Pleak Impact Fees by Project Type
Pleak: Single-Family Impact Fees
Pleak has no published impact fee amounts for a new single-family home (rates sourced November 21, 2026). The schedule below documents the status of each fee.
Sewer Tap Fee (Village of Pleak) and Water Tap Fee (Village of Pleak) are set by the utility and not published online. County Impact Fee (Fort Bend County) is set by the county and has no published standard rate. City Development Fees (Village of Pleak) is set by the city and has no published standard rate. Contact the levying jurisdiction or utility to verify before budgeting; they are not included as dollar figures here.
View the Full Pleak Impact Fee Schedule
- Water Tap Fee (Village of Pleak)Requires confirmationWater in Pleak comes from Fort Bend County MUD 5 or MUD 157 inside those districts, or private wells; the village's own system is under construction.
- Sewer Tap Fee (Village of Pleak)Requires confirmationPleak has no village sewer; district parcels are served by Fort Bend County MUD 5 and others use septic systems.
- City Development Fees (Village of Pleak)Requires confirmationPleak levies no roadway or other municipal impact fee.
- County Impact Fee (Fort Bend County)Requires confirmationFort Bend CountyFort Bend County charges no road, park or public safety impact fees. State law lets the county and its drainage districts charge drainage impact fees; the county's departmental fee schedule effective October 1, 2026 lists none.
Where in Fort Bend County Are You Building?
Each jurisdiction applies its own fee schedule. Pick yours. = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.
Pleak: Multifamily Impact Fees
Pleak has no published impact fee amounts for a new multifamily unit (rates sourced November 21, 2026). The schedule below documents the status of each fee.
Water Tap Fee (Village of Pleak, MF) and Sewer Tap Fee (Village of Pleak, MF) are set by the utility and not published online. County Impact Fee (Fort Bend County, MF) is set by the county and has no published standard rate. City Development Fees (Village of Pleak, MF) is set by the city and has no published standard rate. Contact the levying jurisdiction or utility to verify before budgeting; they are not included as dollar figures here.
View the Full Pleak Impact Fee Schedule
- Water Tap Fee (Village of Pleak, MF)Requires confirmationWater in Pleak comes from Fort Bend County MUD 5 or MUD 157 inside those districts, or private wells; the village's own system is under construction.
- Sewer Tap Fee (Village of Pleak, MF)Requires confirmationPleak has no village sewer; district parcels are served by Fort Bend County MUD 5 and others use septic systems.
- City Development Fees (Village of Pleak, MF)Requires confirmationPleak levies no roadway or other municipal impact fee.
- County Impact Fee (Fort Bend County, MF)Requires confirmationFort Bend CountyFort Bend County charges no road, park or public safety impact fees. State law lets the county and its drainage districts charge drainage impact fees; the county's departmental fee schedule effective October 1, 2026 lists none.
Where in Fort Bend County Are You Building?
Each jurisdiction applies its own fee schedule. Pick yours. = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.
Pleak: Commercial Impact Fees
Commercial development in Pleak pays no per-square-foot impact fees (rates sourced November 21, 2026).
Water Connection Fee (Village of Pleak) and Sewer Connection Fee (Village of Pleak) are set by the utility and not published online. County Impact Fees (Fort Bend County, Commercial) is set by the county and has no published standard rate. Contact the levying jurisdiction or utility to verify before budgeting; they are not included as dollar figures here.
View the Full Pleak Impact Fee Schedule
- Water Connection Fee (Village of Pleak)Requires confirmationVillage of PleakThe Village of Pleak has no water impact fee and publishes no water connection charge. The village is building a public water system (2026-2027 water budget); most existing properties use private wells, and sites inside Fort Bend County MUD 5 or MUD 157 are served by those districts under their own rate orders.
- Sewer Connection Fee (Village of Pleak)Requires confirmationVillage of PleakThe Village of Pleak runs no sewer system and charges no sewer impact fee. Most properties use on-site septic systems; sites inside Fort Bend County MUD 5 or MUD 157 connect to the district plant under the district's own charges.
