Unincorporated St. Lucie County: Single-Family Impact Fees
A new single-family home in unincorporated St. Lucie County pays $27,277.89 per unit in impact fees (rates sourced July 28, 2026). All of it is levied by St. Lucie County.
The largest line items are County School/Educational Impact Fee (SFR) ($6,786.00), County Road/Transportation Impact Fee (SFR) ($5,771.00) and Water Connection Fee (SLCU) ($5,273.00).
Some fees are tiered by unit size or building type; amounts reflect the representative tier noted in the schedule below.
View the full St. Lucie County impact fee schedule
- Water Connection Fee (SLCU)$5,273.00St. Lucie County Water & Wastewater DistrictSt. Lucie County Utilities water capacity (connection) fee: $5,273 per ERC (single-family = 1 ERC), Resolution 25-125 effective August 2025. Meter installation and the water lateral are charged at cost. Some unincorporated parcels are served by private wells.
- Sewer Connection Fee (SLCU)$4,925.00St. Lucie County Water & Wastewater DistrictSt. Lucie County Utilities wastewater capacity (connection) fee: $4,925 per ERC (single-family = 1 ERC), Resolution 25-125 effective August 2025. Some unincorporated parcels are on septic systems.
- Municipal Impact Fee — N/A (Unincorporated)$0.00St. Lucie County (unincorporated)The unincorporated area levies no municipal impact fees; St. Lucie County impact fees apply.
- County School/Educational Impact Fee (SFR)$6,786.00St. Lucie County School BoardSt. Lucie County educational (school) impact fee: $6,786 per single-family dwelling, effective 1/1/2026. Assessed countywide on new residential construction. The schedule is updated around October 1 each year.
- County Road/Transportation Impact Fee (SFR)$5,771.00Unincorporated zone, SF <2,400 sq ftSt. Lucie CountySt. Lucie County road impact fee, unincorporated mainland benefit zone: $5,771 per single-family home under 2,400 sq ft (canonical size), effective 1/1/2026. Larger homes pay more ($7,054 for 2,400-3,499 sq ft; $7,160 for 3,500+ sq ft) and the Hutchinson Island zones carry different rates. Income-restricted homes under 2,000 sq ft pay reduced rates. A significant road-fee increase was proposed in 2025 but postponed.
- County Parks Impact Fee (SFR)$2,560.50St. Lucie CountySt. Lucie County parks & recreation impact fee: $2,560.50 per single-family dwelling, effective 1/1/2026. Updated around October 1 each year.
- County Fire/EMS Impact Fee (SFR)$650.00St. Lucie County Fire DistrictSt. Lucie County Fire District impact fee: $650 per single-family dwelling, effective 1/1/2026. Applies countywide (the Fire District serves the entire county).
- County Public Buildings Impact Fee (SFR)$547.50St. Lucie CountySt. Lucie County public buildings impact fee: $547.50 per single-family dwelling, effective 1/1/2026.
- County Library Impact Fee (SFR)$395.89St. Lucie CountySt. Lucie County library impact fee: $395.89 per single-family dwelling, effective 1/1/2026. Updated around October 1 each year.
- County Law Enforcement Impact Fee (SFR)$369.00St. Lucie CountySt. Lucie County law enforcement impact fee: $369.00 per single-family dwelling, effective 1/1/2026.
Where in St. Lucie County are you building?
Each jurisdiction applies its own fee schedule. Pick yours.
Unincorporated St. Lucie County: Multifamily Impact Fees
A new multifamily unit in unincorporated St. Lucie County pays $20,819.00 per unit in impact fees (rates sourced July 28, 2026). All of it is levied by St. Lucie County.
The largest line items are Water Connection Fee (SLCU) (MF) ($5,273.00), Sewer Connection Fee (SLCU) (MF) ($4,925.00) and County School/Educational Impact Fee (MF) ($3,470.00).
Some fees are tiered by unit size or building type; amounts reflect the representative tier noted in the schedule below.
View the full St. Lucie County impact fee schedule
- Water Connection Fee (SLCU) (MF)$5,273.00St. Lucie County Water & Wastewater DistrictSt. Lucie County Utilities water capacity fee: $5,273 per ERC (Resolution 25-125, effective August 2025). Multifamily is charged per ERC; a master-metered building's per-unit charge scales with its total ERCs.
