Edgewater Impact Fees by Project Type
Edgewater: Single-Family Impact Fees
A new single-family home in Edgewater pays $28,617.67 per unit in impact fees (rates sourced August 7, 2026). Of that, Volusia County-levied fees account for $13,200.67 and municipal or utility fees for $15,417.00.
The largest line items are County School Impact Fee (Volusia County) ($7,022.70), County Thoroughfare Road Impact Fee (Volusia County) ($5,464.00) and Sewer Impact Fee (City of Edgewater) ($4,685.00).
Some fees are tiered by unit size or building type; amounts reflect the representative tier noted in the schedule below.
View the Full Edgewater Impact Fee Schedule
- Water Impact Fee (City of Edgewater)$4,605.00City of EdgewaterThe City of Edgewater's water impact fee is $4,605 per ERU (equivalent residential unit), effective October 1, 2025. A single-family home is charged 1.0 ERU. A separate water connection (meter) fee also applies, ranging from $600 for a standard 3/4-inch meter to $3,800 for a 4-inch meter. Edgewater operates its own water utility.
- Reclaimed Water Connection Fee (City of Edgewater)$600.00City of EdgewaterThe City of Edgewater charges a reclaimed water connection fee of $600 per meter, effective October 1, 2025, where reclaimed (reuse) water service is available.
- Water Connection Fee (City of Edgewater)$600.003/4 inch meterCity of EdgewaterThe City of Edgewater's water connection (meter) fee is $600 for a standard 3/4-inch meter, effective October 1, 2025. Larger meters cost more (1-inch $725, 1.5-inch $1,000, 2-inch $1,575, 3-inch $2,050, 4-inch $3,800 - see other tiers). This is separate from and in addition to the $4,605 per ERU water impact fee.
- Sewer Impact Fee (City of Edgewater)$4,685.00City of EdgewaterThe City of Edgewater's sewer (wastewater) impact fee is $4,685 per ERU, effective October 1, 2025. A single-family home is charged 1.0 ERU. A separate sewer connection fee of $175 per ERU also applies. Edgewater operates its own wastewater utility.
- Sewer Connection Fee (City of Edgewater)$175.00City of EdgewaterThe City of Edgewater's sewer connection fee is $175 per ERU, effective October 1, 2025. This is separate from and in addition to the $4,685 per ERU sewer impact fee.
- Parks & Recreation$1,306.00City of EdgewaterThe City of Edgewater's parks and recreation impact fee is $1,306 per dwelling unit under the city's fiscal year 2026 impact fee schedule. These are City of Edgewater fees only; Volusia County impact fees are collected separately and may also apply.
- Fire Protection and EMS$1,019.00City of EdgewaterThe City of Edgewater's fire and rescue impact fee is $1,019 per dwelling unit under the city's fiscal year 2026 impact fee schedule. The city does not levy a separate emergency medical services impact fee. These are City of Edgewater fees only; Volusia County impact fees are collected separately and may also apply.
- General Government Buildings Impact Fee$833.00City of EdgewaterThe City of Edgewater's general government buildings impact fee is $833 per dwelling unit under the city's fiscal year 2026 impact fee schedule, effective October 1, 2025. The full residential impact fee package totals $3,912 per dwelling unit. These are City of Edgewater fees only; Volusia County impact fees are collected separately and may also apply.
- Police Impact Fee$408.00City of EdgewaterThe City of Edgewater's law enforcement (police) impact fee is $408 per dwelling unit under the city's fiscal year 2026 impact fee schedule. These are City of Edgewater fees only; Volusia County impact fees are collected separately and may also apply.
- Transportation$346.00City of EdgewaterThe City of Edgewater's multi-modal transportation impact fee is $346 per dwelling unit under the city's fiscal year 2026 impact fee schedule. The full residential impact fee package totals $3,912 per dwelling unit. These are City of Edgewater fees only; Volusia County impact fees are collected separately and may also apply.
