Manatee County Impact Fees by Project Type
Where in Manatee County Are You Building?
Each jurisdiction applies its own fee schedule. Pick yours. = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.
Unincorporated Manatee County: Single-Family Impact Fees
A new single-family home in unincorporated Manatee County pays $40,121.47 per unit in impact fees (rates sourced October 21, 2026). All of it is levied by Manatee County.
The largest line items are County Impact Fees (Manatee County) ($34,641.00), Wastewater Facility Investment Fee (Manatee County Utilities) ($3,175.00) and Potable Water Facility Investment Fee (Manatee County Utilities) ($1,738.00).
Some fees are tiered by unit size or building type; amounts reflect the representative tier noted in the schedule below.
View the Full Manatee County Impact Fee Schedule
- Potable Water Facility Investment Fee (Manatee County Utilities)$1,738.005/8" x 3/4"Manatee County UtilitiesManatee County Utilities potable-water Facility Investment Fee (water capacity/impact fee), effective 10/1/2019. Rate shown is for a standard 5/8x3/4" residential meter; larger meters pay more (3/4" $2,607, 1" $4,345, and up). Paid before the building permit.
- Wastewater Facility Investment Fee (Manatee County Utilities)$3,175.005/8" x 3/4"Manatee County UtilitiesManatee County Utilities wastewater Facility Investment Fee (sewer capacity/impact fee), effective 10/1/2019. Rate shown is for a standard 5/8x3/4" residential meter; larger meters pay more. Paid before the building permit.
- City Impact Fees (Unincorporated Manatee - N/A placeholder)$0.00Manatee CountyDevelopment in unincorporated Manatee County pays no municipal (city) impact fees; the applicable charges are the county impact fees and Manatee County Utilities water/sewer Facility Investment Fees, recorded separately.
- County Impact Fees (Manatee County)$34,641.001,701 sq ft or moreManatee CountyTotal Manatee County impact fees for a single-family detached home of 1,701 sq ft or more in unincorporated Manatee (canonical home), effective 9/9/2026: the county's Ord. 25-15 fees plus the countywide Ord. 24-22 school fee, per dwelling unit, the same in all four transportation districts. Tiered by air-conditioned area: 750 sq ft or less $13,820; 751-1,000 $18,270; 1,001-1,300 $23,233; 1,301-1,700 $28,021; 1,701 sq ft or more $34,641. The school component steps up on 9/9/2027 (this tier to $35,407). Excludes Manatee County Utilities water and sewer Facility Investment Fees and fire district fees, billed separately. Paid before the certificate of occupancy.
- Fire Impact Fee (Manatee County fire districts)$567.47Cedar Hammock Fire Rescue DistrictIndependent fire control districts (Manatee County)New residential construction in unincorporated Manatee County pays a fire impact fee set by the independent fire district that serves the parcel. This row carries the highest of them, Cedar Hammock Fire Rescue, at $567.47 per dwelling unit for 10/1/2026 to 9/30/2027; it adjusts each October 1 by the July CPI-U. The others: East Manatee, West Manatee, Southern Manatee and Parrish each charge $500, and North River charges $311, per dwelling unit. The fee is the same for single-family and multifamily units.
Where in Manatee County Are You Building?
Each jurisdiction applies its own fee schedule. Pick yours. = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.
Unincorporated Manatee County: Multifamily Impact Fees
A new multifamily unit in unincorporated Manatee County pays $18,154.47 per unit in impact fees (rates sourced October 21, 2026). All of it is levied by Manatee County.
The largest line items are County Impact Fees (Manatee County, MF) ($14,640.00), Wastewater Facility Investment Fee (Manatee County Utilities) (MF) ($1,905.00) and Potable Water Facility Investment Fee (Manatee County Utilities) (MF) ($1,042.00).
Some fees are tiered by unit size or building type; amounts reflect the representative tier noted in the schedule below.
View the Full Manatee County Impact Fee Schedule
- Potable Water Facility Investment Fee (Manatee County Utilities) (MF)$1,042.00per dwelling unit (master-metered)Manatee County UtilitiesManatee County Utilities potable-water Facility Investment Fee (water capacity/impact fee), effective 10/1/2019, charged at $1,042 per dwelling unit for multifamily (master-metered). Mobile-home parks are $869 per unit. Paid before the building permit.
