North Charleston applies its own fee schedule. Charleston County does not currently add county-level impact fees inside city limits. A new single-family home pays $8,320.00 per unit (rates sourced ). The full breakdown is below.

North Charleston Impact Fees by Project Type

North Charleston: Single-Family Impact Fees

A new single-family home in North Charleston pays $8,320.00 per unit in impact fees (rates sourced November 18, 2026). Every line item is levied at the municipal or utility level.

The largest line items are Water Impact + Tap Fee — Charleston Water System, $4,620 impact + $1,200 tap ($5,820.00) and Sewer Connection Fee — North Charleston Sewer District, 1.0 REU × $2,500/REU ($2,500.00).

Some fees are tiered by unit size or building type; amounts reflect the representative tier noted in the schedule below.

View the Full North Charleston Impact Fee Schedule
Water$5,820.00
  • Water Impact + Tap Fee — Charleston Water System, $4,620 impact + $1,200 tap
    Charleston Water System, 3/4" full tap
    Charleston Water System
    Charleston Water System water impact fee plus tap fee for a 3/4 inch full tap: $4,620 + $1,200. The impact fee rises to $5,115 on January 1, 2027. The full tap applies where Charleston Water System makes the whole service connection; on a lot whose service line the developer built, only the $500 meter set applies (option shown).
    $5,820.00
Sewer$2,500.00
City$0.00
County$0.00
  • County Impact Fee (Charleston County)
    Charleston County
    Charleston County levies no development impact fee. County Council discussed adopting one in March 2025; no impact fee ordinance has followed.
    $0.00
Total (North Charleston): $8,320.00
Sources last checked Official fee schedules:Charleston Water System North Charleston Sewer District City of North Charleston Charleston County

North Charleston: Multifamily Impact Fees

A new multifamily unit in North Charleston pays $7,695.00 per unit in impact fees (rates sourced November 18, 2026). Every line item is levied at the municipal or utility level.

The largest line items are Water Impact + Tap Fee (MF) — Charleston Water System, $4,620 impact + $1,200 tap ($5,820.00) and Sewer Connection Fee (MF) — North Charleston Sewer District, 0.75 REU × $2,500/REU ($1,875.00).

Some fees are tiered by unit size or building type; amounts reflect the representative tier noted in the schedule below.

View the Full North Charleston Impact Fee Schedule
Water$5,820.00
  • Water Impact + Tap Fee (MF) — Charleston Water System, $4,620 impact + $1,200 tap
    Charleston Water System, 3/4" full tap
    Charleston Water System
    Charleston Water System water impact fee plus tap fee for a 3/4 inch full tap: $4,620 + $1,200. The impact fee rises to $5,115 on January 1, 2027. The full tap applies where Charleston Water System makes the whole service connection; on a lot whose service line the developer built, only the $500 meter set applies (option shown). A building on one connection pays once.
    $5,820.00
Sewer$1,875.00
City$0.00
County$0.00
  • County Impact Fee (Charleston County, MF)
    Charleston County
    Charleston County levies no development impact fee. County Council discussed adopting one in March 2025; no impact fee ordinance has followed.
    $0.00
Total (North Charleston): $7,695.00
Sources last checked Official fee schedules:Charleston Water System North Charleston Sewer District City of North Charleston Charleston County

Where in Charleston County Are You Building?

Each jurisdiction applies its own fee schedule. Pick yours. = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.

North Charleston: Commercial Impact Fees

Commercial development in North Charleston pays no per-square-foot impact fees, but owes $11,070.00 in one-time water and sewer connection fees (rates sourced November 18, 2026).

For a 50,000 sq ft building, that comes to about $11,070.00. The calculator below adjusts to your exact square footage.

The largest line items are Water Impact Fee (Charleston Water System) — 1" tap ($7,370.00 one-time), Sewer Connection Fee (North Charleston Sewer District) — 1.0 REU × $2,500/REU ($2,500.00 one-time) and Water Tap Fee (Charleston Water System) — 1" meter ($1,200.00 one-time).

Water and sewer connection fees assume a 1-inch meter; larger services pay more. See the meter-size tiers in the source schedules.

View the Full North Charleston Impact Fee Schedule
Water$8,570.00 one-time
Sewer$2,500.00 one-time
City$0.00
County$0.00
Total (North Charleston): $11,070.00 one-time (≈ $11,070.00 at 50,000 sq ft)
Sources last checked Official fee schedules:Charleston Water System North Charleston Sewer District City of North Charleston Charleston County
Water/sewer connection fees assume a 1-inch meter; larger services pay more.

Where in Charleston County Are You Building?

Each jurisdiction applies its own fee schedule. Pick yours. Totals shown are for a 50,000 sq ft building, including one-time water/sewer fees (assuming a 1-inch meter). * = one-time water/sewer connection charges only; no per-sq-ft impact fee schedule sourced for that jurisdiction. = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.

North Charleston: Industrial Impact Fees

Industrial development in North Charleston pays no per-square-foot impact fees, but owes $11,070.00 in one-time water and sewer connection fees (rates sourced November 18, 2026).

For a 50,000 sq ft building, that comes to about $11,070.00. The calculator below adjusts to your exact square footage.

The largest line items are Water Impact Fee (Charleston Water System) — 1" tap ($7,370.00 one-time), Sewer Connection Fee (North Charleston Sewer District) — 1.0 REU × $2,500/REU ($2,500.00 one-time) and Water Tap Fee (Charleston Water System) — 1" meter ($1,200.00 one-time).

Water and sewer connection fees assume a 1-inch meter; larger services pay more. See the meter-size tiers in the source schedules.

