an option), by Gulf Breeze Regional Water System in the South Santa Rosa area, by the City of Milton and Sundial, and by the county's Navarre Beach utility; many rural parcels use septic systems.
- Municipal Impact Fee (Unincorporated Santa Rosa County, Industrial)$0.00No municipal impact fee applies in unincorporated Santa Rosa County; the applicable overlay is the county transportation impact fee.
- Transportation Impact Fee (Santa Rosa County, Industrial)$0.70/sq ftSanta Rosa CountyApplies to development in the unincorporated areas of Santa Rosa County only. Quoted per 1,000 sq ft of general industrial floor area. Rate reflects the annual CPI adjustment effective January 1, 2026; the next annual adjustment takes effect January 1, 2027.
- Fire Impact Fee (Unincorporated Santa Rosa County, Industrial) — Avalon Beach-Mulat Fire Protection District, $0.5175 per sq ft$0.52/sq ftAvalon Beach-Mulat Fire Protection DistrictNonresidential development in unincorporated Santa Rosa County pays a fire impact fee set by the independent fire district serving the parcel, paid to the district before the county building permit. This row carries the highest of 5 rate districts for industrial space, Avalon Beach-Mulat Fire Protection District, at $0.5175 per sq ft from August 3, 2026, the first of four yearly 12.5% increases (later $0.5750, $0.6325, then $0.6900). The others: Pace $0.46 per sq ft, Navarre Beach $0.41 per sq ft, Midway $56 per 1,000 sq ft and Holley-Navarre $27 per 1,000 sq ft. Areas served by the county volunteer fire departments pay no fire impact fee. Separate from the county transportation impact fee.
Where in Santa Rosa County Are You Building?
Each jurisdiction applies its own fee schedule. Pick yours. Totals shown are for a 25,000 sq ft building, including one-time water/sewer fees (assuming a 1-inch meter). * = one-time water/sewer connection charges only; no per-sq-ft impact fee schedule sourced for that jurisdiction. = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.
Unincorporated Santa Rosa County: Office Impact Fees
Office development in unincorporated Santa Rosa County pays $1.99 per square foot in impact fees, plus $7,700.00 in one-time water and sewer connection fees (rates sourced October 27, 2026).
For a 25,000 sq ft building, that comes to about $57,487.50. The calculator below adjusts to your exact square footage.
The largest line items are Sewer Capacity Fee (Unincorporated Santa Rosa County) — Pace Water System, 1 ERU × $5,500/ERU ($5,500.00 one-time), Water Capacity Fee (Unincorporated Santa Rosa County) — Pace Water System, 1 ERU × $2,200/ERU ($2,200.00 one-time) and Transportation Impact Fee (Santa Rosa County, Office) ($1.47/sq ft).
Water and sewer connection fees assume a 1-inch meter; larger services pay more. See the meter-size tiers in the source schedules.
View the Full Santa Rosa County Impact Fee Schedule
- Water Capacity Fee (Unincorporated Santa Rosa County) — Pace Water System, 1 ERU × $2,200/ERU$2,200.00 one-timePace Water System, Inc.Pace Water System water tap fee: $2,200 per ERU, shown at 1 ERU, unchanged since January 1, 2021 and listed in Pace's rates effective January 1, 2026. Pace publishes no nonresidential ERU method, so the ERU count for a larger project is set by Pace. Pace notes that an additional location impact fee may apply in some service areas. Pace is the largest water utility in unincorporated Santa Rosa County. Other unincorporated areas are served by Holley Navarre Water System (listed as an option), by East Milton Water System (its commercial impact fee is based on consumption and not published), by Midway, Point Baker, Bagdad-Garcon Point and the county's Navarre Beach utility, and by the City of Milton and Gulf Breeze Regional Water System.
- Sewer Capacity Fee (Unincorporated Santa Rosa County) — Pace Water System, 1 ERU × $5,500/ERU$5,500.00 one-timePace Water System, Inc.Pace Water System sewer tap fee: $5,500 per ERU, shown at 1 ERU, unchanged since January 1, 2021 and listed in Pace's rates effective January 1, 2026. Pace publishes no nonresidential ERU method, so the ERU count for a larger project is set by Pace. Pace notes that an additional location impact fee may apply in some service areas. Pace is the largest sewer utility in unincorporated Santa Rosa County. Other sewered areas are served by Holley Navarre Water System (listed as an option), by Gulf Breeze Regional Water System in the South Santa Rosa area, by the City of Milton and Sundial, and by the county's Navarre Beach utility; many rural parcels use septic systems.