- Wastewater Facility Investment Fee (Manatee County Utilities) (MF)$1,905.00per dwelling unit (master-metered)Manatee County UtilitiesManatee County Utilities wastewater Facility Investment Fee (sewer capacity/impact fee), effective 10/1/2019, charged at $1,905 per dwelling unit for multifamily (master-metered). Mobile-home parks are $1,587 per unit. Paid before the building permit.
- City Impact Fees (Unincorporated Manatee - N/A placeholder) (MF)$0.00Manatee CountyMultifamily development in unincorporated Manatee County pays no municipal (city) impact fees; the applicable charges are the county impact fees and Manatee County Utilities water/sewer Facility Investment Fees, recorded separately.
- County Impact Fees (Manatee County, MF)$14,640.00751-1,000 sq ftManatee CountyTotal Manatee County impact fees for a multifamily unit of 751-1,000 sq ft in unincorporated Manatee (canonical unit), effective 9/9/2026: the county's Ord. 25-15 fees plus the countywide Ord. 24-22 school fee, per dwelling unit, the same in all four transportation districts. Tiered by air-conditioned area: 750 sq ft or less $10,886; 751-1,000 $14,640; 1,001-1,300 $18,793; 1,301-1,700 $25,347; 1,701 sq ft or more $25,959. The school component steps up on 9/9/2027 (this tier to $15,078). Excludes Manatee County Utilities water and sewer Facility Investment Fees and fire district fees, billed separately. Paid before the certificate of occupancy.
- Fire Impact Fee (Manatee County fire districts) (MF)$567.47Cedar Hammock Fire Rescue DistrictManatee CountyEach new multifamily unit in unincorporated Manatee County pays a fire impact fee set by the independent fire district serving the parcel. This row carries the highest, Cedar Hammock Fire Rescue, at $567.47 per unit for 10/1/2026 to 9/30/2027, adjusted each October 1 by the July CPI-U. The others: East Manatee, West Manatee, Southern Manatee and Parrish each $500, and North River $311, per unit. Separate from and additional to Manatee County's own impact fees, which exclude fire.
Where in Manatee County Are You Building?
Each jurisdiction applies its own fee schedule. Pick yours. Totals shown are for a 50,000 sq ft building, including one-time water/sewer fees (assuming a 1-inch meter). = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.
Unincorporated Manatee County: Commercial Impact Fees
Commercial development in unincorporated Manatee County pays $28.30 per square foot in impact fees, plus $14,122.00 in one-time water and sewer connection fees (rates sourced October 21, 2026).
For a 50,000 sq ft building, that comes to at least $1,429,322.00. The calculator below adjusts to your exact square footage.
The largest line items are Wastewater Facility Investment Fee (Manatee County Utilities) — 1" meter ($9,127.00 one-time), Potable Water Facility Investment Fee (Manatee County Utilities) — 1" meter ($4,995.00 one-time) and Alternative Transportation Impact Fee (Manatee County, Commercial) ($25.66/sq ft).
Water and sewer connection fees assume a 1-inch meter; larger services pay more. See the meter-size tiers in the source schedules.
Fire Impact Fee (Manatee County fire districts, Commercial) is shown at the last published amount but has not been confirmed with the jurisdiction; it is included in the totals here. Verify before budgeting.
Wastewater Facility Investment Fee (Manatee County Utilities) — over 6" meter and Potable Water Facility Investment Fee (Manatee County Utilities) — over 6" meter are set by the utility and not published online. Contact the levying jurisdiction or utility to verify before budgeting; they are not included as dollar figures here.
View the Full Manatee County Impact Fee Schedule
- Potable Water Facility Investment Fee (Manatee County Utilities) — 1" meter$4,995.00 one-timeManatee County UtilitiesManatee County Utilities facility investment fee, set by water-meter size (commercial schedule); effective 10/1/2019. Meters over 6 inches are priced per gallon of daily reserve capacity.
- Potable Water Facility Investment Fee (Manatee County Utilities) — over 6" meterContact jurisdiction/utility to verifyManatee County UtilitiesCommercial meters over 6 in. pay a Manatee County Utilities potable water facility investment fee of $6.9526 per gallon per day of reserve capacity (schedule effective 10/1/2019). The total depends on the project's demand, so it is not added to the estimate.
