Deer Park Impact Fees by Project Type
Deer Park: Single-Family Impact Fees
A new single-family home in Deer Park pays at least $585.00 per unit in impact fees (rates sourced November 22, 2026). Every line item is levied at the municipal or utility level.
Water Tap Fee (City of Deer Park) and Sewer Tap Fee (City of Deer Park) — 4" line are shown at the last published amount but have not been confirmed with the jurisdiction; they are included in the totals here. Verify before budgeting.
City Impact Fee (City of Deer Park) — none is set by the city and has no published standard rate. Contact the levying jurisdiction or utility to verify before budgeting; it is not included as a dollar figure here.
Some fees are tiered by unit size or building type; amounts reflect the representative tier noted in the schedule below.
View the Full Deer Park Impact Fee Schedule
- Water Tap Fee (City of Deer Park)$310.00Requires confirmationCity of Deer ParkThe City of Deer Park provides water. One-time standard 5/8 x 3/4 inch water tap fee of $310 (Code Sec. 106-23(c), Appendix B as amended July 2, 2024); other tap sizes are charged at actual cost plus 15 percent. No Chapter 395 water impact fee.
- Sewer Tap Fee (City of Deer Park) — 4" line$275.00Requires confirmationCity of Deer ParkThe City of Deer Park provides sewer. One-time sewer tap fee by line size: 4 inch $275, 6 inch $300, 8 inch $350 (Code Sec. 106-23(d), Appendix B as amended July 2, 2024); larger lines are charged at actual cost plus 15 percent. No Chapter 395 wastewater impact fee.
- City Impact Fee (City of Deer Park) — noneRequires confirmationCity of Deer ParkThe City of Deer Park levies no Chapter 395 city development impact fee.
- County Impact Fee (Harris County) — none levied$0.00Harris CountyNo Harris County impact fee applies in Deer Park. Harris County levies no countywide impact fee; the Harris County Flood Control District's drainage impact fee applies only in two watershed service areas of unincorporated northwest Harris County.
Where in Harris County Are You Building?
Each jurisdiction applies its own fee schedule. Pick yours. = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.
Deer Park: Multifamily Impact Fees
A new multifamily unit in Deer Park pays at least $585.00 per unit in impact fees (rates sourced November 22, 2026). Every line item is levied at the municipal or utility level.
Sewer Tap Fee (City of Deer Park, MF) — 4" line and Water Tap Fee (City of Deer Park, MF) are shown at the last published amount but have not been confirmed with the jurisdiction; they are included in the totals here. Verify before budgeting.
City Impact Fee (City of Deer Park, MF) — none is set by the city and has no published standard rate. Contact the levying jurisdiction or utility to verify before budgeting; it is not included as a dollar figure here.
Some fees are tiered by unit size or building type; amounts reflect the representative tier noted in the schedule below.
View the Full Deer Park Impact Fee Schedule
- Water Tap Fee (City of Deer Park, MF)$310.00Requires confirmationCity of Deer ParkThe City of Deer Park provides water. One-time water tap fee per connection: $310 for a standard 5/8 x 3/4 inch tap; larger taps are charged at actual cost plus 15 percent. A building on one connection pays once.
- Sewer Tap Fee (City of Deer Park, MF) — 4" line$275.00Requires confirmationCity of Deer ParkThe City of Deer Park provides sewer. One-time sewer tap fee per connection by line size: 4 inch $275, 6 inch $300, 8 inch $350; a building on one connection pays once.
- City Impact Fee (City of Deer Park, MF) — noneRequires confirmationCity of Deer ParkThe City of Deer Park levies no Chapter 395 city development impact fee.
- County Impact Fee (Harris County, MF) — none levied$0.00Harris CountyNo Harris County impact fee applies in Deer Park. Harris County levies no countywide impact fee; the Harris County Flood Control District's drainage impact fee applies only in two watershed service areas of unincorporated northwest Harris County.
Where in Harris County Are You Building?
