IMPACTFEES.ORG

Jacksonville, Florida Impact Fees

Jacksonville applies its own fee schedule. Duval County does not currently add county-level impact fees inside city limits. A new single-family home pays $10,206.00 per unit (rates sourced ). This figure includes amounts that have not been confirmed with the jurisdiction; verify before budgeting. The full breakdown is below.

Jacksonville impact fees by project type

Jacksonville: Single-Family Impact Fees

A new single-family home in Jacksonville pays $10,206.00 per unit in impact fees (rates sourced August 5, 2026). Every line item is levied at the municipal or utility level.

The largest line items are Sewer Capacity Fee (JEA) ($5,114.00) and Water Capacity Fee (JEA) ($1,170.00).

City Mobility Fee (City of Jacksonville / COJ) is shown at the last published amount but has not been confirmed with the jurisdiction; it is included in the totals here. Verify before budgeting.

View the full Jacksonville impact fee schedule
Water$1,170.00
  • Water Capacity Fee (JEA)
    JEA (Jacksonville Electric Authority)
    JEA water plant capacity fee for a standard 3/4-inch residential meter, effective April 1, 2023 (still current). Charged as the greater of the $1,170 base fee or $4.68 per gallon of average daily flow (250 gpd minimum; no separate irrigation meter). JEA's October 2025 and October 2026 rate adjustments changed monthly usage rates only, not this one-time capacity fee.
    $1,170.00
Sewer$5,114.00
  • Sewer Capacity Fee (JEA)
    JEA (Jacksonville Electric Authority)
    JEA sewer plant capacity fee for a standard 3/4-inch residential meter, effective April 1, 2023 (still current). Charged as the greater of the $5,114 base fee or $25.57 per gallon of estimated average daily sewer capacity (200 gpd minimum). JEA's October 2025 and October 2026 rate adjustments changed monthly usage rates only, not this one-time capacity fee.
    $5,114.00
City$3,922.00
County$0.00
Total (Jacksonville): $10,206.00
Sources last checked Official fee schedules:JEA (Jacksonville Electric Authority) City of Jacksonville (COJ) Duval County
Amounts flagged "Requires confirmation" are the last published figures, included in the totals. Confirm them with the jurisdiction or utility before budgeting.

Where in Duval County are you building?

Each jurisdiction applies its own fee schedule. Pick yours. = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.

Jacksonville: Multifamily Impact Fees

A new multifamily unit in Jacksonville pays $1,924.00 per unit in impact fees (rates sourced August 5, 2026). Every line item is levied at the municipal or utility level.

City Mobility Fee (City of Jacksonville / COJ, MF) is shown at the last published amount but has not been confirmed with the jurisdiction; it is included in the totals here. Verify before budgeting.

View the full Jacksonville impact fee schedule
Water$0.00
  • Water Capacity Fee (JEA, MF)
    JEA (Jacksonville Electric Authority)
    JEA sets water plant capacity charges by estimated average daily flow or by meter size rather than per dwelling unit, so there is no published per-apartment-unit amount. A three-quarter-inch water connection without separate irrigation carries a minimum plant capacity charge of $1,170 plus a $1,695 line extension growth capacity charge, and larger services are charged the greater of the meter-size minimum or $4.68 per gallon of average daily water. For an apartment building the charge is calculated from the engineer's projected daily flow for the whole project.
    $0.00
Sewer$0.00
  • Sewer Capacity Fee (JEA, MF)
    JEA (Jacksonville Electric Authority)
    JEA sets sewer plant capacity charges by estimated average daily flow or by meter size rather than per dwelling unit, so there is no published per-apartment-unit amount. A three-quarter-inch sewer connection carries a minimum plant capacity charge of $5,114, and larger services are charged the greater of the meter-size minimum or $25.57 per gallon of estimated average daily sewer capacity. For an apartment building the charge is calculated from the engineer's projected daily flow for the whole project.
    $0.00
City$1,924.00
County$0.00
Total (Jacksonville): $1,924.00
Sources last checked Official fee schedules:JEA (Jacksonville Electric Authority) City of Jacksonville (COJ) Duval County
Amounts flagged "Requires confirmation" are the last published figures, included in the totals. Confirm them with the jurisdiction or utility before budgeting.

