Von Ormy Impact Fees by Project Type
Von Ormy: Single-Family Impact Fees
A new single-family home in Von Ormy pays at least $10,350.00 per unit in impact fees (rates sourced November 16, 2026). Every line item is levied at the municipal or utility level.
The largest line items are Water Service Charges — Atascosa Rural WSC, short service ($100 membership + $2,000 connection + $7,000 water acquisition + $1,250 capital recovery) ($10,350.00).
Sewer Connection Fee (Von Ormy) is set by the utility and not published online. City Impact Fees (Von Ormy) is set by the city and has no published standard rate. Contact the levying jurisdiction or utility to verify before budgeting; they are not included as dollar figures here.
Some fees are tiered by unit size or building type; amounts reflect the representative tier noted in the schedule below.
View the Full Von Ormy Impact Fee Schedule
- Water Service Charges — Atascosa Rural WSC, short service ($100 membership + $2,000 connection + $7,000 water acquisition + $1,250 capital recovery)$10,350.00Atascosa Rural Water Supply CorporationAtascosa Rural Water Supply Corporation serves Von Ormy. New residential service costs $10,350 (membership $100, connection $2,000, water acquisition $7,000, capital recovery $1,250); a long service needing a road bore adds $1,000.
- Sewer Connection Fee (Von Ormy)Requires confirmationPrivate septic (OSSF)Von Ormy has historically had no public sewer; development uses on-site septic systems. Sewer mains are being extended along I-35, where SAWS fees may apply to new connections.
- City Impact Fees (Von Ormy)Requires confirmationCity of Von OrmyNo municipal impact fee or parkland dedication fee-in-lieu. Water is provided by Atascosa Rural Water Supply Corporation.
- County Impact Fees (Bexar County)$0.00Bexar CountyTexas counties cannot charge impact fees on new development except a storm water and drainage fee in a county of 3.3 million or more people or one bordering such a county; Bexar County does not qualify and levies none.
Where in Bexar County Are You Building?
Each jurisdiction applies its own fee schedule. Pick yours. = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.
Von Ormy: Multifamily Impact Fees
A new multifamily unit in Von Ormy pays at least $10,350.00 per unit in impact fees (rates sourced November 16, 2026). Every line item is levied at the municipal or utility level.
The largest line items are Water Service Charges (MF) — Atascosa Rural WSC, short service ($100 membership + $2,000 connection + $7,000 water acquisition + $1,250 capital recovery) ($10,350.00).
Sewer Connection Fee (Von Ormy, MF) is set by the utility and not published online. City Impact Fees (Von Ormy, MF) is set by the city and has no published standard rate. Contact the levying jurisdiction or utility to verify before budgeting; they are not included as dollar figures here.
Some fees are tiered by unit size or building type; amounts reflect the representative tier noted in the schedule below.
View the Full Von Ormy Impact Fee Schedule
- Water Service Charges (MF) — Atascosa Rural WSC, short service ($100 membership + $2,000 connection + $7,000 water acquisition + $1,250 capital recovery)$10,350.00Atascosa Rural Water Supply CorporationAtascosa Rural Water Supply Corporation serves Von Ormy; each meter may serve only one dwelling, so each apartment unit pays the full $10,350 new service charge.
- Sewer Connection Fee (Von Ormy, MF)Requires confirmationPrivate septic (OSSF)Von Ormy has historically had no public sewer; development uses on-site septic systems. Sewer mains are being extended along I-35, where SAWS fees may apply to new connections.
- City Impact Fees (Von Ormy, MF)Requires confirmationCity of Von OrmyNo municipal impact fee or parkland dedication fee-in-lieu. Water is provided by Atascosa Rural Water Supply Corporation.
- County Impact Fees (Bexar County, MF)$0.00Bexar CountyTexas counties cannot charge impact fees on new development except a storm water and drainage fee in a county of 3.3 million or more people or one bordering such a county; Bexar County does not qualify and levies none.
Where in Bexar County Are You Building?
Each jurisdiction applies its own fee schedule. Pick yours. = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.
Von Ormy: Commercial Impact Fees
Commercial development in Von Ormy pays no per-square-foot impact fees, but owes $11,150.00 in one-time water and sewer connection fees (rates sourced November 16, 2026).
For a 50,000 sq ft building, that comes to at least $11,150.00. The calculator below adjusts to your exact square footage.
The largest line items are Water Connection Fee — Atascosa Rural WSC, 1" ($11,150.00 one-time).
Water and sewer connection fees assume a 1-inch meter; larger services pay more. See the meter-size tiers in the source schedules.
Sewer Connection Fee (City of Von Ormy) is set by the utility and not published online. City Impact Fee (City of Von Ormy, Commercial) is set by the city and has no published standard rate. Contact the levying jurisdiction or utility to verify before budgeting; they are not included as dollar figures here.
