Gaston Impact Fees by Project Type
Gaston: Single-Family Impact Fees
Gaston has no published impact fee amounts for a new single-family home (rates sourced November 13, 2026). The schedule below documents the status of each fee.
Water Tap Fee — Gaston Rural Community Water District and Sewer Tap-In Fee — Town of Gaston are set by the utility and not published online. Contact the levying jurisdiction or utility to verify before budgeting; they are not included as dollar figures here.
View the Full Gaston Impact Fee Schedule
- Water Tap Fee — Gaston Rural Community Water DistrictRequires confirmationGaston Rural Community Water DistrictWater in most of Gaston is provided by the Gaston Rural Community Water District, which publishes no tap fee. A small part of the town is served by the Joint Municipal Water and Sewer Commission instead.
- Sewer Tap-In Fee — Town of GastonRequires confirmationTown of GastonThe Town of Gaston runs its own sewer system. Its code requires a tap-in or cut-in fee for each new sewer connection but sets no amount, and no Town fee schedule publishes one.
- City Development Impact Fee (Town of Gaston - none levied)$0.00Town of GastonThe Town of Gaston levies no development impact fee.
- County Development Impact Fee (Lexington County - none levied)$0.00Lexington CountyLexington County levies no development impact fee. Its fee schedules effective July 1, 2026 list only plan review, permit and inspection charges.
Where in Lexington County Are You Building?
Each jurisdiction applies its own fee schedule. Pick yours. = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.
Gaston: Multifamily Impact Fees
Gaston has no published impact fee amounts for a new multifamily unit (rates sourced November 13, 2026). The schedule below documents the status of each fee.
Water Tap Fee (MF) — Gaston Rural Community Water District and Sewer Tap-In Fee (MF) — Town of Gaston are set by the utility and not published online. Contact the levying jurisdiction or utility to verify before budgeting; they are not included as dollar figures here.
View the Full Gaston Impact Fee Schedule
- Water Tap Fee (MF) — Gaston Rural Community Water DistrictRequires confirmationGaston Rural Community Water DistrictWater in most of Gaston is provided by the Gaston Rural Community Water District, which publishes no tap fee or per-apartment amount.
- Sewer Tap-In Fee (MF) — Town of GastonRequires confirmationTown of GastonThe Town of Gaston runs its own sewer system. Its code requires a tap-in or cut-in fee for each new sewer connection but sets no amount, and no per-apartment basis is published.
- City Development Impact Fee (Town of Gaston - none levied) (MF)$0.00Town of GastonThe Town of Gaston levies no development impact fee.
- County Development Impact Fee (Lexington County - none levied) (MF)$0.00Lexington CountyLexington County levies no development impact fee. Its fee schedules effective July 1, 2026 list only plan review, permit and inspection charges.
Where in Lexington County Are You Building?
Each jurisdiction applies its own fee schedule. Pick yours. = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.
Gaston: Commercial Impact Fees
Commercial development in Gaston pays no per-square-foot impact fees (rates sourced November 13, 2026).
Water and sewer connection fees assume a 1-inch meter; larger services pay more. See the meter-size tiers in the source schedules.
Water Tap Fee (Gaston) — Gaston Rural Community Water District and Sewer Tap-In Fee (Gaston) — Town of Gaston are set by the utility and not published online. Contact the levying jurisdiction or utility to verify before budgeting; they are not included as dollar figures here.
View the Full Gaston Impact Fee Schedule
- Water Tap Fee (Gaston) — Gaston Rural Community Water DistrictRequires confirmationGaston Rural Community Water DistrictWater in most of Gaston is provided by the Gaston Rural Community Water District, which publishes no tap fee. A small part of the town is served by the Joint Municipal Water and Sewer Commission instead.
- Sewer Tap-In Fee (Gaston) — Town of GastonRequires confirmationTown of GastonThe Town of Gaston runs its own sewer system. Its code requires a tap-in or cut-in fee for each new sewer connection but sets no amount, and no Town fee schedule publishes one. A small part of town is sewered by the Joint Municipal Water and Sewer Commission instead.
- City Development Impact Fee (Town of Gaston, Commercial)$0.00Town of GastonThe Town of Gaston does not levy a development impact fee.
- County Development Impact Fee (Lexington County, Commercial)$0.00Lexington CountyLexington County does not levy a development impact fee.
Where in Lexington County Are You Building?
Each jurisdiction applies its own fee schedule. Pick yours. Totals shown are for a 50,000 sq ft building, including one-time water/sewer fees (assuming a 1-inch meter). * = one-time water/sewer connection charges only; no per-sq-ft impact fee schedule sourced for that jurisdiction. = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.
Gaston: Industrial Impact Fees
Industrial development in Gaston pays no per-square-foot impact fees (rates sourced November 13, 2026).
Water and sewer connection fees assume a 1-inch meter; larger services pay more. See the meter-size tiers in the source schedules.
Water Tap Fee (Gaston) — Gaston Rural Community Water District and Sewer Tap-In Fee (Gaston) — Town of Gaston are set by the utility and not published online. Contact the levying jurisdiction or utility to verify before budgeting; they are not included as dollar figures here.
View the Full Gaston Impact Fee Schedule
- Water Tap Fee (Gaston) — Gaston Rural Community Water DistrictRequires confirmationGaston Rural Community Water DistrictWater in most of Gaston is provided by the Gaston Rural Community Water District, which publishes no tap fee. A small part of the town is served by the Joint Municipal Water and Sewer Commission instead.