Where in Duval County are you building?

Each jurisdiction applies its own fee schedule. Pick yours. = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.

Jacksonville: Commercial Impact Fees

Commercial development in Jacksonville pays no per-square-foot impact fees, but owes $7,796.50 in one-time water and sewer connection fees (rates sourced August 5, 2026).

For a 50,000 sq ft building, that comes to at least $7,796.50. The calculator below adjusts to your exact square footage.

The largest line items are Sewer Plant Capacity Fee (JEA) — 1" meter ($6,392.50 one-time) and Water Plant Capacity Fee (JEA) — 1" meter ($1,404.00 one-time).

Water and sewer connection fees assume a 1-inch meter; larger services pay more. See the meter-size tiers in the source schedules.

City Mobility Fee (City of Jacksonville, Commercial) is set by the city and has no published standard rate. Contact the levying jurisdiction or utility to verify before budgeting; it is not included as a dollar figure here.

View the full Jacksonville impact fee schedule
Water$1,404.00 one-time
  • Water Plant Capacity Fee (JEA) — 1" meter
    JEA (Jacksonville Electric Authority)
    Water plant capacity fee, effective April 1, 2023 (JEA, which serves the City of Jacksonville and the consolidated county). The amount shown is the base fee for a 1-inch meter; JEA charges the greater of the base fee or a per-gallon rate applied to estimated average daily flow, so many nonresidential projects pay more. Meters 2 inches and larger have no base fee and are sized entirely from average daily flow. Separate meter-set and tap fees apply. See the other meter sizes for the full ladder.
    $1,404.00 one-time
Sewer$6,392.50 one-time
  • Sewer Plant Capacity Fee (JEA) — 1" meter
    JEA (Jacksonville Electric Authority)
    Sewer plant capacity fee, effective April 1, 2023 (JEA). The amount shown is the base fee for a 1-inch meter; JEA charges the greater of the base fee or a per-gallon rate applied to estimated average daily sewer capacity, so many nonresidential projects pay more. Meters 2 inches and larger have no base fee and are calculated from average daily flow. See the other meter sizes for the full ladder.
    $6,392.50 one-time
City$0.00
  • City Mobility Fee (City of Jacksonville, Commercial)
    City of Jacksonville (COJ) — Concurrency & Mobility Management System Office
    The City of Jacksonville assesses a transportation mobility fee (Ordinance Code Ch. 655) instead of impact fees. It is calculated individually for each development from vehicle-trip generation and the applicable mobility zone, so the City publishes no flat per-square-foot rate.
    Requires confirmation
County$0.00
Total (Jacksonville): $7,796.50 one-time (≈ $7,796.50 at 50,000 sq ft)
Fees flagged "Requires confirmation" have no confirmed published amount. Confirm them with the jurisdiction or utility before budgeting.
Water/sewer connection fees assume a 1-inch meter; larger services pay more.

Where in Duval County are you building?

Each jurisdiction applies its own fee schedule. Pick yours. Totals shown are for a 50,000 sq ft building, including one-time water/sewer fees (assuming a 1-inch meter). * = one-time water/sewer connection charges only; no per-sq-ft impact fee schedule sourced for that jurisdiction. = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.

Jacksonville: Industrial Impact Fees

Industrial development in Jacksonville pays no per-square-foot impact fees, but owes $7,796.50 in one-time water and sewer connection fees (rates sourced August 5, 2026).

For a 50,000 sq ft building, that comes to at least $7,796.50. The calculator below adjusts to your exact square footage.

The largest line items are Sewer Plant Capacity Fee (JEA) — 1" meter ($6,392.50 one-time) and Water Plant Capacity Fee (JEA) — 1" meter ($1,404.00 one-time).

Water and sewer connection fees assume a 1-inch meter; larger services pay more. See the meter-size tiers in the source schedules.

