Myrtle Beach: Single-Family Impact Fees
A new single-family home in Myrtle Beach pays $10,167.00 per unit in impact fees (rates sourced November 11, 2026). Every line item is levied at the municipal or utility level.
The largest line items are Sewer Tap / Connection Charge (City of Myrtle Beach) — 6" lateral ($3,318.00), Water Impact Fee (City of Myrtle Beach) — 1.00 ERU × $2,938/ERU ($2,938.00) and Sewer Impact Fee (City of Myrtle Beach) — 1.00 ERU × $2,786/ERU ($2,786.00).
Some fees are tiered by unit size or building type; amounts reflect the representative tier noted in the schedule below.
View the Full Myrtle Beach Impact Fee Schedule
- Water Impact Fee (City of Myrtle Beach) — 1.00 ERU × $2,938/ERU$2,938.003 BRCity of Myrtle BeachCity of Myrtle Beach water impact fee of $2,938 per ERU inside the city, effective July 1, 2026; a 3-bedroom house counts as 1 ERU. The rate rises each July 1 under the budget ordinance.
- Water Tap / Connection Charge (City of Myrtle Beach) — 3/4" meter$1,125.00City of Myrtle BeachCity of Myrtle Beach water connection charge for a 3/4 inch meter: $1,125, the same inside and outside the city, effective July 1, 2026. Where a licensed contractor installs the line, a $100 inspection fee applies instead.
- Sewer Tap / Connection Charge (City of Myrtle Beach) — 6" lateral$3,318.00City of Myrtle BeachCity of Myrtle Beach sewer connection charge for a 6 inch lateral: $3,318, effective July 1, 2026. Six inches is the standard lateral.
- Sewer Impact Fee (City of Myrtle Beach) — 1.00 ERU × $2,786/ERU$2,786.003 BRCity of Myrtle BeachCity of Myrtle Beach sewer impact fee of $2,786 per ERU inside the city, effective July 1, 2026; a 3-bedroom house counts as 1 ERU.
- City Development Impact Fees (City of Myrtle Beach)$0.00City of Myrtle Beach
- County Development Impact Fee (Horry County)$0.00Horry CountyHorry County's development impact fee applies only in unincorporated Horry County, so it is not charged inside city limits.
Where in Horry County Are You Building?
Each jurisdiction applies its own fee schedule. Pick yours. = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.
Myrtle Beach: Multifamily Impact Fees
A new multifamily unit in Myrtle Beach pays $8,736.00 per unit in impact fees (rates sourced November 11, 2026). Every line item is levied at the municipal or utility level.
The largest line items are Sewer Tap / Connection Charge (City of Myrtle Beach, MF) ($3,318.00), Water Impact Fee (City of Myrtle Beach) (MF) — 0.75 ERU × $2,938/ERU ($2,203.50) and Sewer Impact Fee (City of Myrtle Beach) (MF) — 0.75 ERU × $2,786/ERU ($2,089.50).
Some fees are tiered by unit size or building type; amounts reflect the representative tier noted in the schedule below.
View the Full Myrtle Beach Impact Fee Schedule
- Water Impact Fee (City of Myrtle Beach) (MF) — 0.75 ERU × $2,938/ERU$2,203.502 BRCity of Myrtle BeachCity of Myrtle Beach water impact fee of $2,938 per ERU inside the city, effective July 1, 2026; a 2-bedroom apartment counts as 0.75 ERU.
- Water Tap / Connection Charge (City of Myrtle Beach, MF) — 3/4" meter$1,125.00City of Myrtle BeachCity of Myrtle Beach water connection charge for a 3/4 inch meter: $1,125, the same inside and outside the city, effective July 1, 2026. Where a licensed contractor installs the line, a $100 inspection fee applies instead. A building on one meter pays once.
- Sewer Tap / Connection Charge (City of Myrtle Beach, MF)$3,318.006" lateralCity of Myrtle BeachMyrtle Beach charges sewer connection by lateral size, not per unit: $3,318 for a 6-inch lateral (8-inch $3,853, 10-inch $4,291), effective July 1, 2026. A building on one lateral pays it once. The sewer impact fee is charged separately per unit.