- City Impact Fees (Village of Pleak, Commercial)$0.00Village of PleakThe Village of Pleak has not adopted impact fees, and Texas law allows no city park or public safety impact fees.
- County Impact Fees (Fort Bend County, Commercial)Requires confirmationFort Bend CountyFort Bend County charges no road, park or public safety impact fees. State law lets the county and its drainage districts charge drainage impact fees; the county's departmental fee schedule effective October 1, 2026 lists none.
Where in Fort Bend County Are You Building?
Each jurisdiction applies its own fee schedule. Pick yours. Totals shown are for a 50,000 sq ft building, including water/sewer fees (one-time connection fees assume a 1-inch meter). * = one-time water/sewer connection charges only; no per-sq-ft impact fee schedule sourced for that jurisdiction. = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.
Pleak: Industrial Impact Fees
Industrial development in Pleak pays no per-square-foot impact fees (rates sourced November 21, 2026).
Water Connection Fee (Village of Pleak) and Sewer Connection Fee (Village of Pleak) are set by the utility and not published online. County Impact Fees (Fort Bend County, Industrial) is set by the county and has no published standard rate. Contact the levying jurisdiction or utility to verify before budgeting; they are not included as dollar figures here.
View the Full Pleak Impact Fee Schedule
- Water Connection Fee (Village of Pleak)Requires confirmationVillage of PleakThe Village of Pleak has no water impact fee and publishes no water connection charge. The village is building a public water system (2026-2027 water budget); most existing properties use private wells, and sites inside Fort Bend County MUD 5 or MUD 157 are served by those districts under their own rate orders.
- Sewer Connection Fee (Village of Pleak)Requires confirmationVillage of PleakThe Village of Pleak runs no sewer system and charges no sewer impact fee. Most properties use on-site septic systems; sites inside Fort Bend County MUD 5 or MUD 157 connect to the district plant under the district's own charges.
- City Impact Fees (Village of Pleak, Industrial)$0.00Village of PleakThe Village of Pleak has not adopted impact fees, and Texas law allows no city park or public safety impact fees.
- County Impact Fees (Fort Bend County, Industrial)Requires confirmationFort Bend CountyFort Bend County charges no road, park or public safety impact fees. State law lets the county and its drainage districts charge drainage impact fees; the county's departmental fee schedule effective October 1, 2026 lists none.
Where in Fort Bend County Are You Building?
Each jurisdiction applies its own fee schedule. Pick yours. Totals shown are for a 50,000 sq ft building, including water/sewer fees (one-time connection fees assume a 1-inch meter). * = one-time water/sewer connection charges only; no per-sq-ft impact fee schedule sourced for that jurisdiction. = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.
Pleak: Office Impact Fees
Office development in Pleak pays no per-square-foot impact fees (rates sourced November 21, 2026).
Water Connection Fee (Village of Pleak) and Sewer Connection Fee (Village of Pleak) are set by the utility and not published online. County Impact Fees (Fort Bend County, Office) is set by the county and has no published standard rate. Contact the levying jurisdiction or utility to verify before budgeting; they are not included as dollar figures here.
View the Full Pleak Impact Fee Schedule
- Water Connection Fee (Village of Pleak)Requires confirmationVillage of PleakThe Village of Pleak has no water impact fee and publishes no water connection charge. The village is building a public water system (2026-2027 water budget); most existing properties use private wells, and sites inside Fort Bend County MUD 5 or MUD 157 are served by those districts under their own rate orders.
- Sewer Connection Fee (Village of Pleak)Requires confirmationVillage of PleakThe Village of Pleak runs no sewer system and charges no sewer impact fee. Most properties use on-site septic systems; sites inside Fort Bend County MUD 5 or MUD 157 connect to the district plant under the district's own charges.
- City Impact Fees (Village of Pleak, Office)$0.00Village of PleakThe Village of Pleak has not adopted impact fees, and Texas law allows no city park or public safety impact fees.