- Sewer Connection Fee (SLCU) (MF)$4,925.00St. Lucie County Water & Wastewater DistrictSt. Lucie County Utilities wastewater capacity fee: $4,925 per ERC (Resolution 25-125, effective August 2025). Multifamily is charged per ERC; a master-metered building's per-unit charge scales with its total ERCs.
- Municipal Impact Fee — N/A (Unincorporated) (MF)$0.00St. Lucie County (unincorporated)The unincorporated area levies no municipal impact fees; St. Lucie County impact fees apply.
- County School/Educational Impact Fee (MF)$3,470.00St. Lucie County School BoardSt. Lucie County educational (school) impact fee: $3,470 per multifamily dwelling unit, effective 1/1/2026. Assessed countywide.
- County Road/Transportation Impact Fee (MF)$3,181.00Unincorporated zone, MF 4+ stories, 750-1,499 sq ftSt. Lucie CountySt. Lucie County road impact fee (multifamily), unincorporated mainland zone: $3,181 per unit for a mid-rise (4+ story) building, ~1,000 sq ft unit, effective 1/1/2026. Rates vary by building height, unit size and benefit zone (low-rise 1-3 story units pay more).
- County Parks Impact Fee (MF)$2,284.50St. Lucie CountySt. Lucie County parks & recreation impact fee: $2,284.50 per multifamily dwelling unit, effective 1/1/2026.
- County Fire/EMS Impact Fee (MF)$637.00St. Lucie County Fire DistrictSt. Lucie County Fire District impact fee: $637 per multifamily unit (buildings 3+ stories; 1-2 story buildings $502), effective 1/1/2026. Applies countywide.
- County Public Buildings Impact Fee (MF)$490.50St. Lucie CountySt. Lucie County public buildings impact fee: $490.50 per multifamily dwelling unit, effective 1/1/2026.
- County Library Impact Fee (MF)$295.50St. Lucie CountySt. Lucie County library impact fee: $295.50 per multifamily unit (buildings 3+ stories; 1-2 story buildings $288), effective 1/1/2026.
- County Law Enforcement Impact Fee (MF)$262.50St. Lucie CountySt. Lucie County law enforcement impact fee: $262.50 per multifamily unit (buildings 3+ stories; 1-2 story $256.50), effective 1/1/2026.
Where in St. Lucie County are you building?
Each jurisdiction applies its own fee schedule. Pick yours. Totals shown are for a 50,000 sq ft building, including one-time water/sewer fees (assuming a 1-inch meter). = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.
Unincorporated St. Lucie County: Commercial Impact Fees
Commercial development in unincorporated St. Lucie County pays $8.83 per square foot in impact fees, plus $10,198.00 in one-time water and sewer connection fees (rates sourced July 28, 2026).
For a 50,000 sq ft building, that comes to about $451,509.50. The calculator below adjusts to your exact square footage.
The largest line items are Water Capacity/Connection Fee (SLCU) — 1 ERC ($5,273.00 one-time), Sewer Capacity/Connection Fee (SLCU) — 1 ERC ($4,925.00 one-time) and County Roads/Multimodal Impact Fee (St. Lucie County, Commercial) ($7.13/sq ft).
View the full St. Lucie County impact fee schedule
- Water Capacity/Connection Fee (SLCU) — 1 ERC$5,273.00 one-timeSt. Lucie County Utilities water capital facility charge per ERC (Res. 25-125, effective Aug 2025). Nonres charge assigned by ERC; amount shown is the 1-ERC minimum.
- Sewer Capacity/Connection Fee (SLCU) — 1 ERC$4,925.00 one-timeSt. Lucie County Utilities wastewater capital facility charge per ERC (Res. 25-125, effective Aug 2025). Nonres charge assigned by ERC; amount shown is the 1-ERC minimum.
- Municipal Impact Fee — N/A (St. Lucie County Unincorporated, Commercial)$0.00
- County Roads/Multimodal Impact Fee (St. Lucie County, Commercial)$7.13/sq ftRoad/multimodal impact fee, effective Oct 1, 2025 (Ord. 2025-27); benefit-zone rate for this jurisdiction. Charged countywide, including within municipalities. Scheduled step-ups Oct 1, 2026 and Oct 1, 2027.
- County Public Buildings Impact Fee (St. Lucie County, Commercial)$0.71/sq ftCounty public buildings impact fee, effective October 2025. Charged countywide, including within municipalities.