Each jurisdiction applies its own fee schedule. Pick yours. = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.
Deer Park: Commercial Impact Fees
Commercial development in Deer Park pays no per-square-foot impact fees, but owes $650.00 in one-time water and sewer connection fees (rates sourced November 22, 2026).
For a 50,000 sq ft building, that comes to at least $650.00. The calculator below adjusts to your exact square footage.
The largest line items are Water Meter Fee (City of Deer Park) — 1" meter and box ($375.00 one-time) and Sewer Tap Fee (City of Deer Park) — 4" line ($275.00 one-time).
Water and sewer connection fees assume a 1-inch meter; larger services pay more. See the meter-size tiers in the source schedules.
Water Tap Fee (City of Deer Park) — non-standard tap, cost-based is set by the utility and not published online. Contact the levying jurisdiction or utility to verify before budgeting; it is not included as a dollar figure here.
View the Full Deer Park Impact Fee Schedule
- Water Meter Fee (City of Deer Park) — 1" meter and box$375.00 one-timeCity of Deer ParkCity charge for a commercial water meter and meter box, by meter size (Ord. 4533, July 2024). A water tap is charged separately: a standard 5/8 x 3/4 inch tap is $310, and any larger tap is billed at actual cost plus 15 percent. The city charges no water impact fee.
- Water Tap Fee (City of Deer Park) — non-standard tap, cost-basedRequires confirmationCity of Deer ParkThe city charges a water tap fee in addition to the meter. A standard 5/8 x 3/4 inch tap is $310; every larger tap, including a typical 1 inch commercial service, is billed at the actual cost of material, labor and equipment plus 15 percent.
- Sewer Tap Fee (City of Deer Park) — 4" line$275.00 one-timeCity of Deer ParkCity sewer tap fee by service line size (Ord. 4533, July 2024). Taps larger than 8 inches are billed at actual cost plus 15 percent. The city charges no wastewater impact fee.
- City Impact Fee (City of Deer Park, Commercial)$0.00City of Deer ParkThe City of Deer Park charges no city impact fee on commercial, office or industrial development.
- County Impact Fee (Harris County, Deer Park, Commercial)$0.00Harris CountyHarris County charges no county impact fee on development in Deer Park; the Flood Control District's watershed fees apply only in two service areas of unincorporated northwest Harris County.
Where in Harris County Are You Building?
Each jurisdiction applies its own fee schedule. Pick yours. Totals shown are for a 50,000 sq ft building, including water/sewer fees (one-time connection fees assume a 1-inch meter). * = one-time water/sewer connection charges only; no per-sq-ft impact fee schedule sourced for that jurisdiction. = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.
Deer Park: Industrial Impact Fees
Industrial development in Deer Park pays no per-square-foot impact fees, but owes $650.00 in one-time water and sewer connection fees (rates sourced November 22, 2026).
For a 50,000 sq ft building, that comes to at least $650.00. The calculator below adjusts to your exact square footage.
The largest line items are Water Meter Fee (City of Deer Park) — 1" meter and box ($375.00 one-time) and Sewer Tap Fee (City of Deer Park) — 4" line ($275.00 one-time).
Water and sewer connection fees assume a 1-inch meter; larger services pay more. See the meter-size tiers in the source schedules.
Water Tap Fee (City of Deer Park) — non-standard tap, cost-based is set by the utility and not published online. Contact the levying jurisdiction or utility to verify before budgeting; it is not included as a dollar figure here.
View the Full Deer Park Impact Fee Schedule
- Water Meter Fee (City of Deer Park) — 1" meter and box$375.00 one-timeCity of Deer ParkCity charge for a commercial water meter and meter box, by meter size (Ord. 4533, July 2024). A water tap is charged separately: a standard 5/8 x 3/4 inch tap is $310, and any larger tap is billed at actual cost plus 15 percent. The city charges no water impact fee.