- Municipal Impact Fee (Unincorporated Santa Rosa County, Office)$0.00No municipal impact fee applies in unincorporated Santa Rosa County; the applicable overlay is the county transportation impact fee.
- Transportation Impact Fee (Santa Rosa County, Office)$1.47/sq ftSanta Rosa CountyApplies to development in the unincorporated areas of Santa Rosa County only. Quoted per 1,000 sq ft of office floor area. Rate reflects the annual CPI adjustment effective January 1, 2026; the next annual adjustment takes effect January 1, 2027.
- Fire Impact Fee (Unincorporated Santa Rosa County, Office) — Avalon Beach-Mulat Fire Protection District, $0.5175 per sq ft$0.52/sq ftAvalon Beach-Mulat Fire Protection DistrictNonresidential development in unincorporated Santa Rosa County pays a fire impact fee set by the independent fire district serving the parcel, paid to the district before the county building permit. This row carries the highest of 5 rate districts for office space, Avalon Beach-Mulat Fire Protection District, at $0.5175 per sq ft from August 3, 2026, the first of four yearly 12.5% increases (later $0.5750, $0.6325, then $0.6900). The others: Midway $471 per 1,000 sq ft, Pace $0.46 per sq ft, Navarre Beach $0.41 per sq ft and Holley-Navarre $255 per 1,000 sq ft. Areas served by the county volunteer fire departments pay no fire impact fee. Separate from the county transportation impact fee.
Santa Rosa County Impact Fee Calculator
Estimate impact fees for your project. Set to single-family. Drop a pin or search an address for site-specific fees.
Location
Select a location to begin
Once you select an address or drop a pin, we'll identify the responsible city and county and generate a fee breakdown.
How Impact Fees Work in Florida
Florida impact fees are one-time charges on new development, governed by Section 163.31801, Florida Statutes (the Florida Impact Fee Act). The statute requires fees to be based on the most recent and localized data, spent on the infrastructure category they were collected for, and adopted by ordinance.
Since a 2021 amendment (Ch. 2021-63, Laws of Florida), the law also limits how fast fees can rise: increases up to 25% phase in over two years, increases of 25–50% phase in over four years, and increases above 50% are allowed only with a demonstrated extraordinary-circumstances study and at least a two-thirds vote of the governing body.
Counties and cities can both levy impact fees. Inside an incorporated city, a project typically pays the county's countywide fees plus any municipal fees the city has adopted, which is why totals differ between a city and the unincorporated county around it.
New to impact fees? Our plain-English guide explains what they cover, who pays them, and why they exist.
Summary current as of September 2026. This is an editorial summary, not legal advice; see the official statute text and our terms of use.
Santa Rosa County Impact Fee FAQs
What are single-family impact fees in Santa Rosa County, Florida?
A new single-family home in unincorporated Santa Rosa County pays $10,467.00 per unit in impact fees (rates sourced October 27, 2026). Inside city limits, fees are set by each city's own schedule and may be completely different. See the city pages for their rates.
How much are multifamily impact fees in Santa Rosa County?
Multifamily development in unincorporated Santa Rosa County pays $9,593.00 per unit in impact fees (rates sourced October 27, 2026). Rates inside city limits depend on the municipality. Pick your city on this page.
How much are commercial impact fees in Santa Rosa County?
Commercial development in unincorporated Santa Rosa County pays $4.20 per square foot in impact fees, plus $7,700.00 in one-time water and sewer connection fees (assuming a 1-inch meter), about $217,900.00 for a 50,000 sq ft building.
Do Navarre and Pace pay Santa Rosa County impact fees?
Yes. Navarre, Pace and East Milton are unincorporated, so new construction there pays the unincorporated Santa Rosa County schedule on this page, not a city schedule. Search a specific address in the calculator below to confirm it sits outside every city limit.
Do cities in Santa Rosa County charge their own impact fees?
Yes. Every incorporated city applies its own fee schedule. 3 of 3 cities in Santa Rosa County levy municipal impact or utility fees; each city page shows the full schedule that applies inside its limits.
Can Florida impact fees increase at any time?
No. Section 163.31801, Florida Statutes limits increases to 50% at most, phased in over two to four years, unless the local government makes extraordinary-circumstances findings and approves the increase by at least a two-thirds vote.
Fee amounts on this page are compiled from official published schedules and are provided for planning purposes only. Rates change, and project specifics (unit size, meter size, location within special districts) can alter what applies. Always verify current fees with the jurisdiction and utility before relying on them.