- Wastewater Facility Investment Fee (Manatee County Utilities) — 1" meter$9,127.00 one-timeManatee County UtilitiesManatee County Utilities facility investment fee, set by water-meter size (commercial schedule); effective 10/1/2019. Meters over 6 inches are priced per gallon of daily reserve capacity.
- Wastewater Facility Investment Fee (Manatee County Utilities) — over 6" meterContact jurisdiction/utility to verifyManatee County UtilitiesCommercial meters over 6 in. pay a Manatee County Utilities wastewater facility investment fee of $17.162 per gallon per day of reserve capacity (schedule effective 10/1/2019). The total depends on the project's demand, so it is not added to the estimate.
- City Impact Fees (Unincorporated Manatee - N/A placeholder, Commercial)$0.00Manatee CountyUnincorporated Manatee County has no municipal impact fee. Commercial projects there pay the county impact fees and the fire district fee for their location instead.
- Alternative Transportation Impact Fee (Manatee County, Commercial)$25.66/sq ftShopping Center 40,000-150,000 sq ftManatee CountyEffective 9/9/2025. Applies in unincorporated Manatee County only. Default tier: shopping centers 40,000-150,000 sq ft; smaller (<40,000) or larger (>150,000) centers pay different rates - see other tiers.
- Public Safety Impact Fee (Manatee County, Commercial)$1.55/sq ftShopping Center 40,000-150,000 sq ftManatee CountyEffective 9/9/2025. Applies in unincorporated Manatee County only. Default tier: shopping centers 40,000-150,000 sq ft; smaller (<40,000) or larger (>150,000) centers pay different rates - see other tiers.
- Law Enforcement Impact Fee (Manatee County, Commercial)$0.57/sq ftShopping Center 40,000-150,000 sq ftManatee CountyEffective 9/9/2025. Applies in unincorporated Manatee County only. Default tier: shopping centers 40,000-150,000 sq ft; smaller (<40,000) or larger (>150,000) centers pay different rates - see other tiers.
- Fire Impact Fee (Manatee County fire districts, Commercial)$0.28/sq ftRequires confirmationCedar Hammock Fire Rescue DistrictCedar Hammock Fire Rescue DistrictFire impact fees in unincorporated Manatee County are levied by independent fire districts, each with its own nonresidential rate. From 10/1/2026 Cedar Hammock charges $1,125.93 for the first 5,000 sq ft plus $0.28 per sq ft above 5,000 (CPI-adjusted each October 1); East Manatee and West Manatee charge $980 plus $0.25 per sq ft above 5,000; North River charges $600 plus $0.15 per sq ft above 5,000. The rate depends on the district the site is in; Cedar Hammock, the highest of the district rates, is the one shown.
- Impact Fee Administrative Surcharge (Manatee County, Commercial)$0.25/sq ftShopping Center 40,000-150,000 sq ftManatee CountyEffective 9/9/2025. Applies in unincorporated Manatee County only. Default tier: shopping centers 40,000-150,000 sq ft; smaller (<40,000) or larger (>150,000) centers pay different rates - see other tiers.
- Libraries Impact Fee (Manatee County, Commercial)$0.00Manatee CountyManatee County charges its library impact fee on residential development only. The nonresidential schedule (Ord. 25-15, effective 9/9/2025) has no library column, so commercial construction pays none.
- Parks & Natural Resources Impact Fee (Manatee County, Commercial)$0.00Manatee CountyManatee County charges its parks and natural resources impact fee on residential development only. The nonresidential schedule (Ord. 25-15, effective 9/9/2025) has no parks column, so commercial construction pays none.
Where in Manatee County Are You Building?
Each jurisdiction applies its own fee schedule. Pick yours. Totals shown are for a 50,000 sq ft building, including one-time water/sewer fees (assuming a 1-inch meter). = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.
Unincorporated Manatee County: Industrial Impact Fees
Industrial development in unincorporated Manatee County pays $8.76 per square foot in impact fees, plus $14,122.00 in one-time water and sewer connection fees (rates sourced October 21, 2026).
For a 50,000 sq ft building, that comes to at least $452,222.00. The calculator below adjusts to your exact square footage.
