Deltona applies its own fee schedule: municipal fees plus the Volusia County-levied fees that apply inside city limits. Combined, a new single-family home pays $25,216.57 per unit (rates sourced ). The full breakdown is below.

Deltona Impact Fees by Project Type

Deltona: Single-Family Impact Fees

A new single-family home in Deltona pays $25,216.57 per unit in impact fees (rates sourced August 19, 2026). Of that, Volusia County-levied fees account for $13,200.67 and municipal or utility fees for $12,015.90.

The largest line items are County School Impact Fee (Volusia County) ($7,022.70), Sewer Connection Fee (Deltona) ($5,726.00) and County Thoroughfare Road Impact Fee (Volusia County) ($5,464.00).

Some fees are tiered by unit size or building type; amounts reflect the representative tier noted in the schedule below.

View the Full Deltona Impact Fee Schedule
Water$3,334.00
  • Water Connection Fee (Deltona)
    City of Deltona
    Deltona Water charges a water capital charge of $3,220 plus a capital financing recovery fee of $114 for each equivalent residential connection, a total of $3,334 for a single-family home. The amounts took effect February 1, 2026 and are held at that level through the 2029-30 fiscal year. Meter installation and tapping costs are billed separately.
    $3,334.00
Sewer$5,726.00
  • Sewer Connection Fee (Deltona)
    City of Deltona
    Deltona Water charges a wastewater capital charge of $5,240 plus a capital financing recovery fee of $486 for each equivalent residential connection, a total of $5,726 for a single-family home. The amounts took effect February 1, 2026 and are held at that level through the 2029-30 fiscal year.
    $5,726.00
City$2,955.90
  • City Park Impact Fee (Deltona)
    City of Deltona
    City of Deltona Park Impact Fee — $1,539.90 per single-family dwelling unit. A phased citywide impact-fee increase adopted June 2026 takes effect October 1, 2026.
    $1,539.90
  • City Transportation Impact Fee (Deltona)
    City of Deltona
    City of Deltona Transportation Impact Fee — $1,044 per single-family dwelling unit. A phased citywide impact-fee increase adopted June 2026 takes effect October 1, 2026.
    $1,044.00
  • City Fire/Rescue Impact Fee (Deltona)
    City of Deltona
    City of Deltona Fire/Rescue Impact Fee — $123 per 1,000 sq ft of residential floor area; $246 for the canonical 2,000 sq ft single-family home. A phased citywide impact-fee increase adopted June 2026 takes effect October 1, 2026.
    $246.00
  • City Law Enforcement Impact Fee (Deltona)
    City of Deltona
    City of Deltona Law Enforcement Impact Fee — $63 per 1,000 sq ft of residential floor area; $126 for the canonical 2,000 sq ft single-family home. A phased citywide impact-fee increase adopted June 2026 takes effect October 1, 2026.
    $126.00
County$13,200.67
  • County School Impact Fee (Volusia County)
    Volusia County
    Volusia County School impact fee — 2026 Residential schedule, effective June 3, 2026. $7,022.70 per single-family unit, flat across all home sizes. Applies countywide.
    $7,022.70
  • County Thoroughfare Road Impact Fee (Volusia County)
    SF Detached, 1,701-2,200 sq ft
    Volusia County
    Volusia County Thoroughfare (Transportation) Road impact fee — 2026 Residential schedule, effective June 3, 2026. Detached single-family, tiered by heated floor area: ≤1,200 sq ft $4,864; 1,201–1,700 $5,097; 1,701–2,200 $5,464; 2,201–3,000 $5,835; over 3,000 $6,215. Amount shown is the 1,701–2,200 sq ft tier. Applies countywide (unincorporated + every city).
    $5,464.00
  • County Cultural/Rec District Park Impact Fee (Volusia County)
    SF Detached, 1,701-2,200 sq ft
    Volusia County
    Volusia County Cultural/Recreational District/Coastal Park impact fee — 2026 Residential schedule, effective June 3, 2026. Detached single-family, tiered by heated floor area: ≤1,200 sq ft $527; 1,201–1,700 $606; 1,701–2,200 $644; 2,201–3,000 $675; over 3,000 $742. Amount shown is the 1,701–2,200 sq ft tier. Applies countywide (unincorporated + every city).
    $644.00
  • County EMS Impact Fee (Volusia County)
    SF Detached, 1,701-2,200 sq ft
    Volusia County
    Volusia County EMS impact fee — 2026 Residential schedule, effective June 3, 2026. Detached single-family, tiered by heated floor area: ≤1,200 sq ft $57.41; 1,201–1,700 $65.93; 1,701–2,200 $69.97; 2,201–3,000 $73.55; over 3,000 $80.73. Amount shown is the 1,701–2,200 sq ft tier. Applies countywide (unincorporated + every city).
    $69.97
Total (Deltona): $25,216.57
Sources last checked Official fee schedules:City of Deltona Volusia County

