Horry County Impact Fees by Project Type
Where in Horry County Are You Building?
Each jurisdiction applies its own fee schedule. Pick yours. = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.
Unincorporated Horry County: Single-Family Impact Fees
A new single-family home in unincorporated Horry County pays at least $7,820.00 per unit in impact fees (rates sourced November 19, 2026). Of that, Horry County-levied fees account for $2,050.00 and municipal or utility fees for $5,770.00.
The largest line items are Sewer Impact Fee (GSWSA) ($2,735.00), Development Impact Fee (Horry County) — 1,501 to 2,000 sq ft ($2,050.00) and Water Impact + Tap Fee — GSWSA, $1,225 impact + $790 new tap ($2,015.00).
Fire Impact Fee (Murrells Inlet-Garden City Fire District) is set by the city and has no published standard rate. Contact the levying jurisdiction or utility to verify before budgeting; it is not included as a dollar figure here.
Some fees are tiered by unit size or building type; amounts reflect the representative tier noted in the schedule below.
View the Full Horry County Impact Fee Schedule
- Water Impact + Tap Fee — GSWSA, $1,225 impact + $790 new tap$2,015.00GSWSA, new tapGrand Strand Water & Sewer AuthorityGrand Strand Water and Sewer Authority serves most of unincorporated Horry: water impact fee of $1,225 per residential equivalent unit plus a $790 tap fee for a new tap. Where a tap was already made, as in a developer-built subdivision, the $630 meter base fee applies instead of the tap (option shown).
- Sewer Impact Fee (GSWSA)$2,735.00Grand Strand Water & Sewer AuthorityGrand Strand Water and Sewer Authority sewer impact fee: $2,735 per residential equivalent unit, and a home is 1 unit. Applies only where GSWSA sewer is available; much of unincorporated Horry County uses septic systems and pays no sewer fee. Some areas carry a separate special-area impact fee.
- Sewer Tap Fee (GSWSA)$1,020.00Grand Strand Water & Sewer AuthorityGSWSA sewer tap fee for a standard residential service connection, plus an $80 sewer connection inspection fee. Deeper or nonstandard taps are priced higher. Separate from the sewer impact fee.
- City Development Impact Fees (Horry County - Unincorporated)$0.00Horry CountyUnincorporated Horry County has no municipal development impact fees; the county's own development impact fee applies (listed separately).
- Development Impact Fee (Horry County) — 1,501 to 2,000 sq ft$2,050.00Horry CountyHorry County development impact fee under Ordinance 30-2026 (adopted July 14, 2026), charged per home by floor area: from $995 for 1,000 sq ft or less up to $3,104 for 3,501 sq ft or more. Covers parks, police, fire and medic, emergency operations and solid waste. Unincorporated county only, paid at building permit. Affordable housing for households at or below 80% of county median income is exempt. Not indexed; changes only by ordinance.
- Fire Impact Fee (Murrells Inlet-Garden City Fire District)Requires confirmationMurrells Inlet-Garden City Fire DistrictInside the Murrells Inlet-Garden City Fire District, the district charges its own fire impact fee on new construction: 1% of construction cost for a single-family home, collected with the Horry County building permit in addition to the county impact fee. Not charged elsewhere in the county.
Where in Horry County Are You Building?
Each jurisdiction applies its own fee schedule. Pick yours. = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.
Unincorporated Horry County: Multifamily Impact Fees
A new multifamily unit in unincorporated Horry County pays at least $6,765.00 per unit in impact fees (rates sourced November 19, 2026). Of that, Horry County-levied fees account for $995.00 and municipal or utility fees for $5,770.00.
The largest line items are Sewer Impact Fee (GSWSA, MF) — 1 REU per dwelling unit × $2,735/REU ($2,735.00), Water Impact + Tap Fee (MF) — GSWSA, $1,225 impact + $790 new tap ($2,015.00) and Sewer Tap Fee (GSWSA, MF) ($1,020.00).
Fire Impact Fee (Murrells Inlet-Garden City Fire District, MF) is set by the city and has no published standard rate. Contact the levying jurisdiction or utility to verify before budgeting; it is not included as a dollar figure here.
Some fees are tiered by unit size or building type; amounts reflect the representative tier noted in the schedule below.