The largest line items are Wastewater Facility Investment Fee (Manatee County Utilities) — 1" meter ($9,127.00 one-time), Potable Water Facility Investment Fee (Manatee County Utilities) — 1" meter ($4,995.00 one-time) and Alternative Transportation Impact Fee (Manatee County, Industrial) ($8.06/sq ft).
Water and sewer connection fees assume a 1-inch meter; larger services pay more. See the meter-size tiers in the source schedules.
Fire Impact Fee (Manatee County fire districts, Industrial) is shown at the last published amount but has not been confirmed with the jurisdiction; it is included in the totals here. Verify before budgeting.
Wastewater Facility Investment Fee (Manatee County Utilities) — over 6" meter and Potable Water Facility Investment Fee (Manatee County Utilities) — over 6" meter are set by the utility and not published online. Contact the levying jurisdiction or utility to verify before budgeting; they are not included as dollar figures here.
View the Full Manatee County Impact Fee Schedule
- Potable Water Facility Investment Fee (Manatee County Utilities) — 1" meter$4,995.00 one-timeManatee County UtilitiesManatee County Utilities facility investment fee, set by water-meter size (commercial schedule); effective 10/1/2019. Meters over 6 inches are priced per gallon of daily reserve capacity.
- Potable Water Facility Investment Fee (Manatee County Utilities) — over 6" meterContact jurisdiction/utility to verifyManatee County UtilitiesCommercial meters over 6 in. pay a Manatee County Utilities potable water facility investment fee of $6.9526 per gallon per day of reserve capacity (schedule effective 10/1/2019). The total depends on the project's demand, so it is not added to the estimate.
- Wastewater Facility Investment Fee (Manatee County Utilities) — 1" meter$9,127.00 one-timeManatee County UtilitiesManatee County Utilities facility investment fee, set by water-meter size (commercial schedule); effective 10/1/2019. Meters over 6 inches are priced per gallon of daily reserve capacity.
- Wastewater Facility Investment Fee (Manatee County Utilities) — over 6" meterContact jurisdiction/utility to verifyManatee County UtilitiesCommercial meters over 6 in. pay a Manatee County Utilities wastewater facility investment fee of $17.162 per gallon per day of reserve capacity (schedule effective 10/1/2019). The total depends on the project's demand, so it is not added to the estimate.
- City Impact Fees (Unincorporated Manatee - N/A placeholder, Industrial)$0.00Manatee CountyUnincorporated Manatee County has no municipal impact fee. Industrial projects there pay the county impact fees and the fire district fee for their location instead.
- Alternative Transportation Impact Fee (Manatee County, Industrial)$8.06/sq ftManatee CountyEffective 9/9/2025. Applies in unincorporated Manatee County only.
- Fire Impact Fee (Manatee County fire districts, Industrial)$0.28/sq ftRequires confirmationCedar Hammock Fire Rescue DistrictCedar Hammock Fire Rescue DistrictFire impact fees in unincorporated Manatee County are levied by independent fire districts, each with its own nonresidential rate. From 10/1/2026 Cedar Hammock charges $1,125.93 for the first 5,000 sq ft plus $0.28 per sq ft above 5,000 (CPI-adjusted each October 1); East Manatee and West Manatee charge $980 plus $0.25 per sq ft above 5,000; North River charges $600 plus $0.15 per sq ft above 5,000. The rate depends on the district the site is in; Cedar Hammock, the highest of the district rates, is the one shown.
- Public Safety Impact Fee (Manatee County, Industrial)$0.25/sq ftManatee CountyEffective 9/9/2025. Applies in unincorporated Manatee County only.
- Law Enforcement Impact Fee (Manatee County, Industrial)$0.09/sq ftManatee CountyEffective 9/9/2025. Applies in unincorporated Manatee County only.
- Impact Fee Administrative Surcharge (Manatee County, Industrial)$0.08/sq ftManatee CountyEffective 9/9/2025. Applies in unincorporated Manatee County only.
- Libraries Impact Fee (Manatee County, Industrial)$0.00Manatee CountyManatee County charges its library impact fee on residential development only. The nonresidential schedule (Ord. 25-15, effective 9/9/2025) has no library column, so industrial construction pays none.