- County School Impact Fee (Volusia County)$7,022.70Volusia CountyVolusia County School impact fee — 2026 Residential schedule, effective June 3, 2026. $7,022.70 per single-family unit, flat across all home sizes. Applies countywide.
- County Thoroughfare Road Impact Fee (Volusia County)$5,464.00SF Detached, 1,701-2,200 sq ftVolusia CountyVolusia County Thoroughfare (Transportation) Road impact fee — 2026 Residential schedule, effective June 3, 2026. Detached single-family, tiered by heated floor area: ≤1,200 sq ft $4,864; 1,201–1,700 $5,097; 1,701–2,200 $5,464; 2,201–3,000 $5,835; over 3,000 $6,215. Amount shown is the 1,701–2,200 sq ft tier. Applies countywide (unincorporated + every city).
- County Cultural/Rec District Park Impact Fee (Volusia County)$644.00SF Detached, 1,701-2,200 sq ftVolusia CountyVolusia County Cultural/Recreational District/Coastal Park impact fee — 2026 Residential schedule, effective June 3, 2026. Detached single-family, tiered by heated floor area: ≤1,200 sq ft $527; 1,201–1,700 $606; 1,701–2,200 $644; 2,201–3,000 $675; over 3,000 $742. Amount shown is the 1,701–2,200 sq ft tier. Applies countywide (unincorporated + every city).
- County EMS Impact Fee (Volusia County)$69.97SF Detached, 1,701-2,200 sq ftVolusia CountyVolusia County EMS impact fee — 2026 Residential schedule, effective June 3, 2026. Detached single-family, tiered by heated floor area: ≤1,200 sq ft $57.41; 1,201–1,700 $65.93; 1,701–2,200 $69.97; 2,201–3,000 $73.55; over 3,000 $80.73. Amount shown is the 1,701–2,200 sq ft tier. Applies countywide (unincorporated + every city).
- Stormwater Impact Fee (City of Edgewater)$840.00City of EdgewaterThe City of Edgewater charges a one-time stormwater impact fee of $840 per equivalent dwelling unit (EDU), effective November 17, 2025. A single-family home is one EDU.
Where in Volusia County Are You Building?
Each jurisdiction applies its own fee schedule. Pick yours.
Edgewater: Multifamily Impact Fees
A new multifamily unit in Edgewater pays $22,219.36 per unit in impact fees (rates sourced August 7, 2026). Of that, Volusia County-levied fees account for $6,802.36 and municipal or utility fees for $15,417.00.
The largest line items are Sewer Impact Fee (City of Edgewater, MF) ($4,685.00), Water Impact Fee (City of Edgewater, MF) ($4,605.00) and County School Impact Fee (Volusia County) ($3,728.95).
Some fees are tiered by unit size or building type; amounts reflect the representative tier noted in the schedule below.
View the Full Edgewater Impact Fee Schedule
- Water Impact Fee (City of Edgewater, MF)$4,605.00City of EdgewaterThe City of Edgewater's water impact fee is $4,605 per ERU, effective October 1, 2025. The city assesses residential water impact fees per dwelling unit at 1.0 ERU per unit, so each multifamily unit is charged $4,605. A separate water connection (meter) fee also applies. Edgewater operates its own water utility.
- Reclaimed Water Connection Fee (City of Edgewater, MF)$600.00City of EdgewaterThe City of Edgewater charges a reclaimed water connection fee of $600 per meter, effective October 1, 2025, where reclaimed (reuse) water service is available.
- Water Connection Fee (City of Edgewater, MF)$600.003/4 inch meterCity of EdgewaterThe City of Edgewater's water connection (meter) fee starts at $600 for a 3/4-inch meter, effective October 1, 2025. A multifamily building's master meter is sized to demand and costs more at larger sizes (1-inch $725 up to 4-inch $3,800 - see other tiers). This is separate from and in addition to the $4,605 per ERU water impact fee.