View the Full Horry County Impact Fee Schedule
- Water Impact + Tap Fee (MF) — GSWSA, $1,225 impact + $790 new tap$2,015.00GSWSA, new tapGrand Strand Water & Sewer AuthorityGrand Strand Water and Sewer Authority serves most of unincorporated Horry: water impact fee of $1,225 per residential equivalent unit plus a $790 tap fee for a new tap. Where a tap was already made, as in a developer-built subdivision, the $630 meter base fee applies instead of the tap (option shown). Each dwelling counts as one unit.
- Sewer Impact Fee (GSWSA, MF) — 1 REU per dwelling unit × $2,735/REU$2,735.00Grand Strand Water & Sewer AuthorityGSWSA sewer impact fee: $2,735 per residential equivalent unit. GSWSA assesses each dwelling unit as one unit, whether single family or multifamily and whether individually or master metered. Applies only where GSWSA sewer is available.
- Sewer Tap Fee (GSWSA, MF)$1,020.00Grand Strand Water & Sewer AuthorityGSWSA sewer tap fee for a standard service connection. Charged per connection, not per unit: a building served by one sewer service line pays it once. Deeper or nonstandard taps are priced higher, and a separate $80 sewer connection inspection fee applies. Separate from the sewer impact fee, which is charged per dwelling unit.
- City Development Impact Fees (Horry County - Unincorporated, MF)$0.00Horry CountyUnincorporated Horry County has no municipal development impact fees; the county's own development impact fee applies (listed separately).
- Development Impact Fee (Horry County, MF) — 1,000 sq ft or less$995.00Horry CountyHorry County development impact fee under Ordinance 30-2026 (adopted July 14, 2026), charged per dwelling unit by unit floor area on the same size tiers as houses: $995 for a unit of 1,000 sq ft or less, up to $3,104 for 3,501 sq ft or more. Covers parks, police, fire and medic, emergency operations and solid waste. Unincorporated county only, paid at building permit.
- Fire Impact Fee (Murrells Inlet-Garden City Fire District, MF)Requires confirmationMurrells Inlet-Garden City Fire DistrictInside the Murrells Inlet-Garden City Fire District, the district charges its own fire impact fee on new construction, set as a percentage of construction cost: 2% for condominiums, townhouses, high-rise buildings and commercial construction under its 1985 enabling act. Collected with the Horry County building permit, in addition to the county impact fee. Not charged elsewhere in the county.
Where in Horry County Are You Building?
Each jurisdiction applies its own fee schedule. Pick yours. Totals shown are for a 50,000 sq ft building, including one-time water/sewer fees (assuming a 1-inch meter). * = one-time water/sewer connection charges only; no per-sq-ft impact fee schedule sourced for that jurisdiction. = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.
Unincorporated Horry County: Commercial Impact Fees
Commercial development in unincorporated Horry County pays $1.78 per square foot in impact fees, plus $17,650.00 in one-time water and sewer connection fees (rates sourced November 19, 2026).
For a 50,000 sq ft building, that comes to at least $106,450.00. The calculator below adjusts to your exact square footage.
The largest line items are Sewer Impact Fee (GSWSA) — 1" meter, 4 REU × $2,735/REU ($10,940.00 one-time), Water Impact Fee (GSWSA) — 1" meter, 4 REU × $1,225/REU ($4,900.00 one-time) and County Impact Fee (Horry County, Commercial) ($1.78/sq ft).
Water and sewer connection fees assume a 1-inch meter; larger services pay more. See the meter-size tiers in the source schedules.
Water Tap Fee (GSWSA) and Sewer Tap Fee (GSWSA) are shown at the last published amount but have not been confirmed with the jurisdiction; they are included in the totals here. Verify before budgeting.
Fire Impact Fee (Murrells Inlet-Garden City Fire District, Commercial) is set by the city and has no published standard rate. Contact the levying jurisdiction or utility to verify before budgeting; it is not included as a dollar figure here.
View the Full Horry County Impact Fee Schedule
- Water Impact Fee (GSWSA) — 1" meter, 4 REU × $1,225/REU$4,900.00 one-timeGrand Strand Water & Sewer AuthorityGSWSA water impact fee: $1,225 per residential equivalent unit (REU), charged on the higher of the meter-size minimum or the project's calculated demand. Shown: 1-inch meter, 4 REU minimum. Some areas carry supplemental impact fees, and other providers serve parts of the unincorporated county (Bucksport Water, Ocean Lakes, small private systems).
- Water Tap Fee (GSWSA)$790.00 one-timeRequires confirmationGrand Strand Water & Sewer AuthorityGSWSA water tap fee for a new service tap. Larger commercial taps may be priced differently by the Authority.
