Skip to content
IMPACTFEES.ORG

Harlingen, Texas Impact Fees

Harlingen applies its own fee schedule. Cameron County does not currently add county-level impact fees inside city limits. A new single-family home pays $3,778.00 per unit (rates sourced ). This figure includes amounts that have not been confirmed with the jurisdiction; verify before budgeting. The full breakdown is below.

Harlingen Impact Fees by Project Type

Harlingen: Single-Family Impact Fees

A new single-family home in Harlingen pays $3,778.00 per unit in impact fees (rates sourced November 18, 2026). Every line item is levied at the municipal or utility level.

The largest line items are Wastewater Facilities Impact Fee (Harlingen WaterWorks System) ($1,599.00), Water Facilities Impact Fee (Harlingen WaterWorks System) ($1,044.00) and Sewer Tap Fee (Harlingen WaterWorks System) ($235.00).

Water Tap Fee (Harlingen WaterWorks System) — Tap Required and Parkland Dedication Fee-in-Lieu (City of Harlingen) are shown at the last published amount but have not been confirmed with the jurisdiction; they are included in the totals here. Verify before budgeting.

Some fees are tiered by unit size or building type; amounts reflect the representative tier noted in the schedule below.

View the Full Harlingen Impact Fee Schedule
Water$1,444.00
Sewer$1,834.00
City$500.00
  • Parkland Dedication Fee-in-Lieu (City of Harlingen)
    City of Harlingen
    City of Harlingen parkland dedication fee-in-lieu (Code Sec. 109-193, as re-enacted by Ord. 24-73 on November 6, 2024): $450 per dwelling unit, rising $25 per dwelling unit after each annual anniversary of the ordinance to a $750 cap; the amount shown is the step reached November 6, 2026. Due before the plat is recorded, for residential and multifamily plats in the city and its ETJ. Nonprofit affordable housing developers are exempt.
    $500.00Requires confirmation
County$0.00
Total (Harlingen): $3,778.00
Sources last checked Official fee schedules:Harlingen WaterWorks System (HWWS) Harlingen WaterWorks System City of Harlingen Cameron County
Amounts flagged "Requires confirmation" are the last published figures, included in the totals. Confirm them with the jurisdiction or utility before budgeting.

Where in Cameron County Are You Building?

Each jurisdiction applies its own fee schedule. Pick yours. = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.

Harlingen: Multifamily Impact Fees

A new multifamily unit in Harlingen pays $3,778.00 per unit in impact fees (rates sourced November 18, 2026). Every line item is levied at the municipal or utility level.

The largest line items are Wastewater Facilities Impact Fee (Harlingen WaterWorks System) (MF) ($1,599.00), Water Facilities Impact Fee (Harlingen WaterWorks System) (MF) ($1,044.00) and Sewer Tap Fee (Harlingen WaterWorks System, MF) ($235.00).

Water Tap Fee (Harlingen WaterWorks System, MF) — Tap Required and Parkland Dedication Fee-in-Lieu (City of Harlingen, MF) are shown at the last published amount but have not been confirmed with the jurisdiction; they are included in the totals here. Verify before budgeting.

Some fees are tiered by unit size or building type; amounts reflect the representative tier noted in the schedule below.

View the Full Harlingen Impact Fee Schedule
Water$1,444.00
Sewer$1,834.00
City$500.00
  • Parkland Dedication Fee-in-Lieu (City of Harlingen, MF)
    City of Harlingen
    City of Harlingen parkland dedication fee-in-lieu (Code Sec. 109-193, as re-enacted by Ord. 24-73 on November 6, 2024): $450 per dwelling unit, rising $25 per dwelling unit after each annual anniversary of the ordinance to a $750 cap; the amount shown is the step reached November 6, 2026. Due before the plat is recorded, for residential and multifamily plats in the city and its ETJ. Nonprofit affordable housing developers are exempt.
    $500.00Requires confirmation
County$0.00
Total (Harlingen): $3,778.00
Sources last checked Official fee schedules:Harlingen WaterWorks System (HWWS) Harlingen WaterWorks System City of Harlingen Cameron County
Amounts flagged "Requires confirmation" are the last published figures, included in the totals. Confirm them with the jurisdiction or utility before budgeting.

Where in Cameron County Are You Building?

Each jurisdiction applies its own fee schedule. Pick yours. = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.

Harlingen: Commercial Impact Fees

Commercial development in Harlingen pays no per-square-foot impact fees, but owes $7,293.00 in one-time water and sewer connection fees (rates sourced November 18, 2026).