City Mobility Fee (City of Jacksonville, Industrial) is set by the city and has no published standard rate. Contact the levying jurisdiction or utility to verify before budgeting; it is not included as a dollar figure here.

View the full Jacksonville impact fee schedule
Water$1,404.00 one-time
  • Water Plant Capacity Fee (JEA) — 1" meter
    JEA (Jacksonville Electric Authority)
    Water plant capacity fee, effective April 1, 2023 (JEA, which serves the City of Jacksonville and the consolidated county). The amount shown is the base fee for a 1-inch meter; JEA charges the greater of the base fee or a per-gallon rate applied to estimated average daily flow, so many nonresidential projects pay more. Meters 2 inches and larger have no base fee and are sized entirely from average daily flow. Separate meter-set and tap fees apply. See the other meter sizes for the full ladder.
    $1,404.00 one-time
Sewer$6,392.50 one-time
  • Sewer Plant Capacity Fee (JEA) — 1" meter
    JEA (Jacksonville Electric Authority)
    Sewer plant capacity fee, effective April 1, 2023 (JEA). The amount shown is the base fee for a 1-inch meter; JEA charges the greater of the base fee or a per-gallon rate applied to estimated average daily sewer capacity, so many nonresidential projects pay more. Meters 2 inches and larger have no base fee and are calculated from average daily flow. See the other meter sizes for the full ladder.
    $6,392.50 one-time
City$0.00
  • City Mobility Fee (City of Jacksonville, Industrial)
    City of Jacksonville (COJ) — Concurrency & Mobility Management System Office
    The City of Jacksonville assesses a transportation mobility fee (Ordinance Code Ch. 655) instead of impact fees. It is calculated individually for each development from vehicle-trip generation and the applicable mobility zone, so the City publishes no flat per-square-foot rate.
    Requires confirmation
County$0.00
Total (Jacksonville): $7,796.50 one-time (≈ $7,796.50 at 50,000 sq ft)
Fees flagged "Requires confirmation" have no confirmed published amount. Confirm them with the jurisdiction or utility before budgeting.
Water/sewer connection fees assume a 1-inch meter; larger services pay more.

Where in Duval County are you building?

Each jurisdiction applies its own fee schedule. Pick yours. Totals shown are for a 50,000 sq ft building, including one-time water/sewer fees (assuming a 1-inch meter). * = one-time water/sewer connection charges only; no per-sq-ft impact fee schedule sourced for that jurisdiction. = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.

Jacksonville: Office Impact Fees

Office development in Jacksonville pays no per-square-foot impact fees, but owes $7,796.50 in one-time water and sewer connection fees (rates sourced August 5, 2026).

For a 25,000 sq ft building, that comes to at least $7,796.50. The calculator below adjusts to your exact square footage.

The largest line items are Sewer Plant Capacity Fee (JEA) — 1" meter ($6,392.50 one-time) and Water Plant Capacity Fee (JEA) — 1" meter ($1,404.00 one-time).

Water and sewer connection fees assume a 1-inch meter; larger services pay more. See the meter-size tiers in the source schedules.

City Mobility Fee (City of Jacksonville, Office) is set by the city and has no published standard rate. Contact the levying jurisdiction or utility to verify before budgeting; it is not included as a dollar figure here.