- Water Tap Fee (City of Deer Park) — non-standard tap, cost-basedRequires confirmationCity of Deer ParkThe city charges a water tap fee in addition to the meter. A standard 5/8 x 3/4 inch tap is $310; every larger tap, including a typical 1 inch commercial service, is billed at the actual cost of material, labor and equipment plus 15 percent.
- Sewer Tap Fee (City of Deer Park) — 4" line$275.00 one-timeCity of Deer ParkCity sewer tap fee by service line size (Ord. 4533, July 2024). Taps larger than 8 inches are billed at actual cost plus 15 percent. The city charges no wastewater impact fee.
- City Impact Fee (City of Deer Park, Industrial)$0.00City of Deer ParkThe City of Deer Park charges no city impact fee on commercial, office or industrial development.
- County Impact Fee (Harris County, Deer Park, Industrial)$0.00Harris CountyHarris County charges no county impact fee on development in Deer Park; the Flood Control District's watershed fees apply only in two service areas of unincorporated northwest Harris County.
Where in Harris County Are You Building?
Each jurisdiction applies its own fee schedule. Pick yours. Totals shown are for a 50,000 sq ft building, including water/sewer fees (one-time connection fees assume a 1-inch meter). * = one-time water/sewer connection charges only; no per-sq-ft impact fee schedule sourced for that jurisdiction. = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.
Deer Park: Office Impact Fees
Office development in Deer Park pays no per-square-foot impact fees, but owes $650.00 in one-time water and sewer connection fees (rates sourced November 22, 2026).
For a 25,000 sq ft building, that comes to at least $650.00. The calculator below adjusts to your exact square footage.
The largest line items are Water Meter Fee (City of Deer Park) — 1" meter and box ($375.00 one-time) and Sewer Tap Fee (City of Deer Park) — 4" line ($275.00 one-time).
Water and sewer connection fees assume a 1-inch meter; larger services pay more. See the meter-size tiers in the source schedules.
Water Tap Fee (City of Deer Park) — non-standard tap, cost-based is set by the utility and not published online. Contact the levying jurisdiction or utility to verify before budgeting; it is not included as a dollar figure here.
View the Full Deer Park Impact Fee Schedule
- Water Meter Fee (City of Deer Park) — 1" meter and box$375.00 one-timeCity of Deer ParkCity charge for a commercial water meter and meter box, by meter size (Ord. 4533, July 2024). A water tap is charged separately: a standard 5/8 x 3/4 inch tap is $310, and any larger tap is billed at actual cost plus 15 percent. The city charges no water impact fee.
- Water Tap Fee (City of Deer Park) — non-standard tap, cost-basedRequires confirmationCity of Deer ParkThe city charges a water tap fee in addition to the meter. A standard 5/8 x 3/4 inch tap is $310; every larger tap, including a typical 1 inch commercial service, is billed at the actual cost of material, labor and equipment plus 15 percent.
- Sewer Tap Fee (City of Deer Park) — 4" line$275.00 one-timeCity of Deer ParkCity sewer tap fee by service line size (Ord. 4533, July 2024). Taps larger than 8 inches are billed at actual cost plus 15 percent. The city charges no wastewater impact fee.
- City Impact Fee (City of Deer Park, Office)$0.00City of Deer ParkThe City of Deer Park charges no city impact fee on commercial, office or industrial development.
- County Impact Fee (Harris County, Deer Park, Office)$0.00Harris CountyHarris County charges no county impact fee on development in Deer Park; the Flood Control District's watershed fees apply only in two service areas of unincorporated northwest Harris County.
Where in Harris County Are You Building?
Each jurisdiction applies its own fee schedule. Pick yours. Totals shown are for a 25,000 sq ft building, including water/sewer fees (one-time connection fees assume a 1-inch meter). * = one-time water/sewer connection charges only; no per-sq-ft impact fee schedule sourced for that jurisdiction. = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.
Deer Park Impact Fee Calculator
Estimate impact fees for your project. Set to single-family. Drop a pin or search an address for site-specific fees.