- Sewer Impact Fee (City of Myrtle Beach) (MF) — 0.75 ERU × $2,786/ERU$2,089.502 BRCity of Myrtle BeachCity of Myrtle Beach sewer impact fee of $2,786 per ERU inside the city, effective July 1, 2026; a 2-bedroom apartment counts as 0.75 ERU.
- City Development Impact Fees (City of Myrtle Beach, MF)$0.00City of Myrtle Beach
- County Development Impact Fee (Horry County, MF)$0.00Horry CountyHorry County's development impact fee applies only in unincorporated Horry County, so it is not charged inside city limits.
Where in Horry County Are You Building?
Each jurisdiction applies its own fee schedule. Pick yours. = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.
Myrtle Beach: Commercial Impact Fees
Commercial development in Myrtle Beach pays no per-square-foot impact fees, but owes $10,471.00 in one-time water and sewer connection fees (rates sourced November 11, 2026).
For a 50,000 sq ft building, that comes to about $10,471.00. The calculator below adjusts to your exact square footage.
The largest line items are Sewer Connection Charge (City of Myrtle Beach) — 6" lateral ($3,318.00 one-time) and Water Connection Charge (City of Myrtle Beach) — 1" meter ($1,429.00 one-time).
Water and sewer connection fees assume a 1-inch meter; larger services pay more. See the meter-size tiers in the source schedules.
Sewer Impact Fee (City of Myrtle Beach) and Water Impact Fee (City of Myrtle Beach) are shown at the last published amount but have not been confirmed with the jurisdiction; they are included in the totals here. Verify before budgeting.
View the Full Myrtle Beach Impact Fee Schedule
- Water Impact Fee (City of Myrtle Beach)$2,938.00 one-timeRequires confirmationEffective July 1, 2026 (FY2026-27 budget, Ordinance 2026-43): $2,938 per ERU in-city, $4,407 out-of-city. One ERU = 300 gallons/day; a commercial project is assigned an ERU count by the City. Rate escalates about 5% each July through FY2031. Separate from the water connection charge.
- Water Connection Charge (City of Myrtle Beach) — 1" meter$1,429.00 one-timeEffective July 1, 2026 (Ordinance 2026-43); rate for a 1-inch meter. The water connection charge is set by meter size and is separate from the water impact fee. Reusing an existing service line incurs no connection charge.
- Sewer Connection Charge (City of Myrtle Beach) — 6" lateral$3,318.00 one-timeEffective July 1, 2026; rate for the standard 6-inch sewer lateral. Set by lateral size and separate from the sewer impact fee. Reusing an existing lateral incurs no connection charge.
- Sewer Impact Fee (City of Myrtle Beach)$2,786.00 one-timeRequires confirmationEffective July 1, 2026 (Ordinance 2026-43): $2,786 per ERU in-city, $4,180 out-of-city. One ERU = 300 gallons/day; a commercial project is assigned an ERU count by the City. Rate escalates about 5% each July through FY2031. Separate from the sewer connection charge.
- City Impact Fee (City of Myrtle Beach, Commercial)$0.00The City of Myrtle Beach does not levy a municipal impact fee on nonresidential development. Water and sewer capacity fees are charged separately (see the Water/Sewer records).
- County Impact Fee (Horry County, Commercial)$0.00Horry County development impact fees apply only in unincorporated Horry County; they are not levied within the City of Myrtle Beach.
Where in Horry County Are You Building?
Each jurisdiction applies its own fee schedule. Pick yours. Totals shown are for a 50,000 sq ft building, including one-time water/sewer fees (assuming a 1-inch meter). * = one-time water/sewer connection charges only; no per-sq-ft impact fee schedule sourced for that jurisdiction. = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.
Myrtle Beach: Industrial Impact Fees
Industrial development in Myrtle Beach pays no per-square-foot impact fees, but owes $10,471.00 in one-time water and sewer connection fees (rates sourced November 11, 2026).
For a 50,000 sq ft building, that comes to about $10,471.00. The calculator below adjusts to your exact square footage.
The largest line items are Sewer Connection Charge (City of Myrtle Beach) — 6" lateral ($3,318.00 one-time) and Water Connection Charge (City of Myrtle Beach) — 1" meter ($1,429.00 one-time).
Water and sewer connection fees assume a 1-inch meter; larger services pay more. See the meter-size tiers in the source schedules.