Deltona: Multifamily Impact Fees

A new multifamily unit in Deltona pays $15,954.86 per unit in impact fees (rates sourced August 19, 2026). Of that, Volusia County-levied fees account for $6,802.36 and municipal or utility fees for $9,152.50.

The largest line items are Sewer Connection Fee (Deltona) ($4,580.80), County School Impact Fee (Volusia County) ($3,728.95) and Water Connection Fee (Deltona) ($2,667.20).

Some fees are tiered by unit size or building type; amounts reflect the representative tier noted in the schedule below.

View the Full Deltona Impact Fee Schedule
Water$2,667.20
  • Water Connection Fee (Deltona)
    City of Deltona
    Deltona Water charges its water connection fee per equivalent residential connection: a $3,220 capital charge plus a $114 capital financing recovery fee, a total of $3,334 per ERC. The city's code counts each multifamily dwelling unit as 0.8 ERC, so the charge is $2,667.20 per apartment unit. The amounts took effect February 1, 2026 and are held at that level through the 2029-30 fiscal year. Meter installation and tapping costs are billed separately.
    $2,667.20
Sewer$4,580.80
  • Sewer Connection Fee (Deltona)
    City of Deltona
    Deltona Water charges its sewer connection fee per equivalent residential connection: a $5,240 capital charge plus a $486 capital financing recovery fee, a total of $5,726 per ERC. The city's code counts each multifamily dwelling unit as 0.8 ERC, so the charge is $4,580.80 per apartment unit. The amounts took effect February 1, 2026 and are held at that level through the 2029-30 fiscal year.
    $4,580.80
City$1,904.50
  • City Transportation Impact Fee (Deltona)
    City of Deltona
    City of Deltona Transportation Impact Fee — $888 per multifamily dwelling unit. A phased citywide impact-fee increase adopted June 2026 takes effect October 1, 2026.
    $888.00
  • City Park Impact Fee (Deltona)
    City of Deltona
    City of Deltona Park Impact Fee — $830.50 per multifamily dwelling unit. A phased citywide impact-fee increase adopted June 2026 takes effect October 1, 2026.
    $830.50
  • City Fire/Rescue Impact Fee (Deltona)
    City of Deltona
    City of Deltona Fire/Rescue Impact Fee — $123 per 1,000 sq ft of residential floor area ($123 for the canonical 1,000 sq ft multifamily unit). A phased citywide impact-fee increase adopted June 2026 takes effect October 1, 2026.
    $123.00
  • City Law Enforcement Impact Fee (Deltona)
    City of Deltona
    City of Deltona Law Enforcement Impact Fee — $63 per 1,000 sq ft of residential floor area ($63 for the canonical 1,000 sq ft multifamily unit). A phased citywide impact-fee increase adopted June 2026 takes effect October 1, 2026.
    $63.00
County$6,802.36
  • County School Impact Fee (Volusia County)
    High-Rise
    Volusia County
    Volusia County School impact fee, multifamily — 2026 Residential schedule, effective June 3, 2026. $3,728.95 per unit, flat across duplex, low-rise and high-rise. Applies countywide.
    $3,728.95
  • County Thoroughfare Road Impact Fee (Volusia County)
    High-Rise
    Volusia County
    Volusia County Thoroughfare (Transportation) Road impact fee, multifamily — 2026 Residential schedule, effective June 3, 2026. Per unit by building type: duplex $4,733; low-rise (3 stories or less) $3,700; high-rise (4+ stories) $2,489. Amount shown is high-rise (the canonical 4-story unit). Mobile home/RV park $1,903 not modeled. Applies countywide.
    $2,489.00
  • County District/Coastal Park Impact Fee
    1,200 sq ft or less
    Volusia County
    Volusia County Cultural/Recreational District/Coastal Park impact fee, multifamily — 2026 Residential schedule, effective June 3, 2026. Charged per unit by heated floor area using the residential tier table; amount shown is the ≤1,200 sq ft tier (canonical ~1,000 sq ft unit), rising with unit size. Applies countywide (unincorporated + every city).
    $527.00
  • County EMS Impact Fee
    1,200 sq ft or less
    Volusia County
    Volusia County EMS impact fee, multifamily — 2026 Residential schedule, effective June 3, 2026. Charged per unit by heated floor area using the residential tier table; amount shown is the ≤1,200 sq ft tier (canonical ~1,000 sq ft unit), rising with unit size. Applies countywide (unincorporated + every city).
    $57.41
Total (Deltona): $15,954.86
Sources last checked Official fee schedules:City of Deltona Volusia County

