Webster Impact Fees by Project Type
Webster: Single-Family Impact Fees
A new single-family home in Webster pays at least $7,461.00 per unit in impact fees (rates sourced November 24, 2026). Every line item is levied at the municipal or utility level.
The largest line items are Wastewater Impact Fee (City of Webster) — 5/8" meter ($5,243.00) and Water Impact Fee (City of Webster) — 5/8" meter ($2,218.00).
Water and Sewer Tap Fee (City of Webster) is set by the city and has no published standard rate. Contact the levying jurisdiction or utility to verify before budgeting; it is not included as a dollar figure here.
Some fees are tiered by unit size or building type; amounts reflect the representative tier noted in the schedule below.
View the Full Webster Impact Fee Schedule
- Water Impact Fee (City of Webster) — 5/8" meter$2,218.00City of WebsterChapter 395 water impact fee for a 5/8 inch meter, City of Webster Ordinance 22-12, effective November 15, 2022. A separate city tap charge also applies.
- Wastewater Impact Fee (City of Webster) — 5/8" meter$5,243.00City of WebsterChapter 395 wastewater impact fee for a 5/8 inch meter, City of Webster Ordinance 22-12, effective November 15, 2022. A separate city tap charge also applies.
- City Impact Fee (City of Webster)$0.00City of WebsterThe City of Webster's only impact fees are for water and wastewater; it levies no roadway, drainage, or parkland dedication fee.
- County Impact Fee (Harris County)$0.00Harris CountyNo Harris County impact fee applies in Webster. Harris County levies no countywide impact fee; the Harris County Flood Control District's drainage impact fee applies only in two watershed service areas of unincorporated northwest Harris County.
- Water and Sewer Tap Fee (City of Webster)Requires confirmationCity of WebsterThe City of Webster collects a separate charge to install water and sewer taps, in addition to its impact fees; the amount is not published.
Where in Harris County Are You Building?
Each jurisdiction applies its own fee schedule. Pick yours. = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.
Webster: Multifamily Impact Fees
A new multifamily unit in Webster pays at least $7,461.00 per unit in impact fees (rates sourced November 24, 2026). Every line item is levied at the municipal or utility level.
The largest line items are Wastewater Impact Fee (City of Webster, MF) — 5/8" meter ($5,243.00) and Water Impact Fee (City of Webster, MF) — 5/8" meter ($2,218.00).
Water and Sewer Tap Fee (City of Webster, MF) is set by the city and has no published standard rate. Contact the levying jurisdiction or utility to verify before budgeting; it is not included as a dollar figure here.
Some fees are tiered by unit size or building type; amounts reflect the representative tier noted in the schedule below.
View the Full Webster Impact Fee Schedule
- Water Impact Fee (City of Webster, MF) — 5/8" meter$2,218.00City of WebsterChapter 395 water impact fee for a 5/8 inch meter, City of Webster Ordinance 22-12, effective November 15, 2022. A multifamily building pays on the size of each meter serving it. A separate city tap charge also applies.
- Wastewater Impact Fee (City of Webster, MF) — 5/8" meter$5,243.00City of WebsterChapter 395 wastewater impact fee for a 5/8 inch meter, City of Webster Ordinance 22-12, effective November 15, 2022. A multifamily building pays on the size of each meter serving it. A separate city tap charge also applies.
- City Impact Fee (City of Webster, MF)$0.00City of WebsterThe City of Webster's only impact fees are for water and wastewater; it levies no roadway, drainage, or parkland dedication fee.
- County Impact Fee (Harris County, MF)$0.00Harris CountyNo Harris County impact fee applies in Webster. Harris County levies no countywide impact fee; the Harris County Flood Control District's drainage impact fee applies only in two watershed service areas of unincorporated northwest Harris County.
- Water and Sewer Tap Fee (City of Webster, MF)Requires confirmationCity of WebsterThe City of Webster collects a separate charge to install water and sewer taps, in addition to its impact fees; the amount is not published.
Where in Harris County Are You Building?
Each jurisdiction applies its own fee schedule. Pick yours. = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.
Webster: Commercial Impact Fees
Commercial development in Webster pays no per-square-foot impact fees, but owes $19,846.00 in one-time water and sewer connection fees (rates sourced November 24, 2026).
For a 50,000 sq ft building, that comes to at least $19,846.00. The calculator below adjusts to your exact square footage.
The largest line items are Wastewater Impact Fee (City of Webster) — 1" meter ($13,945.00 one-time) and Water Impact Fee (City of Webster) — 1" meter ($5,901.00 one-time).
Water and sewer connection fees assume a 1-inch meter; larger services pay more. See the meter-size tiers in the source schedules.
Water and Sewer Tap Fee (City of Webster) is set by the city and has no published standard rate. Contact the levying jurisdiction or utility to verify before budgeting; it is not included as a dollar figure here.