- Sewer Impact Fee (City of Edgewater, MF)$4,685.00City of EdgewaterThe City of Edgewater's sewer (wastewater) impact fee is $4,685 per ERU, effective October 1, 2025. The city assesses residential sewer impact fees per dwelling unit at 1.0 ERU per unit, so each multifamily unit is charged $4,685. A separate sewer connection fee of $175 per ERU also applies. Edgewater operates its own wastewater utility.
- Sewer Connection Fee (City of Edgewater, MF)$175.00City of EdgewaterThe City of Edgewater's sewer connection fee is $175 per ERU, effective October 1, 2025 (one ERU per unit). This is separate from and in addition to the $4,685 per ERU sewer impact fee.
- Parks & Recreation Impact Fee (MF)$1,306.00City of EdgewaterThe City of Edgewater's parks and recreation impact fee is $1,306 per dwelling unit, effective October 1, 2025, and applies equally to single-family and multifamily units. The full residential impact fee package totals $3,912 per dwelling unit. These are City of Edgewater fees only; Volusia County impact fees are collected separately and may also apply.
- Fire and Rescue Impact Fee (MF)$1,019.00City of EdgewaterThe City of Edgewater's fire and rescue impact fee is $1,019 per dwelling unit, effective October 1, 2025, and applies equally to single-family and multifamily units (the city schedule lists one combined residential rate). The full residential impact fee package totals $3,912 per dwelling unit. These are City of Edgewater fees only; Volusia County impact fees are collected separately and may also apply.
- General Government Buildings Impact Fee (MF)$833.00City of EdgewaterThe City of Edgewater's general government buildings impact fee is $833 per dwelling unit, effective October 1, 2025, and applies equally to single-family and multifamily units. The full residential impact fee package totals $3,912 per dwelling unit. These are City of Edgewater fees only; Volusia County impact fees are collected separately and may also apply.
- Police Impact Fee (MF)$408.00City of EdgewaterThe City of Edgewater's law enforcement (police) impact fee is $408 per dwelling unit, effective October 1, 2025, and applies equally to single-family and multifamily units. The full residential impact fee package totals $3,912 per dwelling unit. These are City of Edgewater fees only; Volusia County impact fees are collected separately and may also apply.
- Multi-Modal Transportation Impact Fee (MF)$346.00City of EdgewaterThe City of Edgewater's multi-modal transportation impact fee is $346 per dwelling unit, effective October 1, 2025, and applies equally to single-family and multifamily units. The full residential impact fee package totals $3,912 per dwelling unit. These are City of Edgewater fees only; Volusia County impact fees are collected separately and may also apply.
- County School Impact Fee (Volusia County)$3,728.95High-RiseVolusia CountyVolusia County School impact fee, multifamily — 2026 Residential schedule, effective June 3, 2026. $3,728.95 per unit, flat across duplex, low-rise and high-rise. Applies countywide.
- County Thoroughfare Road Impact Fee (Volusia County)$2,489.00High-RiseVolusia CountyVolusia County Thoroughfare (Transportation) Road impact fee, multifamily — 2026 Residential schedule, effective June 3, 2026. Per unit by building type: duplex $4,733; low-rise (3 stories or less) $3,700; high-rise (4+ stories) $2,489. Amount shown is high-rise (the canonical 4-story unit). Mobile home/RV park $1,903 not modeled. Applies countywide.
- County District/Coastal Park Impact Fee$527.001,200 sq ft or lessVolusia CountyVolusia County Cultural/Recreational District/Coastal Park impact fee, multifamily — 2026 Residential schedule, effective June 3, 2026. Charged per unit by heated floor area using the residential tier table; amount shown is the ≤1,200 sq ft tier (canonical ~1,000 sq ft unit), rising with unit size. Applies countywide (unincorporated + every city).