For a 50,000 sq ft building, that comes to about $7,293.00. The calculator below adjusts to your exact square footage.

The largest line items are Wastewater Facilities Impact Fee (Harlingen WaterWorks System) — 1" ($3,998.00 one-time), Water Facilities Impact Fee (Harlingen WaterWorks System) — 1" ($2,610.00 one-time) and Sewer Tap Fee (Harlingen WaterWorks System) — 4" lateral ($200 + $35 inspection) ($235.00 one-time).

Water and sewer connection fees assume a 1-inch meter; larger services pay more. See the meter-size tiers in the source schedules.

Water Tap Fee (Harlingen WaterWorks System) — 1", tap required is shown at the last published amount but has not been confirmed with the jurisdiction; it is included in the totals here. Verify before budgeting.

View the Full Harlingen Impact Fee Schedule
Water$3,060.00 one-time
  • Water Facilities Impact Fee (Harlingen WaterWorks System) — 1"
    Harlingen WaterWorks System
    Harlingen WaterWorks System water impact fee by meter size, assessed at plat recording and collected at connection or building permit. Customers outside the city limits pay about 11% more (1" meter $2,900). Tap fees are charged separately.
    $2,610.00 one-time
  • Water Tap Fee (Harlingen WaterWorks System) — 1", tap required
    Harlingen WaterWorks System
    Harlingen WaterWorks System water tap fee for a 1" meter where a new tap is needed; $250 where a tap already exists. Prices can vary with main line and property location, and taps over 2" are billed at cost. The water impact fee is charged separately.
    $450.00 one-timeRequires confirmation
Sewer$4,233.00 one-time
City$0.00
  • City Impact Fee (City of Harlingen, Commercial)
    City of Harlingen
    The City of Harlingen charges no roadway or other city impact fee on nonresidential development. Inside the V-line relief drain special district, a per-acre drainage fee is due before a plat is recorded. Water and wastewater impact fees are charged by Harlingen WaterWorks System.
    $0.00
County$0.00
  • County Impact Fee (Cameron County, Commercial)
    Cameron County
    Cameron County does not charge impact fees on nonresidential development. Texas counties may levy impact fees only for drainage, and only in or next to counties of 3.3 million or more residents.
    $0.00
Total (Harlingen): $7,293.00 one-time (≈ $7,293.00 at 50,000 sq ft)
Sources last checked Official fee schedules:Harlingen WaterWorks System City of Harlingen Cameron County
Amounts flagged "Requires confirmation" are the last published figures, included in the totals. Confirm them with the jurisdiction or utility before budgeting.
Water/sewer connection fees assume a 1-inch meter; larger services pay more.

Where in Cameron County Are You Building?

Each jurisdiction applies its own fee schedule. Pick yours. Totals shown are for a 50,000 sq ft building, including water/sewer fees (one-time connection fees assume a 1-inch meter). * = one-time water/sewer connection charges only; no per-sq-ft impact fee schedule sourced for that jurisdiction. = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.

Harlingen: Industrial Impact Fees

Industrial development in Harlingen pays no per-square-foot impact fees, but owes $7,293.00 in one-time water and sewer connection fees (rates sourced November 18, 2026).

For a 50,000 sq ft building, that comes to about $7,293.00. The calculator below adjusts to your exact square footage.

The largest line items are Wastewater Facilities Impact Fee (Harlingen WaterWorks System) — 1" ($3,998.00 one-time), Water Facilities Impact Fee (Harlingen WaterWorks System) — 1" ($2,610.00 one-time) and Sewer Tap Fee (Harlingen WaterWorks System) — 4" lateral ($200 + $35 inspection) ($235.00 one-time).

Water and sewer connection fees assume a 1-inch meter; larger services pay more. See the meter-size tiers in the source schedules.

Water Tap Fee (Harlingen WaterWorks System) — 1", tap required is shown at the last published amount but has not been confirmed with the jurisdiction; it is included in the totals here. Verify before budgeting.