Sewer Impact Fee (City of Myrtle Beach) and Water Impact Fee (City of Myrtle Beach) are shown at the last published amount but have not been confirmed with the jurisdiction; they are included in the totals here. Verify before budgeting.
View the Full Myrtle Beach Impact Fee Schedule
- Water Impact Fee (City of Myrtle Beach)$2,938.00 one-timeRequires confirmationEffective July 1, 2026 (FY2026-27 budget, Ordinance 2026-43): $2,938 per ERU in-city, $4,407 out-of-city. One ERU = 300 gallons/day; a commercial project is assigned an ERU count by the City. Rate escalates about 5% each July through FY2031. Separate from the water connection charge.
- Water Connection Charge (City of Myrtle Beach) — 1" meter$1,429.00 one-timeEffective July 1, 2026 (Ordinance 2026-43); rate for a 1-inch meter. The water connection charge is set by meter size and is separate from the water impact fee. Reusing an existing service line incurs no connection charge.
- Sewer Connection Charge (City of Myrtle Beach) — 6" lateral$3,318.00 one-timeEffective July 1, 2026; rate for the standard 6-inch sewer lateral. Set by lateral size and separate from the sewer impact fee. Reusing an existing lateral incurs no connection charge.
- Sewer Impact Fee (City of Myrtle Beach)$2,786.00 one-timeRequires confirmationEffective July 1, 2026 (Ordinance 2026-43): $2,786 per ERU in-city, $4,180 out-of-city. One ERU = 300 gallons/day; a commercial project is assigned an ERU count by the City. Rate escalates about 5% each July through FY2031. Separate from the sewer connection charge.
- City Impact Fee (City of Myrtle Beach, Industrial)$0.00The City of Myrtle Beach does not levy a municipal impact fee on nonresidential development. Water and sewer capacity fees are charged separately (see the Water/Sewer records).
- County Impact Fee (Horry County, Industrial)$0.00Horry County development impact fees apply only in unincorporated Horry County; they are not levied within the City of Myrtle Beach.
Where in Horry County Are You Building?
Each jurisdiction applies its own fee schedule. Pick yours. Totals shown are for a 50,000 sq ft building, including one-time water/sewer fees (assuming a 1-inch meter). * = one-time water/sewer connection charges only; no per-sq-ft impact fee schedule sourced for that jurisdiction. = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.
Myrtle Beach: Office Impact Fees
Office development in Myrtle Beach pays no per-square-foot impact fees, but owes $10,471.00 in one-time water and sewer connection fees (rates sourced November 11, 2026).
For a 25,000 sq ft building, that comes to about $10,471.00. The calculator below adjusts to your exact square footage.
The largest line items are Sewer Connection Charge (City of Myrtle Beach) — 6" lateral ($3,318.00 one-time) and Water Connection Charge (City of Myrtle Beach) — 1" meter ($1,429.00 one-time).
Water and sewer connection fees assume a 1-inch meter; larger services pay more. See the meter-size tiers in the source schedules.
Sewer Impact Fee (City of Myrtle Beach) and Water Impact Fee (City of Myrtle Beach) are shown at the last published amount but have not been confirmed with the jurisdiction; they are included in the totals here. Verify before budgeting.
View the Full Myrtle Beach Impact Fee Schedule
- Water Impact Fee (City of Myrtle Beach)$2,938.00 one-timeRequires confirmationEffective July 1, 2026 (FY2026-27 budget, Ordinance 2026-43): $2,938 per ERU in-city, $4,407 out-of-city. One ERU = 300 gallons/day; a commercial project is assigned an ERU count by the City. Rate escalates about 5% each July through FY2031. Separate from the water connection charge.
- Water Connection Charge (City of Myrtle Beach) — 1" meter$1,429.00 one-timeEffective July 1, 2026 (Ordinance 2026-43); rate for a 1-inch meter. The water connection charge is set by meter size and is separate from the water impact fee. Reusing an existing service line incurs no connection charge.
- Sewer Connection Charge (City of Myrtle Beach) — 6" lateral$3,318.00 one-timeEffective July 1, 2026; rate for the standard 6-inch sewer lateral. Set by lateral size and separate from the sewer impact fee. Reusing an existing lateral incurs no connection charge.