Deltona: Commercial Impact Fees

Commercial development in Deltona pays $8.70 per square foot in impact fees (rates sourced August 19, 2026).

For a 50,000 sq ft building, that comes to at least $435,050.00. The calculator below adjusts to your exact square footage.

The largest line items are County Thoroughfare Road Impact Fee (Deltona, Commercial) ($6.32/sq ft), City Transportation Impact Fee (Deltona, Commercial) ($2.08/sq ft) and City Fire/Rescue Impact Fee (Deltona, Commercial) ($0.12/sq ft).

Water Capital Charge (Deltona Water & Wastewater Utility) and Sewer Capital Charge (Deltona Water & Wastewater Utility) are set by the utility and not published online. Contact the levying jurisdiction or utility to verify before budgeting; they are not included as dollar figures here.

View the Full Deltona Impact Fee Schedule
Water$0.00
Sewer$0.00
County$6.44/sq ft
Total (Deltona): $8.70/sq ft (≈ $435,050.00 at 50,000 sq ft)
Sources last checked Official fee schedules:City of Deltona (Deltona Water) City of Deltona Volusia County
Fees flagged "Requires confirmation" have no confirmed published amount. Confirm them with the jurisdiction or utility before budgeting.

Where in Volusia County Are You Building?

Each jurisdiction applies its own fee schedule. Pick yours. Totals shown are for a 50,000 sq ft building, including one-time water/sewer fees (assuming a 1-inch meter). = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.

Deltona: Industrial Impact Fees

Industrial development in Deltona pays $3.93 per square foot in impact fees (rates sourced August 19, 2026).

For a 50,000 sq ft building, that comes to at least $196,700.00. The calculator below adjusts to your exact square footage.

The largest line items are County Thoroughfare Road Impact Fee (Deltona, Industrial) ($2.42/sq ft), City Transportation Impact Fee (Deltona, Industrial) ($1.31/sq ft) and City Fire/Rescue Impact Fee (Deltona, Industrial) ($0.12/sq ft).

Water Capital Charge (Deltona Water & Wastewater Utility) and Sewer Capital Charge (Deltona Water & Wastewater Utility) are set by the utility and not published online. Contact the levying jurisdiction or utility to verify before budgeting; they are not included as dollar figures here.

View the Full Deltona Impact Fee Schedule
Water$0.00
Sewer$0.00
County$2.44/sq ft
Total (Deltona): $3.93/sq ft (≈ $196,700.00 at 50,000 sq ft)
Sources last checked Official fee schedules:City of Deltona (Deltona Water) City of Deltona Volusia County
Fees flagged "Requires confirmation" have no confirmed published amount. Confirm them with the jurisdiction or utility before budgeting.

Where in Volusia County Are You Building?