- County Impact Fees (Fort Bend County, Office)Requires confirmationFort Bend CountyFort Bend County charges no road, park or public safety impact fees. State law lets the county and its drainage districts charge drainage impact fees; the county's departmental fee schedule effective October 1, 2026 lists none.
Where in Fort Bend County Are You Building?
Each jurisdiction applies its own fee schedule. Pick yours. Totals shown are for a 25,000 sq ft building, including water/sewer fees (one-time connection fees assume a 1-inch meter). * = one-time water/sewer connection charges only; no per-sq-ft impact fee schedule sourced for that jurisdiction. = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.
Pleak Impact Fee Calculator
Estimate impact fees for your project. Set to single-family. Drop a pin or search an address for site-specific fees.
Location
Select a location to begin
Once you select an address or drop a pin, we'll identify the responsible city and county and generate a fee breakdown.
How Impact Fees Work in Texas
Texas cities, and certain special districts and authorities, assess impact fees under Chapter 395 of the Local Government Code and, with narrow exceptions, may charge one only by following it. A fee rests on adopted land use assumptions and a capital improvements plan, and imposing one takes the votes of two-thirds of the governing body's members.
Impact fees may fund only water supply, treatment and distribution; wastewater collection and treatment; storm water, drainage and flood control; and roadway facilities. Parks, schools, police and fire facilities are not on the chapter's list. The chapter does not treat park land dedication, or a payment in its place, as an impact fee, so a city can require that separately. The fee per service unit is capped at the plan's growth-related cost, less a required credit, divided by the projected service units. Counties generally cannot charge impact fees: the chapter gives that authority only to counties of 3.3 million or more people and the counties bordering them, and only for storm water, drainage and flood control. Since September 2025 a city also may not charge an impact fee where an office, retail or warehouse building at least five years old is converted to multifamily or mixed-use residential use (at least 65 percent of the building and of each usable floor), unless the land was already subject to an impact fee before the conversion's building permit was filed (Section 218.204).
For land platted after a fee is adopted, the fee is assessed no later than when the plat is recorded, which fixes the most that can be charged per service unit. Where water and wastewater capacity is available, it is generally collected when the building permit is issued, or when a water or wastewater meter connection is applied for on land outside city limits or where the entity charging the fee issues no building permits. A fee not spent as the chapter allows within 10 years of payment must generally be refunded with interest, and the land use assumptions and capital improvements plan are updated at least every five years unless the governing body formally determines that no update is needed.
A city may charge water, wastewater and drainage impact fees in its extraterritorial jurisdiction as well as inside its limits, but roadway impact fees stop at the city limits. Where a utility district or another provider supplies water or sewer instead of the city, its charges are separate from the city's, so the total can differ between a city, its neighbors and the unincorporated land around it.
For a primer on how impact fees work, see our plain-English guide.
Summary current as of November 2026. This is an editorial summary, not legal advice; see the official statute text and our terms of use.
Pleak Impact Fee FAQs
How much are commercial impact fees in Pleak?
Pleak does not currently levy impact fees on commercial development.
Does Pleak charge its own impact fees?
Yes. Pleak levies its own municipal impact or utility fees, and county-levied fees also apply inside city limits. The schedule on this page shows every fee that applies to development in Pleak, with the combined total.
Can a Texas impact fee increase at any time?
No. Under Section 395.0515 of the Local Government Code, added in 2025, a city or district may not increase an impact fee for three years from the later of the date the fee was adopted or last increased, although it may phase in collection up to the adopted maximum over no more than ten years. An increase also needs an independent financial audit and a public hearing on its results first (Section 395.059), and the measure approving it cannot be adopted as an emergency measure (Section 395.057). Once a fee is assessed on a tract, it cannot be raised for that tract unless the number of service units increases (Section 395.017). Charges set by a separate water or sewer provider may follow different rules.
Fee amounts on this page are compiled from official published schedules and are provided for planning purposes only. Rates change, and project specifics (unit size, meter size, location within special districts) can alter what applies. Always verify current fees with the jurisdiction and utility before relying on them.
Compare unincorporated rates and every other city on the Fort Bend County impact fees page.