View the full Jacksonville impact fee schedule
Water$1,404.00 one-time
  • Water Plant Capacity Fee (JEA) — 1" meter
    JEA (Jacksonville Electric Authority)
    Water plant capacity fee, effective April 1, 2023 (JEA, which serves the City of Jacksonville and the consolidated county). The amount shown is the base fee for a 1-inch meter; JEA charges the greater of the base fee or a per-gallon rate applied to estimated average daily flow, so many nonresidential projects pay more. Meters 2 inches and larger have no base fee and are sized entirely from average daily flow. Separate meter-set and tap fees apply. See the other meter sizes for the full ladder.
    $1,404.00 one-time
Sewer$6,392.50 one-time
  • Sewer Plant Capacity Fee (JEA) — 1" meter
    JEA (Jacksonville Electric Authority)
    Sewer plant capacity fee, effective April 1, 2023 (JEA). The amount shown is the base fee for a 1-inch meter; JEA charges the greater of the base fee or a per-gallon rate applied to estimated average daily sewer capacity, so many nonresidential projects pay more. Meters 2 inches and larger have no base fee and are calculated from average daily flow. See the other meter sizes for the full ladder.
    $6,392.50 one-time
City$0.00
  • City Mobility Fee (City of Jacksonville, Office)
    City of Jacksonville (COJ) — Concurrency & Mobility Management System Office
    The City of Jacksonville assesses a transportation mobility fee (Ordinance Code Ch. 655) instead of impact fees. It is calculated individually for each development from vehicle-trip generation and the applicable mobility zone, so the City publishes no flat per-square-foot rate.
    Requires confirmation
County$0.00
Total (Jacksonville): $7,796.50 one-time (≈ $7,796.50 at 25,000 sq ft)
Fees flagged "Requires confirmation" have no confirmed published amount. Confirm them with the jurisdiction or utility before budgeting.
Water/sewer connection fees assume a 1-inch meter; larger services pay more.

Where in Duval County are you building?

Each jurisdiction applies its own fee schedule. Pick yours. Totals shown are for a 25,000 sq ft building, including one-time water/sewer fees (assuming a 1-inch meter). * = one-time water/sewer connection charges only; no per-sq-ft impact fee schedule sourced for that jurisdiction. = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.

Jacksonville impact fee calculator

Estimate impact fees for your project. Set to single-family. Drop a pin or search an address for site-specific fees.

Location

Select a location to begin

Once you select an address or drop a pin, we'll identify the responsible city and county and generate a fee breakdown.

Water & Sewer
Transportation
Parks
Schools
Fire & Police
General

How impact fees work in Florida

Florida impact fees are one-time charges on new development, governed by Section 163.31801, Florida Statutes (the Florida Impact Fee Act). The statute requires fees to be based on the most recent and localized data, spent on the infrastructure category they were collected for, and adopted by ordinance.

Since 2021, the law also limits how fast fees can rise: increases up to 25% phase in over two years, increases of 25–50% phase in over four years, and increases above 50% are allowed only with a demonstrated extraordinary-circumstances study and at least a two-thirds vote of the governing body.

Counties and cities can both levy impact fees. Inside an incorporated city, a project typically pays the county's countywide fees plus any municipal fees the city has adopted, which is why totals differ between a city and the unincorporated county around it.

If you're still asking what are impact fees, start with our guide to the definition, common categories, and legal basis.

Jacksonville impact fee FAQs

What are the total impact fees for a single-family home in Jacksonville, Florida?

A new single-family home in Jacksonville pays $10,206.00 per unit in combined impact fees (rates sourced August 5, 2026). This figure includes amounts that have not been confirmed with the jurisdiction; verify before budgeting.

How much are commercial impact fees in Jacksonville?

Commercial development in Jacksonville pays no per-square-foot impact fees, but owes $7,796.50 in one-time water and sewer connection fees (assuming a 1-inch meter). One additional fee has no published standard amount and is not included, so the full cost may be higher; verify before budgeting.

Does Jacksonville charge its own impact fees?

Yes. Jacksonville levies its own municipal impact or utility fees. Duval County does not currently add county-level impact fees inside Jacksonville. The schedule on this page shows every fee that applies to development in Jacksonville.

Can Florida impact fees increase at any time?

No. Section 163.31801, Florida Statutes limits increases to 50% at most, phased in over two to four years, unless the local government makes extraordinary-circumstances findings and approves the increase by at least a two-thirds vote.

Fee amounts on this page are compiled from official published schedules and are provided for planning purposes only. Rates change, and project specifics (unit size, meter size, location within special districts) can alter what applies. Always verify current fees with the jurisdiction and utility before relying on them.

Compare unincorporated rates and every other city on the Duval County impact fees page.