Each jurisdiction applies its own fee schedule. Pick yours. Totals shown are for a 50,000 sq ft building, including one-time water/sewer fees (assuming a 1-inch meter). = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.

Deltona: Office Impact Fees

Office development in Deltona pays $7.26 per square foot in impact fees (rates sourced August 19, 2026).

For a 25,000 sq ft building, that comes to at least $181,600.00. The calculator below adjusts to your exact square footage.

The largest line items are County Thoroughfare Road Impact Fee (Deltona, Office) ($5.40/sq ft), City Transportation Impact Fee (Deltona, Office) ($1.64/sq ft) and City Fire/Rescue Impact Fee (Deltona, Office) ($0.12/sq ft).

Water Capital Charge (Deltona Water & Wastewater Utility) and Sewer Capital Charge (Deltona Water & Wastewater Utility) are set by the utility and not published online. Contact the levying jurisdiction or utility to verify before budgeting; they are not included as dollar figures here.

View the Full Deltona Impact Fee Schedule
Water$0.00
Sewer$0.00
County$5.44/sq ft
Total (Deltona): $7.26/sq ft (≈ $181,600.00 at 25,000 sq ft)
Sources last checked Official fee schedules:City of Deltona (Deltona Water) City of Deltona Volusia County
Fees flagged "Requires confirmation" have no confirmed published amount. Confirm them with the jurisdiction or utility before budgeting.

Where in Volusia County Are You Building?

Each jurisdiction applies its own fee schedule. Pick yours. Totals shown are for a 25,000 sq ft building, including one-time water/sewer fees (assuming a 1-inch meter). = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.

Deltona Impact Fee Calculator

Estimate impact fees for your project. Set to single-family. Drop a pin or search an address for site-specific fees.

Location

Select a location to begin

Once you select an address or drop a pin, we'll identify the responsible city and county and generate a fee breakdown.

Water & Sewer
Transportation
Parks
Schools
Fire & Police
General

Pending and Recent Changes

How Impact Fees Work in Florida

Florida impact fees are one-time charges on new development, governed by Section 163.31801, Florida Statutes (the Florida Impact Fee Act). The statute requires fees to be based on the most recent and localized data, spent on the infrastructure category they were collected for, and adopted by ordinance.

Since a 2021 amendment (Ch. 2021-63, Laws of Florida), the law also limits how fast fees can rise: increases up to 25% phase in over two years, increases of 25–50% phase in over four years, and increases above 50% are allowed only with a demonstrated extraordinary-circumstances study and at least a two-thirds vote of the governing body.

Counties and cities can both levy impact fees. Inside an incorporated city, a project typically pays the county's countywide fees plus any municipal fees the city has adopted, which is why totals differ between a city and the unincorporated county around it.

For a primer on how impact fees work, see our plain-English guide.

Summary current as of September 2026. This is an editorial summary, not legal advice; see the official statute text and our terms of use.

Deltona Impact Fee FAQs

What are the total impact fees for a single-family home in Deltona, Florida?

A new single-family home in Deltona pays $25,216.57 per unit in combined impact fees (rates sourced August 19, 2026).

How much are commercial impact fees in Deltona?

Commercial development in Deltona pays $8.70 per square foot in impact fees, at least $435,050.00 for a 50,000 sq ft building. 2 additional fees have no published standard amounts and are not included, so the full cost may be higher; verify before budgeting.

Does Deltona charge its own impact fees?

Yes. Deltona levies its own municipal impact or utility fees, and county-levied fees also apply inside city limits. The schedule on this page shows every fee that applies to development in Deltona, with the combined total.

Can Florida impact fees increase at any time?

No. Section 163.31801, Florida Statutes limits increases to 50% at most, phased in over two to four years, unless the local government makes extraordinary-circumstances findings and approves the increase by at least a two-thirds vote.

Fee amounts on this page are compiled from official published schedules and are provided for planning purposes only. Rates change, and project specifics (unit size, meter size, location within special districts) can alter what applies. Always verify current fees with the jurisdiction and utility before relying on them.

Compare unincorporated rates and every other city on the Volusia County impact fees page.