- Parks & Natural Resources Impact Fee (Manatee County, Industrial)$0.00Manatee CountyManatee County charges its parks and natural resources impact fee on residential development only. The nonresidential schedule (Ord. 25-15, effective 9/9/2025) has no parks column, so industrial construction pays none.
Where in Manatee County Are You Building?
Each jurisdiction applies its own fee schedule. Pick yours. Totals shown are for a 25,000 sq ft building, including one-time water/sewer fees (assuming a 1-inch meter). = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.
Unincorporated Manatee County: Office Impact Fees
Office development in unincorporated Manatee County pays $19.13 per square foot in impact fees, plus $14,122.00 in one-time water and sewer connection fees (rates sourced October 21, 2026).
For a 25,000 sq ft building, that comes to at least $492,472.00. The calculator below adjusts to your exact square footage.
The largest line items are Wastewater Facility Investment Fee (Manatee County Utilities) — 1" meter ($9,127.00 one-time), Potable Water Facility Investment Fee (Manatee County Utilities) — 1" meter ($4,995.00 one-time) and Alternative Transportation Impact Fee (Manatee County, Office) ($17.95/sq ft).
Water and sewer connection fees assume a 1-inch meter; larger services pay more. See the meter-size tiers in the source schedules.
Fire Impact Fee (Manatee County fire districts, Office) is shown at the last published amount but has not been confirmed with the jurisdiction; it is included in the totals here. Verify before budgeting.
Wastewater Facility Investment Fee (Manatee County Utilities) — over 6" meter and Potable Water Facility Investment Fee (Manatee County Utilities) — over 6" meter are set by the utility and not published online. Contact the levying jurisdiction or utility to verify before budgeting; they are not included as dollar figures here.
View the Full Manatee County Impact Fee Schedule
- Potable Water Facility Investment Fee (Manatee County Utilities) — 1" meter$4,995.00 one-timeManatee County UtilitiesManatee County Utilities facility investment fee, set by water-meter size (commercial schedule); effective 10/1/2019. Meters over 6 inches are priced per gallon of daily reserve capacity.
- Potable Water Facility Investment Fee (Manatee County Utilities) — over 6" meterContact jurisdiction/utility to verifyManatee County UtilitiesCommercial meters over 6 in. pay a Manatee County Utilities potable water facility investment fee of $6.9526 per gallon per day of reserve capacity (schedule effective 10/1/2019). The total depends on the project's demand, so it is not added to the estimate.
- Wastewater Facility Investment Fee (Manatee County Utilities) — 1" meter$9,127.00 one-timeManatee County UtilitiesManatee County Utilities facility investment fee, set by water-meter size (commercial schedule); effective 10/1/2019. Meters over 6 inches are priced per gallon of daily reserve capacity.
- Wastewater Facility Investment Fee (Manatee County Utilities) — over 6" meterContact jurisdiction/utility to verifyManatee County UtilitiesCommercial meters over 6 in. pay a Manatee County Utilities wastewater facility investment fee of $17.162 per gallon per day of reserve capacity (schedule effective 10/1/2019). The total depends on the project's demand, so it is not added to the estimate.
- City Impact Fees (Unincorporated Manatee - N/A placeholder, Office)$0.00Manatee CountyUnincorporated Manatee County has no municipal impact fee. Office projects there pay the county impact fees and the fire district fee for their location instead.
- Alternative Transportation Impact Fee (Manatee County, Office)$17.95/sq ftManatee CountyEffective 9/9/2025. Applies in unincorporated Manatee County only.
- Public Safety Impact Fee (Manatee County, Office)$0.54/sq ftManatee CountyEffective 9/9/2025. Applies in unincorporated Manatee County only.
- Fire Impact Fee (Manatee County fire districts, Office)$0.28/sq ftRequires confirmationCedar Hammock Fire Rescue DistrictCedar Hammock Fire Rescue DistrictFire impact fees in unincorporated Manatee County are levied by independent fire districts, each with its own nonresidential rate. From 10/1/2026 Cedar Hammock charges $1,125.93 for the first 5,000 sq ft plus $0.28 per sq ft above 5,000 (CPI-adjusted each October 1); East Manatee and West Manatee charge $980 plus $0.25 per sq ft above 5,000; North River charges $600 plus $0.15 per sq ft above 5,000. The rate depends on the district the site is in; Cedar Hammock, the highest of the district rates, is the one shown.