- County EMS Impact Fee$57.411,200 sq ft or lessVolusia CountyVolusia County EMS impact fee, multifamily — 2026 Residential schedule, effective June 3, 2026. Charged per unit by heated floor area using the residential tier table; amount shown is the ≤1,200 sq ft tier (canonical ~1,000 sq ft unit), rising with unit size. Applies countywide (unincorporated + every city).
- Stormwater Impact Fee (City of Edgewater, MF)$840.00City of EdgewaterThe City of Edgewater charges a one-time stormwater impact fee of $840 per equivalent dwelling unit (EDU), effective November 17, 2025. Each multifamily dwelling unit is one EDU.
Where in Volusia County Are You Building?
Each jurisdiction applies its own fee schedule. Pick yours.
Edgewater: Commercial Impact Fees
Commercial development in Edgewater pays $6.44 per square foot in impact fees, plus $3,839.12 in one-time water and sewer connection fees (rates sourced August 7, 2026).
For a 50,000 sq ft building, that comes to about $325,839.12. The calculator below adjusts to your exact square footage.
The largest line items are County Thoroughfare Road Impact Fee (Edgewater, Commercial) ($6.32/sq ft) and County EMS Impact Fee (Edgewater, Commercial) ($0.12/sq ft).
Water Impact Fee (City of Edgewater) — 1 ERU min and Sewer Impact Fee (City of Edgewater) — 1 ERU min are shown at the last published amount but have not been confirmed with the jurisdiction; they are included in the totals here. Verify before budgeting.
View the Full Edgewater Impact Fee Schedule
- Water Impact Fee (City of Edgewater) — 1 ERU min$1,612.43 one-timeRequires confirmationCity of Edgewater
- Sewer Impact Fee (City of Edgewater) — 1 ERU min$2,226.69 one-timeRequires confirmationCity of Edgewater
- City Impact Fee (Edgewater, Commercial)$0.00City of Edgewater
- $6.32/sq ft
- County EMS Impact Fee (Edgewater, Commercial)$0.12/sq ftVolusia County
Where in Volusia County Are You Building?
Each jurisdiction applies its own fee schedule. Pick yours. Totals shown are for a 50,000 sq ft building, including one-time water/sewer fees (assuming a 1-inch meter). = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.
Edgewater: Industrial Impact Fees
Industrial development in Edgewater pays $2.44 per square foot in impact fees, plus $3,839.12 in one-time water and sewer connection fees (rates sourced August 7, 2026).
For a 50,000 sq ft building, that comes to about $125,839.12. The calculator below adjusts to your exact square footage.
The largest line items are County Thoroughfare Road Impact Fee (Edgewater, Industrial) ($2.42/sq ft) and County EMS Impact Fee (Edgewater, Industrial) ($0.02/sq ft).
Water Impact Fee (City of Edgewater) — 1 ERU min and Sewer Impact Fee (City of Edgewater) — 1 ERU min are shown at the last published amount but have not been confirmed with the jurisdiction; they are included in the totals here. Verify before budgeting.
View the Full Edgewater Impact Fee Schedule
- Water Impact Fee (City of Edgewater) — 1 ERU min$1,612.43 one-timeRequires confirmationCity of Edgewater
- Sewer Impact Fee (City of Edgewater) — 1 ERU min$2,226.69 one-timeRequires confirmationCity of Edgewater
- City Impact Fee (Edgewater, Industrial)$0.00City of Edgewater
- $2.42/sq ft
- County EMS Impact Fee (Edgewater, Industrial)$0.02/sq ftVolusia County
Where in Volusia County Are You Building?
Each jurisdiction applies its own fee schedule. Pick yours. Totals shown are for a 50,000 sq ft building, including one-time water/sewer fees (assuming a 1-inch meter). = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.
Edgewater: Office Impact Fees
Office development in Edgewater pays $5.44 per square foot in impact fees, plus $3,839.12 in one-time water and sewer connection fees (rates sourced August 7, 2026).