View the Full Von Ormy Impact Fee Schedule
- Water Connection Fee — Atascosa Rural WSC, 1"$11,150.00 one-timeAtascosa Rural Water Supply CorporationAtascosa Rural Water Supply Corporation holds the water service certificate for all of Von Ormy; SAWS also holds a certificate over part of the city. Atascosa Rural WSC's all-in price for a new commercial service on an existing line, 1 inch meter, short service. A long service (road bore) adds the WSC's contractor cost.
- Sewer Connection Fee (City of Von Ormy)Requires confirmationCity of Von OrmyVon Ormy has no public sewer system today; development uses on-site septic systems. The city has a sewer project in planning.
- City Impact Fee (City of Von Ormy, Commercial)Requires confirmationCity of Von OrmyVon Ormy has no published city impact fee on nonresidential development.
- County Impact Fee (Bexar County, Commercial)$0.00Bexar CountyBexar County does not charge impact fees on nonresidential development.
Where in Bexar County Are You Building?
Each jurisdiction applies its own fee schedule. Pick yours. Totals shown are for a 50,000 sq ft building, including water/sewer fees (one-time connection fees assume a 1-inch meter). * = one-time water/sewer connection charges only; no per-sq-ft impact fee schedule sourced for that jurisdiction. = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.
Von Ormy: Industrial Impact Fees
Industrial development in Von Ormy pays no per-square-foot impact fees, but owes $11,150.00 in one-time water and sewer connection fees (rates sourced November 16, 2026).
For a 50,000 sq ft building, that comes to at least $11,150.00. The calculator below adjusts to your exact square footage.
The largest line items are Water Connection Fee — Atascosa Rural WSC, 1" ($11,150.00 one-time).
Water and sewer connection fees assume a 1-inch meter; larger services pay more. See the meter-size tiers in the source schedules.
Sewer Connection Fee (City of Von Ormy) is set by the utility and not published online. City Impact Fee (City of Von Ormy, Industrial) is set by the city and has no published standard rate. Contact the levying jurisdiction or utility to verify before budgeting; they are not included as dollar figures here.
View the Full Von Ormy Impact Fee Schedule
- Water Connection Fee — Atascosa Rural WSC, 1"$11,150.00 one-timeAtascosa Rural Water Supply CorporationAtascosa Rural Water Supply Corporation holds the water service certificate for all of Von Ormy; SAWS also holds a certificate over part of the city. Atascosa Rural WSC's all-in price for a new commercial service on an existing line, 1 inch meter, short service. A long service (road bore) adds the WSC's contractor cost.
- Sewer Connection Fee (City of Von Ormy)Requires confirmationCity of Von OrmyVon Ormy has no public sewer system today; development uses on-site septic systems. The city has a sewer project in planning.
- City Impact Fee (City of Von Ormy, Industrial)Requires confirmationCity of Von OrmyVon Ormy has no published city impact fee on nonresidential development.
- County Impact Fee (Bexar County, Industrial)$0.00Bexar CountyBexar County does not charge impact fees on nonresidential development.
Where in Bexar County Are You Building?
Each jurisdiction applies its own fee schedule. Pick yours. Totals shown are for a 50,000 sq ft building, including water/sewer fees (one-time connection fees assume a 1-inch meter). * = one-time water/sewer connection charges only; no per-sq-ft impact fee schedule sourced for that jurisdiction. = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.
Von Ormy: Office Impact Fees
Office development in Von Ormy pays no per-square-foot impact fees, but owes $11,150.00 in one-time water and sewer connection fees (rates sourced November 16, 2026).
For a 25,000 sq ft building, that comes to at least $11,150.00. The calculator below adjusts to your exact square footage.
The largest line items are Water Connection Fee — Atascosa Rural WSC, 1" ($11,150.00 one-time).
Water and sewer connection fees assume a 1-inch meter; larger services pay more. See the meter-size tiers in the source schedules.
Sewer Connection Fee (City of Von Ormy) is set by the utility and not published online. City Impact Fee (City of Von Ormy, Office) is set by the city and has no published standard rate. Contact the levying jurisdiction or utility to verify before budgeting; they are not included as dollar figures here.
View the Full Von Ormy Impact Fee Schedule
- Water Connection Fee — Atascosa Rural WSC, 1"$11,150.00 one-timeAtascosa Rural Water Supply CorporationAtascosa Rural Water Supply Corporation holds the water service certificate for all of Von Ormy; SAWS also holds a certificate over part of the city. Atascosa Rural WSC's all-in price for a new commercial service on an existing line, 1 inch meter, short service. A long service (road bore) adds the WSC's contractor cost.
