Center Hill impact fees by project type
Center Hill: Single-Family Impact Fees
A new single-family home in Center Hill pays at least $3,332.00 per unit in impact fees (rates sourced August 15, 2026). All of it is levied by Sumter County.
The largest line items are Road Impact Fee (Sumter County) ($3,332.00).
Water Connection/Capacity Fee (City of Center Hill) and Sewer Connection/Capacity Fee (City of Center Hill) are set by the utility and not published online. Contact the levying jurisdiction or utility to verify before budgeting; they are not included as dollar figures here.
View the full Center Hill impact fee schedule
- Water Connection/Capacity Fee (City of Center Hill)Requires confirmationCity of Center Hill
- Sewer Connection/Capacity Fee (City of Center Hill)Requires confirmationCity of Center Hill
- Municipal Impact Fees (City of Center Hill)$0.00City of Center Hill
- Road Impact Fee (Sumter County)$3,332.00Sumter CountySumter County Road Impact Fee, single-family detached: $3,332 per home (Phase II, effective 1/1/2026). Levied countywide, including in incorporated cities. Scheduled increases: $3,665 on 1/1/2027 and $3,999 on 1/1/2028.
Where in Sumter County are you building?
Each jurisdiction applies its own fee schedule. Pick yours. = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.
Center Hill: Multifamily Impact Fees
A new multifamily unit in Center Hill pays at least $1,773.00 per unit in impact fees (rates sourced August 15, 2026). All of it is levied by Sumter County.
The largest line items are Road Impact Fee (Sumter County, MF) ($1,773.00).
Sewer Connection/Capacity Fee (City of Center Hill, MF) and Water Connection/Capacity Fee (City of Center Hill, MF) are set by the utility and not published online. Contact the levying jurisdiction or utility to verify before budgeting; they are not included as dollar figures here.
Some fees are tiered by unit size or building type; amounts reflect the representative tier noted in the schedule below.
View the full Center Hill impact fee schedule
- Water Connection/Capacity Fee (City of Center Hill, MF)Requires confirmationCity of Center Hill
- Sewer Connection/Capacity Fee (City of Center Hill, MF)Requires confirmationCity of Center Hill
- Municipal Impact Fees (City of Center Hill, MF)$0.00City of Center Hill
- Road Impact Fee (Sumter County, MF)$1,773.00Mid/High-Rise 4+ floorsSumter CountySumter County Road Impact Fee, multifamily (4+ floors): $1,773 per unit (Phase II, effective 1/1/2026). Levied countywide. Scheduled increases: $1,950 on 1/1/2027 and $2,128 on 1/1/2028. This is the default multifamily tier; units in 1-3 floor buildings pay $2,389.
Where in Sumter County are you building?
Each jurisdiction applies its own fee schedule. Pick yours. = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.
Center Hill: Commercial Impact Fees
Commercial development in Center Hill pays $4.72 per square foot in impact fees (rates sourced August 15, 2026).
For a 50,000 sq ft building, that comes to at least $235,900.00. The calculator below adjusts to your exact square footage.
The largest line items are Road Impact Fee (Sumter County, Commercial) ($4.72/sq ft).
Sewer Connection/Capacity Fee (City of Center Hill) and Water Connection/Capacity Fee (City of Center Hill) are set by the utility and not published online. Municipal Impact Fee (City of Center Hill, Commercial) is set by the city and has no published standard rate. Contact the levying jurisdiction or utility to verify before budgeting; they are not included as dollar figures here.
View the full Center Hill impact fee schedule
- Water Connection/Capacity Fee (City of Center Hill)Requires confirmationCity of Center Hill
- Sewer Connection/Capacity Fee (City of Center Hill)Requires confirmationCity of Center Hill
- Municipal Impact Fee (City of Center Hill, Commercial)Requires confirmationCity of Center Hill
- Road Impact Fee (Sumter County, Commercial)$4.72/sq ftSumter CountyCurrent rate effective January 1, 2026 (Phase II of a four-phase adoption). Scheduled increases: $5,190 per 1,000 sq ft on January 1, 2027; $5,661 on January 1, 2028. Applies countywide, including within incorporated municipalities.
Where in Sumter County are you building?
Each jurisdiction applies its own fee schedule. Pick yours. Totals shown are for a 50,000 sq ft building, including one-time water/sewer fees (assuming a 1-inch meter). = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.
Center Hill: Industrial Impact Fees
Industrial development in Center Hill pays $1.51 per square foot in impact fees (rates sourced August 15, 2026).
For a 50,000 sq ft building, that comes to at least $75,300.00. The calculator below adjusts to your exact square footage.
The largest line items are Road Impact Fee (Sumter County, Industrial) ($1.51/sq ft).
Sewer Connection/Capacity Fee (City of Center Hill) and Water Connection/Capacity Fee (City of Center Hill) are set by the utility and not published online. Municipal Impact Fee (City of Center Hill, Industrial) is set by the city and has no published standard rate. Contact the levying jurisdiction or utility to verify before budgeting; they are not included as dollar figures here.