Location
Select a location to begin
Once you select an address or drop a pin, we'll identify the responsible city and county and generate a fee breakdown.
How Impact Fees Work in Texas
Texas cities, and certain special districts and authorities, assess impact fees under Chapter 395 of the Local Government Code and, with narrow exceptions, may charge one only by following it. A fee rests on adopted land use assumptions and a capital improvements plan, and imposing one takes the votes of two-thirds of the governing body's members.
Impact fees may fund only water supply, treatment and distribution; wastewater collection and treatment; storm water, drainage and flood control; and roadway facilities. Parks, schools, police and fire facilities are not on the chapter's list. The chapter does not treat park land dedication, or a payment in its place, as an impact fee, so a city can require that separately. The fee per service unit is capped at the plan's growth-related cost, less a required credit, divided by the projected service units. Counties generally cannot charge impact fees: the chapter gives that authority only to counties of 3.3 million or more people and the counties bordering them, and only for storm water, drainage and flood control. Since September 2025 a city also may not charge an impact fee where an office, retail or warehouse building at least five years old is converted to multifamily or mixed-use residential use (at least 65 percent of the building and of each usable floor), unless the land was already subject to an impact fee before the conversion's building permit was filed (Section 218.204).
For land platted after a fee is adopted, the fee is assessed no later than when the plat is recorded, which fixes the most that can be charged per service unit. Where water and wastewater capacity is available, it is generally collected when the building permit is issued, or when a water or wastewater meter connection is applied for on land outside city limits or where the entity charging the fee issues no building permits. A fee not spent as the chapter allows within 10 years of payment must generally be refunded with interest, and the land use assumptions and capital improvements plan are updated at least every five years unless the governing body formally determines that no update is needed.
A city may charge water, wastewater and drainage impact fees in its extraterritorial jurisdiction as well as inside its limits, but roadway impact fees stop at the city limits. Where a utility district or another provider supplies water or sewer instead of the city, its charges are separate from the city's, so the total can differ between a city, its neighbors and the unincorporated land around it.
New to impact fees? Our plain-English guide explains what they cover, who pays them, and why they exist.
Summary current as of November 2026. This is an editorial summary, not legal advice; see the official statute text and our terms of use.
Deer Park Impact Fee FAQs
What are the total impact fees for a single-family home in Deer Park, Texas?
A new single-family home in Deer Park pays at least $585.00 per unit in combined impact fees (rates sourced November 22, 2026). This figure includes amounts that have not been confirmed and excludes fees with no published standard amount, so the full cost may be higher; verify before budgeting.
How much are commercial impact fees in Deer Park?
Commercial development in Deer Park pays no per-square-foot impact fees, but owes $650.00 in one-time water and sewer connection fees (assuming a 1-inch meter). One additional fee has no published standard amount and is not included, so the full cost may be higher; verify before budgeting.
Does Deer Park charge its own impact fees?
Yes. Deer Park levies its own municipal impact or utility fees. Harris County does not currently add county-level impact fees inside Deer Park. The schedule on this page shows every fee that applies to development in Deer Park.
Can a Texas impact fee increase at any time?
No. Under Section 395.0515 of the Local Government Code, added in 2025, a city or district may not increase an impact fee for three years from the later of the date the fee was adopted or last increased, although it may phase in collection up to the adopted maximum over no more than ten years. An increase also needs an independent financial audit and a public hearing on its results first (Section 395.059), and the measure approving it cannot be adopted as an emergency measure (Section 395.057). Once a fee is assessed on a tract, it cannot be raised for that tract unless the number of service units increases (Section 395.017). Charges set by a separate water or sewer provider may follow different rules.
Fee amounts on this page are compiled from official published schedules and are provided for planning purposes only. Rates change, and project specifics (unit size, meter size, location within special districts) can alter what applies. Always verify current fees with the jurisdiction and utility before relying on them.
Compare unincorporated rates and every other city on the Harris County impact fees page.