- Sewer Connection Fee (City of Von Ormy)Requires confirmationCity of Von OrmyVon Ormy has no public sewer system today; development uses on-site septic systems. The city has a sewer project in planning.
- City Impact Fee (City of Von Ormy, Office)Requires confirmationCity of Von OrmyVon Ormy has no published city impact fee on nonresidential development.
- County Impact Fee (Bexar County, Office)$0.00Bexar CountyBexar County does not charge impact fees on nonresidential development.
Where in Bexar County Are You Building?
Each jurisdiction applies its own fee schedule. Pick yours. Totals shown are for a 25,000 sq ft building, including water/sewer fees (one-time connection fees assume a 1-inch meter). * = one-time water/sewer connection charges only; no per-sq-ft impact fee schedule sourced for that jurisdiction. = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.
Von Ormy Impact Fee Calculator
Estimate impact fees for your project. Set to single-family. Drop a pin or search an address for site-specific fees.
Location
Select a location to begin
Once you select an address or drop a pin, we'll identify the responsible city and county and generate a fee breakdown.
How Impact Fees Work in Texas
Texas cities, and certain special districts and authorities, assess impact fees under Chapter 395 of the Local Government Code and, with narrow exceptions, may charge one only by following it. A fee rests on adopted land use assumptions and a capital improvements plan, and imposing one takes the votes of two-thirds of the governing body's members.
Impact fees may fund only water supply, treatment and distribution; wastewater collection and treatment; storm water, drainage and flood control; and roadway facilities. Parks, schools, police and fire facilities are not on the chapter's list. The chapter does not treat park land dedication, or a payment in its place, as an impact fee, so a city can require that separately. The fee per service unit is capped at the plan's growth-related cost, less a required credit, divided by the projected service units. Counties generally cannot charge impact fees: the chapter gives that authority only to counties of 3.3 million or more people and the counties bordering them, and only for storm water, drainage and flood control. Since September 2025 a city also may not charge an impact fee where an office, retail or warehouse building at least five years old is converted to multifamily or mixed-use residential use (at least 65 percent of the building and of each usable floor), unless the land was already subject to an impact fee before the conversion's building permit was filed (Section 218.204).
For land platted after a fee is adopted, the fee is assessed no later than when the plat is recorded, which fixes the most that can be charged per service unit. Where water and wastewater capacity is available, it is generally collected when the building permit is issued, or when a water or wastewater meter connection is applied for on land outside city limits or where the entity charging the fee issues no building permits. A fee not spent as the chapter allows within 10 years of payment must generally be refunded with interest, and the land use assumptions and capital improvements plan are updated at least every five years unless the governing body formally determines that no update is needed.
A city may charge water, wastewater and drainage impact fees in its extraterritorial jurisdiction as well as inside its limits, but roadway impact fees stop at the city limits. Where a utility district or another provider supplies water or sewer instead of the city, its charges are separate from the city's, so the total can differ between a city, its neighbors and the unincorporated land around it.
Brush up on impact fee basics before you budget your next project.
Summary current as of November 2026. This is an editorial summary, not legal advice; see the official statute text and our terms of use.
Von Ormy Impact Fee FAQs
What are the total impact fees for a single-family home in Von Ormy, Texas?
A new single-family home in Von Ormy pays at least $10,350.00 per unit in combined impact fees (rates sourced November 16, 2026). 2 additional fees have no published standard amounts and are not included, so the full cost may be higher; verify before budgeting.
How much are commercial impact fees in Von Ormy?
Commercial development in Von Ormy pays no per-square-foot impact fees, but owes $11,150.00 in one-time water and sewer connection fees (assuming a 1-inch meter). 2 additional fees have no published standard amounts and are not included, so the full cost may be higher; verify before budgeting.
Does Von Ormy charge its own impact fees?
Yes. Von Ormy levies its own municipal impact or utility fees. Bexar County does not currently add county-level impact fees inside Von Ormy. The schedule on this page shows every fee that applies to development in Von Ormy.
Can a Texas impact fee increase at any time?
No. Under Section 395.0515 of the Local Government Code, added in 2025, a city or district may not increase an impact fee for three years from the later of the date the fee was adopted or last increased, although it may phase in collection up to the adopted maximum over no more than ten years. An increase also needs an independent financial audit and a public hearing on its results first (Section 395.059), and the measure approving it cannot be adopted as an emergency measure (Section 395.057). Once a fee is assessed on a tract, it cannot be raised for that tract unless the number of service units increases (Section 395.017). Charges set by a separate water or sewer provider may follow different rules.
Fee amounts on this page are compiled from official published schedules and are provided for planning purposes only. Rates change, and project specifics (unit size, meter size, location within special districts) can alter what applies. Always verify current fees with the jurisdiction and utility before relying on them.
Compare unincorporated rates and every other city on the Bexar County impact fees page.