View the full Center Hill impact fee schedule
- Water Connection/Capacity Fee (City of Center Hill)Requires confirmationCity of Center Hill
- Sewer Connection/Capacity Fee (City of Center Hill)Requires confirmationCity of Center Hill
- Municipal Impact Fee (City of Center Hill, Industrial)Requires confirmationCity of Center Hill
- Road Impact Fee (Sumter County, Industrial)$1.51/sq ftSumter CountyCurrent rate effective January 1, 2026 (Phase II of a four-phase adoption). Scheduled increases: $1,657 per 1,000 sq ft on January 1, 2027; $1,806 on January 1, 2028. Applies countywide, including within incorporated municipalities.
Where in Sumter County are you building?
Each jurisdiction applies its own fee schedule. Pick yours. Totals shown are for a 50,000 sq ft building, including one-time water/sewer fees (assuming a 1-inch meter). = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.
Center Hill: Office Impact Fees
Office development in Center Hill pays $2.96 per square foot in impact fees (rates sourced August 15, 2026).
For a 25,000 sq ft building, that comes to at least $73,975.00. The calculator below adjusts to your exact square footage.
The largest line items are Road Impact Fee (Sumter County, Office) ($2.96/sq ft).
Sewer Connection/Capacity Fee (City of Center Hill) and Water Connection/Capacity Fee (City of Center Hill) are set by the utility and not published online. Municipal Impact Fee (City of Center Hill, Office) is set by the city and has no published standard rate. Contact the levying jurisdiction or utility to verify before budgeting; they are not included as dollar figures here.
View the full Center Hill impact fee schedule
- Water Connection/Capacity Fee (City of Center Hill)Requires confirmationCity of Center Hill
- Sewer Connection/Capacity Fee (City of Center Hill)Requires confirmationCity of Center Hill
- Municipal Impact Fee (City of Center Hill, Office)Requires confirmationCity of Center Hill
- Road Impact Fee (Sumter County, Office)$2.96/sq ftCurrent rate effective January 1, 2026 (Phase II of a four-phase adoption). Scheduled increases: $3,255 per 1,000 sq ft on January 1, 2027; $3,550 on January 1, 2028. Applies countywide, including within incorporated municipalities.
Where in Sumter County are you building?
Each jurisdiction applies its own fee schedule. Pick yours. Totals shown are for a 25,000 sq ft building, including one-time water/sewer fees (assuming a 1-inch meter). = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.
Center Hill impact fee calculator
Estimate impact fees for your project. Set to single-family. Drop a pin or search an address for site-specific fees.
Location
Select a location to begin
Once you select an address or drop a pin, we'll identify the responsible city and county and generate a fee breakdown.
How impact fees work in Florida
Florida impact fees are one-time charges on new development, governed by Section 163.31801, Florida Statutes (the Florida Impact Fee Act). The statute requires fees to be based on the most recent and localized data, spent on the infrastructure category they were collected for, and adopted by ordinance.
Since 2021, the law also limits how fast fees can rise: increases up to 25% phase in over two years, increases of 25–50% phase in over four years, and increases above 50% are allowed only with a demonstrated extraordinary-circumstances study and at least a two-thirds vote of the governing body.
Counties and cities can both levy impact fees. Inside an incorporated city, a project typically pays the county's countywide fees plus any municipal fees the city has adopted, which is why totals differ between a city and the unincorporated county around it.
If you're still asking what are impact fees, start with our guide to the definition, common categories, and legal basis.
Center Hill impact fee FAQs
What are the total impact fees for a single-family home in Center Hill, Florida?
A new single-family home in Center Hill pays at least $3,332.00 per unit in combined impact fees (rates sourced August 15, 2026). 2 additional fees have no published standard amounts and are not included, so the full cost may be higher; verify before budgeting.
How much are commercial impact fees in Center Hill?
Commercial development in Center Hill pays $4.72 per square foot in impact fees, at least $235,900.00 for a 50,000 sq ft building. 3 additional fees have no published standard amounts and are not included, so the full cost may be higher; verify before budgeting.
Does Center Hill charge its own impact fees?
Yes. Center Hill levies its own municipal impact or utility fees, and county-levied fees also apply inside city limits. The schedule on this page shows every fee that applies to development in Center Hill, with the combined total.
Can Florida impact fees increase at any time?
No. Section 163.31801, Florida Statutes limits increases to 50% at most, phased in over two to four years, unless the local government makes extraordinary-circumstances findings and approves the increase by at least a two-thirds vote.
Fee amounts on this page are compiled from official published schedules and are provided for planning purposes only. Rates change, and project specifics (unit size, meter size, location within special districts) can alter what applies. Always verify current fees with the jurisdiction and utility before relying on them.