View the Full North Charleston Impact Fee Schedule
Water$8,570.00 one-time
Sewer$2,500.00 one-time
City$0.00
County$0.00
Total (North Charleston): $11,070.00 one-time (≈ $11,070.00 at 50,000 sq ft)
Sources last checked Official fee schedules:Charleston Water System North Charleston Sewer District City of North Charleston Charleston County
Water/sewer connection fees assume a 1-inch meter; larger services pay more.

Where in Charleston County Are You Building?

Each jurisdiction applies its own fee schedule. Pick yours. Totals shown are for a 50,000 sq ft building, including one-time water/sewer fees (assuming a 1-inch meter). * = one-time water/sewer connection charges only; no per-sq-ft impact fee schedule sourced for that jurisdiction. = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.

North Charleston: Office Impact Fees

Office development in North Charleston pays no per-square-foot impact fees, but owes $11,070.00 in one-time water and sewer connection fees (rates sourced November 18, 2026).

For a 25,000 sq ft building, that comes to about $11,070.00. The calculator below adjusts to your exact square footage.

The largest line items are Water Impact Fee (Charleston Water System) — 1" tap ($7,370.00 one-time), Sewer Connection Fee (North Charleston Sewer District) — 1.0 REU × $2,500/REU ($2,500.00 one-time) and Water Tap Fee (Charleston Water System) — 1" meter ($1,200.00 one-time).

Water and sewer connection fees assume a 1-inch meter; larger services pay more. See the meter-size tiers in the source schedules.

View the Full North Charleston Impact Fee Schedule
Water$8,570.00 one-time
Sewer$2,500.00 one-time
City$0.00
County$0.00
Total (North Charleston): $11,070.00 one-time (≈ $11,070.00 at 25,000 sq ft)
Sources last checked Official fee schedules:Charleston Water System North Charleston Sewer District City of North Charleston Charleston County
Water/sewer connection fees assume a 1-inch meter; larger services pay more.

Where in Charleston County Are You Building?

Each jurisdiction applies its own fee schedule. Pick yours. Totals shown are for a 25,000 sq ft building, including one-time water/sewer fees (assuming a 1-inch meter). * = one-time water/sewer connection charges only; no per-sq-ft impact fee schedule sourced for that jurisdiction. = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.

North Charleston Impact Fee Calculator

Estimate impact fees for your project. Set to single-family. Drop a pin or search an address for site-specific fees.

Location

Select a location to begin

Once you select an address or drop a pin, we'll identify the responsible city and county and generate a fee breakdown.

Water & Sewer
Transportation
Parks
Schools
Fire & Police
General

How Development Impact Fees Work in South Carolina

South Carolina counties and municipalities assess development impact fees under the Development Impact Fee Act (S.C. Code 6-1-910 et seq.). Only a government with a comprehensive plan (or a capital improvements plan that substantially complies with the Act) may impose one, by an ordinance approved by a positive majority, and before charging residential units it must report how the fee affects the availability of affordable housing.

Fees may fund only the public facilities the Act lists: water and wastewater, solid waste, roads and bridges, stormwater and flood control, public safety (law enforcement, fire, emergency medical and street lighting), capital equipment and vehicles of at least $100,000 a unit, parks, libraries and recreation, and, since 2016, K-12 public school facilities. A fee may not exceed the development's proportionate share of the cost, after credits for land, money or improvements the developer contributes and for other funding sources.

Fee revenue is kept in interest-bearing accounts by category and service area and spent only on that category in that area. A fee not spent within three years of the date it was scheduled to be spent, or paid on a building permit that is denied, is refunded with its share of interest. The fee is due no earlier than the building permit (or the development permit where no building permit is needed).

Water and sewer charges usually come from the utility that serves a parcel: the Act's definition of an impact fee excludes connection or hookup charges, and a water or wastewater provider meeting the conditions of 6-1-1080 sets its impact fees outside the Act. That is why totals differ between a city, its neighbors and the unincorporated county around it.

New to impact fees? Our plain-English guide explains what they cover, who pays them, and why they exist.

Summary current as of November 2026. This is an editorial summary, not legal advice; see the official statute text and our terms of use.

North Charleston Impact Fee FAQs

What are the total impact fees for a single-family home in North Charleston, South Carolina?

A new single-family home in North Charleston pays $8,320.00 per unit in combined impact fees (rates sourced November 18, 2026).

How much are commercial impact fees in North Charleston?

Commercial development in North Charleston pays no per-square-foot impact fees, but owes $11,070.00 in one-time water and sewer connection fees (assuming a 1-inch meter).

Does North Charleston charge its own impact fees?

Yes. North Charleston levies its own municipal impact or utility fees. Charleston County does not currently add county-level impact fees inside North Charleston. The schedule on this page shows every fee that applies to development in North Charleston.

Can a South Carolina impact fee be raised after it is adopted?

Only through a new ordinance. Under S.C. Code 6-1-940 the government is bound by the amount its impact fee ordinance sets for each unit of development and may not charge higher or additional impact fees for the same purpose unless the project's service units increase or its scope changes, and then only for the added share. Water and sewer capacity and tap fees set by utilities follow each provider's own rate process.

Fee amounts on this page are compiled from official published schedules and are provided for planning purposes only. Rates change, and project specifics (unit size, meter size, location within special districts) can alter what applies. Always verify current fees with the jurisdiction and utility before relying on them.

Compare unincorporated rates and every other city on the Charleston County impact fees page.

Missing a jurisdiction? Get in touch.

Request coverage for a city or county, report an issue, ask about enterprise access, or inquire about sponsorship opportunities. We typically reply within one business day.