- Sewer Tap-In Fee (Gaston) — Town of GastonRequires confirmationTown of GastonThe Town of Gaston runs its own sewer system. Its code requires a tap-in or cut-in fee for each new sewer connection but sets no amount, and no Town fee schedule publishes one. A small part of town is sewered by the Joint Municipal Water and Sewer Commission instead.
- City Development Impact Fee (Town of Gaston, Industrial)$0.00Town of GastonThe Town of Gaston does not levy a development impact fee.
- County Development Impact Fee (Lexington County, Industrial)$0.00Lexington CountyLexington County does not levy a development impact fee.
Where in Lexington County Are You Building?
Each jurisdiction applies its own fee schedule. Pick yours. Totals shown are for a 50,000 sq ft building, including one-time water/sewer fees (assuming a 1-inch meter). * = one-time water/sewer connection charges only; no per-sq-ft impact fee schedule sourced for that jurisdiction. = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.
Gaston: Office Impact Fees
Office development in Gaston pays no per-square-foot impact fees (rates sourced November 13, 2026).
Water and sewer connection fees assume a 1-inch meter; larger services pay more. See the meter-size tiers in the source schedules.
Water Tap Fee (Gaston) — Gaston Rural Community Water District and Sewer Tap-In Fee (Gaston) — Town of Gaston are set by the utility and not published online. Contact the levying jurisdiction or utility to verify before budgeting; they are not included as dollar figures here.
View the Full Gaston Impact Fee Schedule
- Water Tap Fee (Gaston) — Gaston Rural Community Water DistrictRequires confirmationGaston Rural Community Water DistrictWater in most of Gaston is provided by the Gaston Rural Community Water District, which publishes no tap fee. A small part of the town is served by the Joint Municipal Water and Sewer Commission instead.
- Sewer Tap-In Fee (Gaston) — Town of GastonRequires confirmationTown of GastonThe Town of Gaston runs its own sewer system. Its code requires a tap-in or cut-in fee for each new sewer connection but sets no amount, and no Town fee schedule publishes one. A small part of town is sewered by the Joint Municipal Water and Sewer Commission instead.
- City Development Impact Fee (Town of Gaston, Office)$0.00Town of GastonThe Town of Gaston does not levy a development impact fee.
- County Development Impact Fee (Lexington County, Office)$0.00Lexington CountyLexington County does not levy a development impact fee.
Where in Lexington County Are You Building?
Each jurisdiction applies its own fee schedule. Pick yours. Totals shown are for a 25,000 sq ft building, including one-time water/sewer fees (assuming a 1-inch meter). * = one-time water/sewer connection charges only; no per-sq-ft impact fee schedule sourced for that jurisdiction. = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.
Gaston Impact Fee Calculator
Estimate impact fees for your project. Set to single-family. Drop a pin or search an address for site-specific fees.
Location
Select a location to begin
Once you select an address or drop a pin, we'll identify the responsible city and county and generate a fee breakdown.
How Development Impact Fees Work in South Carolina
South Carolina counties and municipalities assess development impact fees under the Development Impact Fee Act (S.C. Code 6-1-910 et seq.). Only a government with a comprehensive plan (or a capital improvements plan that substantially complies with the Act) may impose one, by an ordinance approved by a positive majority, and before charging residential units it must report how the fee affects the availability of affordable housing.
Fees may fund only the public facilities the Act lists: water and wastewater, solid waste, roads and bridges, stormwater and flood control, public safety (law enforcement, fire, emergency medical and street lighting), capital equipment and vehicles of at least $100,000 a unit, parks, libraries and recreation, and, since 2016, K-12 public school facilities. A fee may not exceed the development's proportionate share of the cost, after credits for land, money or improvements the developer contributes and for other funding sources.
Fee revenue is kept in interest-bearing accounts by category and service area and spent only on that category in that area. A fee not spent within three years of the date it was scheduled to be spent, or paid on a building permit that is denied, is refunded with its share of interest. The fee is due no earlier than the building permit (or the development permit where no building permit is needed).
Water and sewer charges usually come from the utility that serves a parcel: the Act's definition of an impact fee excludes connection or hookup charges, and a water or wastewater provider meeting the conditions of 6-1-1080 sets its impact fees outside the Act. That is why totals differ between a city, its neighbors and the unincorporated county around it.
New to impact fees? Our plain-English guide explains what they cover, who pays them, and why they exist.
Summary current as of November 2026. This is an editorial summary, not legal advice; see the official statute text and our terms of use.
Gaston Impact Fee FAQs
How much are commercial impact fees in Gaston?
Gaston does not currently levy impact fees on commercial development.
Does Gaston charge its own impact fees?
Yes. Gaston levies its own municipal impact or utility fees. Lexington County does not currently add county-level impact fees inside Gaston. The schedule on this page shows every fee that applies to development in Gaston.
Can a South Carolina impact fee be raised after it is adopted?
Only through a new ordinance. Under S.C. Code 6-1-940 the government is bound by the amount its impact fee ordinance sets for each unit of development and may not charge higher or additional impact fees for the same purpose unless the project's service units increase or its scope changes, and then only for the added share. Water and sewer capacity and tap fees set by utilities follow each provider's own rate process.
Fee amounts on this page are compiled from official published schedules and are provided for planning purposes only. Rates change, and project specifics (unit size, meter size, location within special districts) can alter what applies. Always verify current fees with the jurisdiction and utility before relying on them.
Compare unincorporated rates and every other city on the Lexington County impact fees page.