- Sewer Impact Fee (City of Myrtle Beach)$2,786.00 one-timeRequires confirmationEffective July 1, 2026 (Ordinance 2026-43): $2,786 per ERU in-city, $4,180 out-of-city. One ERU = 300 gallons/day; a commercial project is assigned an ERU count by the City. Rate escalates about 5% each July through FY2031. Separate from the sewer connection charge.
- City Impact Fee (City of Myrtle Beach, Office)$0.00The City of Myrtle Beach does not levy a municipal impact fee on nonresidential development. Water and sewer capacity fees are charged separately (see the Water/Sewer records).
- County Impact Fee (Horry County, Office)$0.00Horry County development impact fees apply only in unincorporated Horry County; they are not levied within the City of Myrtle Beach.
Where in Horry County Are You Building?
Each jurisdiction applies its own fee schedule. Pick yours. Totals shown are for a 25,000 sq ft building, including one-time water/sewer fees (assuming a 1-inch meter). * = one-time water/sewer connection charges only; no per-sq-ft impact fee schedule sourced for that jurisdiction. = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.
Myrtle Beach Impact Fee Calculator
Estimate impact fees for your project. Set to single-family. Drop a pin or search an address for site-specific fees.
Location
Select a location to begin
Once you select an address or drop a pin, we'll identify the responsible city and county and generate a fee breakdown.
How Development Impact Fees Work in South Carolina
South Carolina counties and municipalities assess development impact fees under the Development Impact Fee Act (S.C. Code 6-1-910 et seq.). Only a government with a comprehensive plan (or a capital improvements plan that substantially complies with the Act) may impose one, by an ordinance approved by a positive majority, and before charging residential units it must report how the fee affects the availability of affordable housing.
Fees may fund only the public facilities the Act lists: water and wastewater, solid waste, roads and bridges, stormwater and flood control, public safety (law enforcement, fire, emergency medical and street lighting), capital equipment and vehicles of at least $100,000 a unit, parks, libraries and recreation, and, since 2016, K-12 public school facilities. A fee may not exceed the development's proportionate share of the cost, after credits for land, money or improvements the developer contributes and for other funding sources.
Fee revenue is kept in interest-bearing accounts by category and service area and spent only on that category in that area. A fee not spent within three years of the date it was scheduled to be spent, or paid on a building permit that is denied, is refunded with its share of interest. The fee is due no earlier than the building permit (or the development permit where no building permit is needed).
Water and sewer charges usually come from the utility that serves a parcel: the Act's definition of an impact fee excludes connection or hookup charges, and a water or wastewater provider meeting the conditions of 6-1-1080 sets its impact fees outside the Act. That is why totals differ between a city, its neighbors and the unincorporated county around it.
If you're still asking what are impact fees, start with our guide to the definition, common categories, and legal basis.
Summary current as of November 2026. This is an editorial summary, not legal advice; see the official statute text and our terms of use.
Myrtle Beach Impact Fee FAQs
What are the total impact fees for a single-family home in Myrtle Beach, South Carolina?
A new single-family home in Myrtle Beach pays $10,167.00 per unit in combined impact fees (rates sourced November 11, 2026).
How much are commercial impact fees in Myrtle Beach?
Commercial development in Myrtle Beach pays no per-square-foot impact fees, but owes $10,471.00 in one-time water and sewer connection fees (assuming a 1-inch meter). This figure includes amounts that have not been confirmed with the jurisdiction; verify before budgeting.
Does Myrtle Beach charge its own impact fees?
Yes. Myrtle Beach levies its own municipal impact or utility fees. Horry County does not currently add county-level impact fees inside Myrtle Beach. The schedule on this page shows every fee that applies to development in Myrtle Beach.
Can a South Carolina impact fee be raised after it is adopted?
Only through a new ordinance. Under S.C. Code 6-1-940 the government is bound by the amount its impact fee ordinance sets for each unit of development and may not charge higher or additional impact fees for the same purpose unless the project's service units increase or its scope changes, and then only for the added share. Water and sewer capacity and tap fees set by utilities follow each provider's own rate process.
Fee amounts on this page are compiled from official published schedules and are provided for planning purposes only. Rates change, and project specifics (unit size, meter size, location within special districts) can alter what applies. Always verify current fees with the jurisdiction and utility before relying on them.