View the Full Harlingen Impact Fee Schedule
Water$3,060.00 one-time
  • Water Facilities Impact Fee (Harlingen WaterWorks System) — 1"
    Harlingen WaterWorks System
    Harlingen WaterWorks System water impact fee by meter size, assessed at plat recording and collected at connection or building permit. Customers outside the city limits pay about 11% more (1" meter $2,900). Tap fees are charged separately.
    $2,610.00 one-time
  • Water Tap Fee (Harlingen WaterWorks System) — 1", tap required
    Harlingen WaterWorks System
    Harlingen WaterWorks System water tap fee for a 1" meter where a new tap is needed; $250 where a tap already exists. Prices can vary with main line and property location, and taps over 2" are billed at cost. The water impact fee is charged separately.
    $450.00 one-timeRequires confirmation
Sewer$4,233.00 one-time
City$0.00
  • City Impact Fee (City of Harlingen, Industrial)
    City of Harlingen
    The City of Harlingen charges no roadway or other city impact fee on nonresidential development. Inside the V-line relief drain special district, a per-acre drainage fee is due before a plat is recorded. Water and wastewater impact fees are charged by Harlingen WaterWorks System.
    $0.00
County$0.00
  • County Impact Fee (Cameron County, Industrial)
    Cameron County
    Cameron County does not charge impact fees on nonresidential development. Texas counties may levy impact fees only for drainage, and only in or next to counties of 3.3 million or more residents.
    $0.00
Total (Harlingen): $7,293.00 one-time (≈ $7,293.00 at 50,000 sq ft)
Sources last checked Official fee schedules:Harlingen WaterWorks System City of Harlingen Cameron County
Amounts flagged "Requires confirmation" are the last published figures, included in the totals. Confirm them with the jurisdiction or utility before budgeting.
Water/sewer connection fees assume a 1-inch meter; larger services pay more.

Where in Cameron County Are You Building?

Each jurisdiction applies its own fee schedule. Pick yours. Totals shown are for a 50,000 sq ft building, including water/sewer fees (one-time connection fees assume a 1-inch meter). * = one-time water/sewer connection charges only; no per-sq-ft impact fee schedule sourced for that jurisdiction. = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.

Harlingen: Office Impact Fees

Office development in Harlingen pays no per-square-foot impact fees, but owes $7,293.00 in one-time water and sewer connection fees (rates sourced November 18, 2026).

For a 25,000 sq ft building, that comes to about $7,293.00. The calculator below adjusts to your exact square footage.

The largest line items are Wastewater Facilities Impact Fee (Harlingen WaterWorks System) — 1" ($3,998.00 one-time), Water Facilities Impact Fee (Harlingen WaterWorks System) — 1" ($2,610.00 one-time) and Sewer Tap Fee (Harlingen WaterWorks System) — 4" lateral ($200 + $35 inspection) ($235.00 one-time).

Water and sewer connection fees assume a 1-inch meter; larger services pay more. See the meter-size tiers in the source schedules.

Water Tap Fee (Harlingen WaterWorks System) — 1", tap required is shown at the last published amount but has not been confirmed with the jurisdiction; it is included in the totals here. Verify before budgeting.

View the Full Harlingen Impact Fee Schedule
Water$3,060.00 one-time
  • Water Facilities Impact Fee (Harlingen WaterWorks System) — 1"
    Harlingen WaterWorks System
    Harlingen WaterWorks System water impact fee by meter size, assessed at plat recording and collected at connection or building permit. Customers outside the city limits pay about 11% more (1" meter $2,900). Tap fees are charged separately.
    $2,610.00 one-time
  • Water Tap Fee (Harlingen WaterWorks System) — 1", tap required
    Harlingen WaterWorks System
    Harlingen WaterWorks System water tap fee for a 1" meter where a new tap is needed; $250 where a tap already exists. Prices can vary with main line and property location, and taps over 2" are billed at cost. The water impact fee is charged separately.
    $450.00 one-timeRequires confirmation
Sewer$4,233.00 one-time
City$0.00
  • City Impact Fee (City of Harlingen, Office)
    City of Harlingen
    The City of Harlingen charges no roadway or other city impact fee on nonresidential development. Inside the V-line relief drain special district, a per-acre drainage fee is due before a plat is recorded. Water and wastewater impact fees are charged by Harlingen WaterWorks System.
    $0.00
County$0.00
  • County Impact Fee (Cameron County, Office)
    Cameron County
    Cameron County does not charge impact fees on nonresidential development. Texas counties may levy impact fees only for drainage, and only in or next to counties of 3.3 million or more residents.
    $0.00
Total (Harlingen): $7,293.00 one-time (≈ $7,293.00 at 25,000 sq ft)
Sources last checked Official fee schedules:Harlingen WaterWorks System City of Harlingen Cameron County
Amounts flagged "Requires confirmation" are the last published figures, included in the totals. Confirm them with the jurisdiction or utility before budgeting.
Water/sewer connection fees assume a 1-inch meter; larger services pay more.

Where in Cameron County Are You Building?