- Sewer Impact Fee (GSWSA) — 1" meter, 4 REU × $2,735/REU$10,940.00 one-timeGrand Strand Water & Sewer AuthorityGSWSA sewer impact fee: $2,735 per residential equivalent unit (REU), charged on the higher of the water-meter-size minimum or the project's calculated demand. Shown: 1-inch meter, 4 REU minimum. Some areas carry supplemental impact fees; parts of the unincorporated county are on septic or other systems.
- Sewer Tap Fee (GSWSA)$1,020.00 one-timeRequires confirmationGrand Strand Water & Sewer AuthorityGSWSA sewer tap fee is $1,020 plus an $80 connection inspection fee.
- City Impact Fee (Horry County - Unincorporated, Commercial)$0.00There is no municipal government in unincorporated Horry County; only Horry County's impact fee applies here (shown on the County records).
- County Impact Fee (Horry County, Commercial)$1.78/sq ftHorry CountyHorry County development impact fee under Ord. No. 30-2026 (adopted July 14, 2026): police, fire/medic and emergency operations center components, charged per 1,000 sq ft of retail floor area. Applies only in unincorporated Horry County. Parks, recreation and solid waste components do not apply to nonresidential development. Inside the Murrells Inlet-Garden City Fire District, the district also charges its own fire impact fee.
- Fire Impact Fee (Murrells Inlet-Garden City Fire District, Commercial)Requires confirmationMurrells Inlet-Garden City Fire DistrictInside the Murrells Inlet-Garden City Fire District, the district charges its own fire impact fee on all commercial construction: 2% of construction cost, collected with the Horry County building permit in addition to the county impact fee. Not charged elsewhere in the county.
Where in Horry County Are You Building?
Each jurisdiction applies its own fee schedule. Pick yours. Totals shown are for a 50,000 sq ft building, including one-time water/sewer fees (assuming a 1-inch meter). * = one-time water/sewer connection charges only; no per-sq-ft impact fee schedule sourced for that jurisdiction. = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.
Unincorporated Horry County: Industrial Impact Fees
Industrial development in unincorporated Horry County pays $0.24 per square foot in impact fees, plus $17,650.00 in one-time water and sewer connection fees (rates sourced November 19, 2026).
For a 50,000 sq ft building, that comes to at least $29,450.00. The calculator below adjusts to your exact square footage.
The largest line items are Sewer Impact Fee (GSWSA) — 1" meter, 4 REU × $2,735/REU ($10,940.00 one-time), Water Impact Fee (GSWSA) — 1" meter, 4 REU × $1,225/REU ($4,900.00 one-time) and County Impact Fee (Horry County, Industrial) ($0.24/sq ft).
Water and sewer connection fees assume a 1-inch meter; larger services pay more. See the meter-size tiers in the source schedules.
Water Tap Fee (GSWSA) and Sewer Tap Fee (GSWSA) are shown at the last published amount but have not been confirmed with the jurisdiction; they are included in the totals here. Verify before budgeting.
Fire Impact Fee (Murrells Inlet-Garden City Fire District, Industrial) is set by the city and has no published standard rate. Contact the levying jurisdiction or utility to verify before budgeting; it is not included as a dollar figure here.
View the Full Horry County Impact Fee Schedule
- Water Impact Fee (GSWSA) — 1" meter, 4 REU × $1,225/REU$4,900.00 one-timeGrand Strand Water & Sewer AuthorityGSWSA water impact fee: $1,225 per residential equivalent unit (REU), charged on the higher of the meter-size minimum or the project's calculated demand. Shown: 1-inch meter, 4 REU minimum. Some areas carry supplemental impact fees, and other providers serve parts of the unincorporated county (Bucksport Water, Ocean Lakes, small private systems).
- Water Tap Fee (GSWSA)$790.00 one-timeRequires confirmationGrand Strand Water & Sewer AuthorityGSWSA water tap fee for a new service tap. Larger commercial taps may be priced differently by the Authority.
- Sewer Impact Fee (GSWSA) — 1" meter, 4 REU × $2,735/REU$10,940.00 one-timeGrand Strand Water & Sewer AuthorityGSWSA sewer impact fee: $2,735 per residential equivalent unit (REU), charged on the higher of the water-meter-size minimum or the project's calculated demand. Shown: 1-inch meter, 4 REU minimum. Some areas carry supplemental impact fees; parts of the unincorporated county are on septic or other systems.