- County Fire/EMS Impact Fee (St. Lucie County, Commercial)$0.62/sq ftFire/EMS impact fee, effective January 2026. Charged countywide, including within municipalities.
- County Law Enforcement Impact Fee (St. Lucie County, Commercial)$0.36/sq ftLaw enforcement impact fee, effective October 2024. Charged countywide, including within municipalities.
- County Library Impact Fee (St. Lucie County, Commercial)$0.00County library impact fee is not levied on nonresidential development (residential-only).
- County Parks Impact Fee (St. Lucie County, Commercial)$0.00County parks impact fee is not levied on nonresidential development (residential-only).
Where in St. Lucie County are you building?
Each jurisdiction applies its own fee schedule. Pick yours. Totals shown are for a 50,000 sq ft building, including one-time water/sewer fees (assuming a 1-inch meter). = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.
Unincorporated St. Lucie County: Industrial Impact Fees
Industrial development in unincorporated St. Lucie County pays $1.52 per square foot in impact fees, plus $10,198.00 in one-time water and sewer connection fees (rates sourced July 28, 2026).
For a 50,000 sq ft building, that comes to about $86,060.50. The calculator below adjusts to your exact square footage.
The largest line items are Water Capacity/Connection Fee (SLCU) — 1 ERC ($5,273.00 one-time), Sewer Capacity/Connection Fee (SLCU) — 1 ERC ($4,925.00 one-time) and County Roads/Multimodal Impact Fee (St. Lucie County, Industrial) ($1.24/sq ft).
View the full St. Lucie County impact fee schedule
- Water Capacity/Connection Fee (SLCU) — 1 ERC$5,273.00 one-timeSt. Lucie County Utilities water capital facility charge per ERC (Res. 25-125, effective Aug 2025). Nonres charge assigned by ERC; amount shown is the 1-ERC minimum.
- Sewer Capacity/Connection Fee (SLCU) — 1 ERC$4,925.00 one-timeSt. Lucie County Utilities wastewater capital facility charge per ERC (Res. 25-125, effective Aug 2025). Nonres charge assigned by ERC; amount shown is the 1-ERC minimum.
- Municipal Impact Fee — N/A (St. Lucie County Unincorporated, Industrial)$0.00
- County Roads/Multimodal Impact Fee (St. Lucie County, Industrial)$1.24/sq ftRoad/multimodal impact fee, effective Oct 1, 2025 (Ord. 2025-27); benefit-zone rate for this jurisdiction. Charged countywide, including within municipalities. Scheduled step-ups Oct 1, 2026 and Oct 1, 2027.
- County Public Buildings Impact Fee (St. Lucie County, Industrial)$0.11/sq ftCounty public buildings impact fee, effective October 2025. Charged countywide, including within municipalities.
- County Fire/EMS Impact Fee (St. Lucie County, Industrial)$0.09/sq ftFire/EMS impact fee, effective January 2026. Charged countywide, including within municipalities.
- County Law Enforcement Impact Fee (St. Lucie County, Industrial)$0.07/sq ftLaw enforcement impact fee, effective October 2024. Charged countywide, including within municipalities.
- County Parks Impact Fee (St. Lucie County, Industrial)$0.00County parks impact fee is not levied on nonresidential development (residential-only).
- County Library Impact Fee (St. Lucie County, Industrial)$0.00County library impact fee is not levied on nonresidential development (residential-only).
Where in St. Lucie County are you building?
Each jurisdiction applies its own fee schedule. Pick yours. Totals shown are for a 25,000 sq ft building, including one-time water/sewer fees (assuming a 1-inch meter). = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.
Unincorporated St. Lucie County: Office Impact Fees
Office development in unincorporated St. Lucie County pays $5.54 per square foot in impact fees, plus $10,198.00 in one-time water and sewer connection fees (rates sourced July 28, 2026).
For a 25,000 sq ft building, that comes to about $148,757.50. The calculator below adjusts to your exact square footage.
The largest line items are Water Capacity/Connection Fee (SLCU) — 1 ERC ($5,273.00 one-time), Sewer Capacity/Connection Fee (SLCU) — 1 ERC ($4,925.00 one-time) and County Roads/Multimodal Impact Fee (St. Lucie County, Office) ($4.18/sq ft).