Each jurisdiction applies its own fee schedule. Pick yours. Totals shown are for a 25,000 sq ft building, including water/sewer fees (one-time connection fees assume a 1-inch meter). * = one-time water/sewer connection charges only; no per-sq-ft impact fee schedule sourced for that jurisdiction. = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.

Harlingen Impact Fee Calculator

Estimate impact fees for your project. Set to single-family. Drop a pin or search an address for site-specific fees.

Location

Select a location to begin

Once you select an address or drop a pin, we'll identify the responsible city and county and generate a fee breakdown.

Water & Sewer
Transportation
Parks
Schools
Fire & Police
General

How Impact Fees Work in Texas

Texas cities, and certain special districts and authorities, assess impact fees under Chapter 395 of the Local Government Code and, with narrow exceptions, may charge one only by following it. A fee rests on adopted land use assumptions and a capital improvements plan, and imposing one takes the votes of two-thirds of the governing body's members.

Impact fees may fund only water supply, treatment and distribution; wastewater collection and treatment; storm water, drainage and flood control; and roadway facilities. Parks, schools, police and fire facilities are not on the chapter's list. The chapter does not treat park land dedication, or a payment in its place, as an impact fee, so a city can require that separately. The fee per service unit is capped at the plan's growth-related cost, less a required credit, divided by the projected service units. Counties generally cannot charge impact fees: the chapter gives that authority only to counties of 3.3 million or more people and the counties bordering them, and only for storm water, drainage and flood control. Since September 2025 a city also may not charge an impact fee where an office, retail or warehouse building at least five years old is converted to multifamily or mixed-use residential use (at least 65 percent of the building and of each usable floor), unless the land was already subject to an impact fee before the conversion's building permit was filed (Section 218.204).

For land platted after a fee is adopted, the fee is assessed no later than when the plat is recorded, which fixes the most that can be charged per service unit. Where water and wastewater capacity is available, it is generally collected when the building permit is issued, or when a water or wastewater meter connection is applied for on land outside city limits or where the entity charging the fee issues no building permits. A fee not spent as the chapter allows within 10 years of payment must generally be refunded with interest, and the land use assumptions and capital improvements plan are updated at least every five years unless the governing body formally determines that no update is needed.

A city may charge water, wastewater and drainage impact fees in its extraterritorial jurisdiction as well as inside its limits, but roadway impact fees stop at the city limits. Where a utility district or another provider supplies water or sewer instead of the city, its charges are separate from the city's, so the total can differ between a city, its neighbors and the unincorporated land around it.

Brush up on impact fee basics before you budget your next project.

Summary current as of November 2026. This is an editorial summary, not legal advice; see the official statute text and our terms of use.

Harlingen Impact Fee FAQs

What are the total impact fees for a single-family home in Harlingen, Texas?

A new single-family home in Harlingen pays $3,778.00 per unit in combined impact fees (rates sourced November 18, 2026). This figure includes amounts that have not been confirmed with the jurisdiction; verify before budgeting.

How much are commercial impact fees in Harlingen?

Commercial development in Harlingen pays no per-square-foot impact fees, but owes $7,293.00 in one-time water and sewer connection fees (assuming a 1-inch meter). This figure includes amounts that have not been confirmed with the jurisdiction; verify before budgeting.

Does Harlingen charge its own impact fees?

Yes. Harlingen levies its own municipal impact or utility fees. Cameron County does not currently add county-level impact fees inside Harlingen. The schedule on this page shows every fee that applies to development in Harlingen.

Can a Texas impact fee increase at any time?

No. Under Section 395.0515 of the Local Government Code, added in 2025, a city or district may not increase an impact fee for three years from the later of the date the fee was adopted or last increased, although it may phase in collection up to the adopted maximum over no more than ten years. An increase also needs an independent financial audit and a public hearing on its results first (Section 395.059), and the measure approving it cannot be adopted as an emergency measure (Section 395.057). Once a fee is assessed on a tract, it cannot be raised for that tract unless the number of service units increases (Section 395.017). Charges set by a separate water or sewer provider may follow different rules.

Fee amounts on this page are compiled from official published schedules and are provided for planning purposes only. Rates change, and project specifics (unit size, meter size, location within special districts) can alter what applies. Always verify current fees with the jurisdiction and utility before relying on them.

Compare unincorporated rates and every other city on the Cameron County impact fees page.

Missing a jurisdiction, or want to sponsor one?

Request coverage for a city or county, ask about sponsoring its page, or report an issue. We typically reply within one business day.