- Sewer Tap Fee (GSWSA)$1,020.00 one-timeRequires confirmationGrand Strand Water & Sewer AuthorityGSWSA sewer tap fee is $1,020 plus an $80 connection inspection fee.
- City Impact Fee (Horry County - Unincorporated, Industrial)$0.00There is no municipal government in unincorporated Horry County; only Horry County's impact fee applies here (shown on the County records).
- County Impact Fee (Horry County, Industrial)$0.24/sq ftHorry CountyHorry County development impact fee under Ord. No. 30-2026 (adopted July 14, 2026): police, fire/medic and emergency operations center components, charged per 1,000 sq ft of industrial floor area. Applies only in unincorporated Horry County. Parks, recreation and solid waste components do not apply to nonresidential development. Inside the Murrells Inlet-Garden City Fire District, the district also charges its own fire impact fee.
- Fire Impact Fee (Murrells Inlet-Garden City Fire District, Industrial)Requires confirmationMurrells Inlet-Garden City Fire DistrictInside the Murrells Inlet-Garden City Fire District, the district charges its own fire impact fee on all commercial construction: 2% of construction cost, collected with the Horry County building permit in addition to the county impact fee. Not charged elsewhere in the county.
Where in Horry County Are You Building?
Each jurisdiction applies its own fee schedule. Pick yours. Totals shown are for a 25,000 sq ft building, including one-time water/sewer fees (assuming a 1-inch meter). * = one-time water/sewer connection charges only; no per-sq-ft impact fee schedule sourced for that jurisdiction. = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.
Unincorporated Horry County: Office Impact Fees
Office development in unincorporated Horry County pays $0.80 per square foot in impact fees, plus $17,650.00 in one-time water and sewer connection fees (rates sourced November 19, 2026).
For a 25,000 sq ft building, that comes to at least $37,575.00. The calculator below adjusts to your exact square footage.
The largest line items are Sewer Impact Fee (GSWSA) — 1" meter, 4 REU × $2,735/REU ($10,940.00 one-time), Water Impact Fee (GSWSA) — 1" meter, 4 REU × $1,225/REU ($4,900.00 one-time) and County Impact Fee (Horry County, Office) ($0.80/sq ft).
Water and sewer connection fees assume a 1-inch meter; larger services pay more. See the meter-size tiers in the source schedules.
Water Tap Fee (GSWSA) and Sewer Tap Fee (GSWSA) are shown at the last published amount but have not been confirmed with the jurisdiction; they are included in the totals here. Verify before budgeting.
Fire Impact Fee (Murrells Inlet-Garden City Fire District, Office) is set by the city and has no published standard rate. Contact the levying jurisdiction or utility to verify before budgeting; it is not included as a dollar figure here.
View the Full Horry County Impact Fee Schedule
- Water Impact Fee (GSWSA) — 1" meter, 4 REU × $1,225/REU$4,900.00 one-timeGrand Strand Water & Sewer AuthorityGSWSA water impact fee: $1,225 per residential equivalent unit (REU), charged on the higher of the meter-size minimum or the project's calculated demand. Shown: 1-inch meter, 4 REU minimum. Some areas carry supplemental impact fees, and other providers serve parts of the unincorporated county (Bucksport Water, Ocean Lakes, small private systems).
- Water Tap Fee (GSWSA)$790.00 one-timeRequires confirmationGrand Strand Water & Sewer AuthorityGSWSA water tap fee for a new service tap. Larger commercial taps may be priced differently by the Authority.
- Sewer Impact Fee (GSWSA) — 1" meter, 4 REU × $2,735/REU$10,940.00 one-timeGrand Strand Water & Sewer AuthorityGSWSA sewer impact fee: $2,735 per residential equivalent unit (REU), charged on the higher of the water-meter-size minimum or the project's calculated demand. Shown: 1-inch meter, 4 REU minimum. Some areas carry supplemental impact fees; parts of the unincorporated county are on septic or other systems.
- Sewer Tap Fee (GSWSA)$1,020.00 one-timeRequires confirmationGrand Strand Water & Sewer AuthorityGSWSA sewer tap fee is $1,020 plus an $80 connection inspection fee.
- City Impact Fee (Horry County - Unincorporated, Office)$0.00There is no municipal government in unincorporated Horry County; only Horry County's impact fee applies here (shown on the County records).