- Law Enforcement Impact Fee (Manatee County, Office)$0.20/sq ftManatee CountyEffective 9/9/2025. Applies in unincorporated Manatee County only.
- Impact Fee Administrative Surcharge (Manatee County, Office)$0.17/sq ftManatee CountyEffective 9/9/2025. Applies in unincorporated Manatee County only.
- Parks & Natural Resources Impact Fee (Manatee County, Office)$0.00Manatee CountyManatee County charges its parks and natural resources impact fee on residential development only. The nonresidential schedule (Ord. 25-15, effective 9/9/2025) has no parks column, so office construction pays none.
- Libraries Impact Fee (Manatee County, Office)$0.00Manatee CountyManatee County charges its library impact fee on residential development only. The nonresidential schedule (Ord. 25-15, effective 9/9/2025) has no library column, so office construction pays none.
Manatee County Impact Fee Calculator
Estimate impact fees for your project. Set to single-family. Drop a pin or search an address for site-specific fees.
Location
Select a location to begin
Once you select an address or drop a pin, we'll identify the responsible city and county and generate a fee breakdown.
How Impact Fees Work in Florida
Florida impact fees are one-time charges on new development, governed by Section 163.31801, Florida Statutes (the Florida Impact Fee Act). The statute requires fees to be based on the most recent and localized data, spent on the infrastructure category they were collected for, and adopted by ordinance.
Since a 2021 amendment (Ch. 2021-63, Laws of Florida), the law also limits how fast fees can rise: increases up to 25% phase in over two years, increases of 25–50% phase in over four years, and increases above 50% are allowed only with a demonstrated extraordinary-circumstances study and at least a two-thirds vote of the governing body.
Counties and cities can both levy impact fees. Inside an incorporated city, a project typically pays the county's countywide fees plus any municipal fees the city has adopted, which is why totals differ between a city and the unincorporated county around it.
For a primer on how impact fees work, see our plain-English guide.
Summary current as of September 2026. This is an editorial summary, not legal advice; see the official statute text and our terms of use.
Manatee County Impact Fee FAQs
What are single-family impact fees in Manatee County, Florida?
A new single-family home in unincorporated Manatee County pays $40,121.47 per unit in impact fees (rates sourced October 21, 2026). Inside city limits, fees are set by each city's own schedule and may be completely different. See the city pages for their rates.
How much are multifamily impact fees in Manatee County?
Multifamily development in unincorporated Manatee County pays $18,154.47 per unit in impact fees (rates sourced October 21, 2026). Rates inside city limits depend on the municipality. Pick your city on this page.
How much are commercial impact fees in Manatee County?
Commercial development in unincorporated Manatee County pays $28.30 per square foot in impact fees, plus $14,122.00 in one-time water and sewer connection fees (assuming a 1-inch meter), at least $1,429,322.00 for a 50,000 sq ft building. This figure includes amounts that have not been confirmed and excludes fees with no published standard amount, so the full cost may be higher; verify before budgeting.
Do South Bradenton and Bayshore Gardens pay Manatee County impact fees?
Yes. South Bradenton and Bayshore Gardens are unincorporated, so new construction there pays the unincorporated Manatee County schedule on this page, not a city schedule. Search a specific address in the calculator below to confirm it sits outside every city limit.
Does Lakewood Ranch pay Manatee County impact fees?
Only in part. Lakewood Ranch spans Manatee and Sarasota counties, so the fee depends on which jurisdiction a parcel is in. Search the address in the calculator below to see the schedule that applies.
See also: Sarasota County Impact Fees.
Do cities in Manatee County charge their own impact fees?
Yes. Every incorporated city applies its own fee schedule. 6 of 6 cities in Manatee County levy municipal impact or utility fees; each city page shows the full schedule that applies inside its limits.
Can Florida impact fees increase at any time?
No. Section 163.31801, Florida Statutes limits increases to 50% at most, phased in over two to four years, unless the local government makes extraordinary-circumstances findings and approves the increase by at least a two-thirds vote.
Fee amounts on this page are compiled from official published schedules and are provided for planning purposes only. Rates change, and project specifics (unit size, meter size, location within special districts) can alter what applies. Always verify current fees with the jurisdiction and utility before relying on them.