View the full St. Lucie County impact fee schedule
- Water Capacity/Connection Fee (SLCU) — 1 ERC$5,273.00 one-timeSt. Lucie County Utilities water capital facility charge per ERC (Res. 25-125, effective Aug 2025). Nonres charge assigned by ERC; amount shown is the 1-ERC minimum.
- Sewer Capacity/Connection Fee (SLCU) — 1 ERC$4,925.00 one-timeSt. Lucie County Utilities wastewater capital facility charge per ERC (Res. 25-125, effective Aug 2025). Nonres charge assigned by ERC; amount shown is the 1-ERC minimum.
- Municipal Impact Fee — N/A (St. Lucie County Unincorporated, Office)$0.00
- County Roads/Multimodal Impact Fee (St. Lucie County, Office)$4.18/sq ftRoad/multimodal impact fee, effective Oct 1, 2025 (Ord. 2025-27); benefit-zone rate for this jurisdiction. Charged countywide, including within municipalities. Scheduled step-ups Oct 1, 2026 and Oct 1, 2027.
- County Fire/EMS Impact Fee (St. Lucie County, Office)$0.70/sq ftFire/EMS impact fee, effective January 2026. Charged countywide, including within municipalities.
- County Public Buildings Impact Fee (St. Lucie County, Office)$0.48/sq ftCounty public buildings impact fee, effective October 2025. Charged countywide, including within municipalities.
- County Law Enforcement Impact Fee (St. Lucie County, Office)$0.17/sq ftLaw enforcement impact fee, effective October 2024. Charged countywide, including within municipalities.
- County Library Impact Fee (St. Lucie County, Office)$0.00County library impact fee is not levied on nonresidential development (residential-only).
- County Parks Impact Fee (St. Lucie County, Office)$0.00County parks impact fee is not levied on nonresidential development (residential-only).
St. Lucie County impact fee calculator
Estimate impact fees for your project. Set to single-family. Drop a pin or search an address for site-specific fees.
Location
Select a location to begin
Once you select an address or drop a pin, we'll identify the responsible city and county and generate a fee breakdown.
How impact fees work in Florida
Florida impact fees are one-time charges on new development, governed by Section 163.31801, Florida Statutes (the Florida Impact Fee Act). The statute requires fees to be based on the most recent and localized data, spent on the infrastructure category they were collected for, and adopted by ordinance.
Since 2021, the law also limits how fast fees can rise: increases up to 25% phase in over two years, increases of 25–50% phase in over four years, and increases above 50% are allowed only with a demonstrated extraordinary-circumstances study and at least a two-thirds vote of the governing body.
Counties and cities can both levy impact fees. Inside an incorporated city, a project typically pays the county's countywide fees plus any municipal fees the city has adopted, which is why totals differ between a city and the unincorporated county around it.
If you're still asking what are impact fees, start with our guide to the definition, common categories, and legal basis.
St. Lucie County impact fee FAQs
What are single-family impact fees in St. Lucie County, Florida?
A new single-family home in unincorporated St. Lucie County pays $27,277.89 per unit in impact fees (rates sourced July 28, 2026). Inside city limits, fees are set by each city's own schedule and may be completely different. See the city pages for their rates.
How much are multifamily impact fees in St. Lucie County?
Multifamily development in unincorporated St. Lucie County pays $20,819.00 per unit in impact fees (rates sourced July 28, 2026). Rates inside city limits depend on the municipality. Pick your city on this page.
How much are commercial impact fees in St. Lucie County?
Commercial development in unincorporated St. Lucie County pays $8.83 per square foot in impact fees, plus $10,198.00 in one-time water and sewer connection fees, about $451,509.50 for a 50,000 sq ft building.
Do cities in St. Lucie County charge their own impact fees?
Yes. Every incorporated city applies its own fee schedule. 2 of 3 cities in St. Lucie County levy municipal impact or utility fees; each city page shows the full schedule that applies inside its limits.
Can Florida impact fees increase at any time?
No. Section 163.31801, Florida Statutes limits increases to 50% at most, phased in over two to four years, unless the local government makes extraordinary-circumstances findings and approves the increase by at least a two-thirds vote.
Fee amounts on this page are compiled from official published schedules and are provided for planning purposes only. Rates change, and project specifics (unit size, meter size, location within special districts) can alter what applies. Always verify current fees with the jurisdiction and utility before relying on them.