- County Impact Fee (Horry County, Office)$0.80/sq ftHorry CountyHorry County development impact fee under Ord. No. 30-2026 (adopted July 14, 2026): police, fire/medic and emergency operations center components, charged per 1,000 sq ft of office floor area. Applies only in unincorporated Horry County. Parks, recreation and solid waste components do not apply to nonresidential development. Inside the Murrells Inlet-Garden City Fire District, the district also charges its own fire impact fee.
- Fire Impact Fee (Murrells Inlet-Garden City Fire District, Office)Requires confirmationMurrells Inlet-Garden City Fire DistrictInside the Murrells Inlet-Garden City Fire District, the district charges its own fire impact fee on all commercial construction: 2% of construction cost, collected with the Horry County building permit in addition to the county impact fee. Not charged elsewhere in the county.
Horry County Impact Fee Calculator
Estimate impact fees for your project. Set to single-family. Drop a pin or search an address for site-specific fees.
Location
Select a location to begin
Once you select an address or drop a pin, we'll identify the responsible city and county and generate a fee breakdown.
How Development Impact Fees Work in South Carolina
South Carolina counties and municipalities assess development impact fees under the Development Impact Fee Act (S.C. Code 6-1-910 et seq.). Only a government with a comprehensive plan (or a capital improvements plan that substantially complies with the Act) may impose one, by an ordinance approved by a positive majority, and before charging residential units it must report how the fee affects the availability of affordable housing.
Fees may fund only the public facilities the Act lists: water and wastewater, solid waste, roads and bridges, stormwater and flood control, public safety (law enforcement, fire, emergency medical and street lighting), capital equipment and vehicles of at least $100,000 a unit, parks, libraries and recreation, and, since 2016, K-12 public school facilities. A fee may not exceed the development's proportionate share of the cost, after credits for land, money or improvements the developer contributes and for other funding sources.
Fee revenue is kept in interest-bearing accounts by category and service area and spent only on that category in that area. A fee not spent within three years of the date it was scheduled to be spent, or paid on a building permit that is denied, is refunded with its share of interest. The fee is due no earlier than the building permit (or the development permit where no building permit is needed).
Water and sewer charges usually come from the utility that serves a parcel: the Act's definition of an impact fee excludes connection or hookup charges, and a water or wastewater provider meeting the conditions of 6-1-1080 sets its impact fees outside the Act. That is why totals differ between a city, its neighbors and the unincorporated county around it.
If you're still asking what are impact fees, start with our guide to the definition, common categories, and legal basis.
Summary current as of November 2026. This is an editorial summary, not legal advice; see the official statute text and our terms of use.
Horry County Impact Fee FAQs
What are single-family impact fees in Horry County, South Carolina?
A new single-family home in unincorporated Horry County pays at least $7,820.00 per unit in impact fees (rates sourced November 19, 2026). One additional fee has no published standard amount and is not included, so the full cost may be higher; verify before budgeting. Inside city limits, fees are set by each city's own schedule and may be completely different. See the city pages for their rates.
How much are multifamily impact fees in Horry County?
Multifamily development in unincorporated Horry County pays at least $6,765.00 per unit in impact fees (rates sourced November 19, 2026). One additional fee has no published standard amount and is not included, so the full cost may be higher; verify before budgeting. Rates inside city limits depend on the municipality. Pick your city on this page.
How much are commercial impact fees in Horry County?
Commercial development in unincorporated Horry County pays $1.78 per square foot in impact fees, plus $17,650.00 in one-time water and sewer connection fees (assuming a 1-inch meter), at least $106,450.00 for a 50,000 sq ft building. This figure includes amounts that have not been confirmed and excludes fees with no published standard amount, so the full cost may be higher; verify before budgeting.
Do cities in Horry County charge their own impact fees?
Yes. Every incorporated city applies its own fee schedule. 8 of 8 cities in Horry County levy municipal impact or utility fees; each city page shows the full schedule that applies inside its limits.
Can a South Carolina impact fee be raised after it is adopted?
Only through a new ordinance. Under S.C. Code 6-1-940 the government is bound by the amount its impact fee ordinance sets for each unit of development and may not charge higher or additional impact fees for the same purpose unless the project's service units increase or its scope changes, and then only for the added share. Water and sewer capacity and tap fees set by utilities follow each provider's own rate process.
Fee amounts on this page are compiled from official published schedules and are provided for planning purposes only. Rates change, and project specifics (unit size, meter size, location within special districts) can alter what applies. Always verify current fees with the jurisdiction and utility before relying on them.