For a 25,000 sq ft building, that comes to about $139,839.12. The calculator below adjusts to your exact square footage.
The largest line items are County Thoroughfare Road Impact Fee (Edgewater, Office) ($5.40/sq ft) and County EMS Impact Fee (Edgewater, Office) ($0.04/sq ft).
Water Impact Fee (City of Edgewater) — 1 ERU min and Sewer Impact Fee (City of Edgewater) — 1 ERU min are shown at the last published amount but have not been confirmed with the jurisdiction; they are included in the totals here. Verify before budgeting.
View the Full Edgewater Impact Fee Schedule
- Water Impact Fee (City of Edgewater) — 1 ERU min$1,612.43 one-timeRequires confirmationCity of Edgewater
- Sewer Impact Fee (City of Edgewater) — 1 ERU min$2,226.69 one-timeRequires confirmationCity of Edgewater
- City Impact Fee (Edgewater, Office)$0.00City of Edgewater
- County Thoroughfare Road Impact Fee (Edgewater, Office)$5.40/sq ftVolusia County
- County EMS Impact Fee (Edgewater, Office)$0.04/sq ftVolusia County
Where in Volusia County Are You Building?
Each jurisdiction applies its own fee schedule. Pick yours. Totals shown are for a 25,000 sq ft building, including one-time water/sewer fees (assuming a 1-inch meter). = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.
Edgewater Impact Fee Calculator
Estimate impact fees for your project. Set to single-family. Drop a pin or search an address for site-specific fees.
Location
Select a location to begin
Once you select an address or drop a pin, we'll identify the responsible city and county and generate a fee breakdown.
How Impact Fees Work in Florida
Florida impact fees are one-time charges on new development, governed by Section 163.31801, Florida Statutes (the Florida Impact Fee Act). The statute requires fees to be based on the most recent and localized data, spent on the infrastructure category they were collected for, and adopted by ordinance.
Since a 2021 amendment (Ch. 2021-63, Laws of Florida), the law also limits how fast fees can rise: increases up to 25% phase in over two years, increases of 25–50% phase in over four years, and increases above 50% are allowed only with a demonstrated extraordinary-circumstances study and at least a two-thirds vote of the governing body.
Counties and cities can both levy impact fees. Inside an incorporated city, a project typically pays the county's countywide fees plus any municipal fees the city has adopted, which is why totals differ between a city and the unincorporated county around it.
Brush up on impact fee basics before you budget your next project.
Summary current as of September 2026. This is an editorial summary, not legal advice; see the official statute text and our terms of use.
Edgewater Impact Fee FAQs
What are the total impact fees for a single-family home in Edgewater, Florida?
A new single-family home in Edgewater pays $28,617.67 per unit in combined impact fees (rates sourced August 7, 2026).
How much are commercial impact fees in Edgewater?
Commercial development in Edgewater pays $6.44 per square foot in impact fees, plus $3,839.12 in one-time water and sewer connection fees, about $325,839.12 for a 50,000 sq ft building. This figure includes amounts that have not been confirmed with the jurisdiction; verify before budgeting.
Does Edgewater charge its own impact fees?
Yes. Edgewater levies its own municipal impact or utility fees, and county-levied fees also apply inside city limits. The schedule on this page shows every fee that applies to development in Edgewater, with the combined total.
Can Florida impact fees increase at any time?
No. Section 163.31801, Florida Statutes limits increases to 50% at most, phased in over two to four years, unless the local government makes extraordinary-circumstances findings and approves the increase by at least a two-thirds vote.
Fee amounts on this page are compiled from official published schedules and are provided for planning purposes only. Rates change, and project specifics (unit size, meter size, location within special districts) can alter what applies. Always verify current fees with the jurisdiction and utility before relying on them.
Compare unincorporated rates and every other city on the Volusia County impact fees page.