View the Full Webster Impact Fee Schedule
- Water Impact Fee (City of Webster) — 1" meter$5,901.00 one-timeCity of WebsterCity of Webster water impact fee for a 1 inch meter, Ordinance 22-12, effective November 15, 2022. Meters 3 inches and larger are compound meters. A separate city tap charge also applies.
- Wastewater Impact Fee (City of Webster) — 1" meter$13,945.00 one-timeCity of WebsterCity of Webster wastewater impact fee for a 1 inch water meter, Ordinance 22-12, effective November 15, 2022. A separate city tap charge also applies.
- City Impact Fee (City of Webster, Commercial)$0.00City of WebsterThe City of Webster charges no roadway, drainage or other city impact fee on commercial, office or industrial development. Its water and wastewater impact fees are listed with the utility fees.
- County Impact Fee (Harris County, Webster, Commercial)$0.00Harris CountyHarris County charges no county impact fee on development in Webster; the Flood Control District's watershed fees apply only in two service areas of unincorporated northwest Harris County.
- Water and Sewer Tap Fee (City of Webster)Requires confirmationCity of WebsterThe City of Webster collects a separate charge to install water and sewer taps, in addition to its impact fees; the amount is not published.
Where in Harris County Are You Building?
Each jurisdiction applies its own fee schedule. Pick yours. Totals shown are for a 50,000 sq ft building, including water/sewer fees (one-time connection fees assume a 1-inch meter). * = one-time water/sewer connection charges only; no per-sq-ft impact fee schedule sourced for that jurisdiction. = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.
Webster: Industrial Impact Fees
Industrial development in Webster pays no per-square-foot impact fees, but owes $19,846.00 in one-time water and sewer connection fees (rates sourced November 24, 2026).
For a 50,000 sq ft building, that comes to at least $19,846.00. The calculator below adjusts to your exact square footage.
The largest line items are Wastewater Impact Fee (City of Webster) — 1" meter ($13,945.00 one-time) and Water Impact Fee (City of Webster) — 1" meter ($5,901.00 one-time).
Water and sewer connection fees assume a 1-inch meter; larger services pay more. See the meter-size tiers in the source schedules.
Water and Sewer Tap Fee (City of Webster) is set by the city and has no published standard rate. Contact the levying jurisdiction or utility to verify before budgeting; it is not included as a dollar figure here.
View the Full Webster Impact Fee Schedule
- Water Impact Fee (City of Webster) — 1" meter$5,901.00 one-timeCity of WebsterCity of Webster water impact fee for a 1 inch meter, Ordinance 22-12, effective November 15, 2022. Meters 3 inches and larger are compound meters. A separate city tap charge also applies.
- Wastewater Impact Fee (City of Webster) — 1" meter$13,945.00 one-timeCity of WebsterCity of Webster wastewater impact fee for a 1 inch water meter, Ordinance 22-12, effective November 15, 2022. A separate city tap charge also applies.
- City Impact Fee (City of Webster, Industrial)$0.00City of WebsterThe City of Webster charges no roadway, drainage or other city impact fee on commercial, office or industrial development. Its water and wastewater impact fees are listed with the utility fees.
- County Impact Fee (Harris County, Webster, Industrial)$0.00Harris CountyHarris County charges no county impact fee on development in Webster; the Flood Control District's watershed fees apply only in two service areas of unincorporated northwest Harris County.
- Water and Sewer Tap Fee (City of Webster)Requires confirmationCity of WebsterThe City of Webster collects a separate charge to install water and sewer taps, in addition to its impact fees; the amount is not published.
Where in Harris County Are You Building?
Each jurisdiction applies its own fee schedule. Pick yours. Totals shown are for a 50,000 sq ft building, including water/sewer fees (one-time connection fees assume a 1-inch meter). * = one-time water/sewer connection charges only; no per-sq-ft impact fee schedule sourced for that jurisdiction. = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.
Webster: Office Impact Fees
Office development in Webster pays no per-square-foot impact fees, but owes $19,846.00 in one-time water and sewer connection fees (rates sourced November 24, 2026).
For a 25,000 sq ft building, that comes to at least $19,846.00. The calculator below adjusts to your exact square footage.
The largest line items are Wastewater Impact Fee (City of Webster) — 1" meter ($13,945.00 one-time) and Water Impact Fee (City of Webster) — 1" meter ($5,901.00 one-time).
Water and sewer connection fees assume a 1-inch meter; larger services pay more. See the meter-size tiers in the source schedules.
Water and Sewer Tap Fee (City of Webster) is set by the city and has no published standard rate. Contact the levying jurisdiction or utility to verify before budgeting; it is not included as a dollar figure here.
View the Full Webster Impact Fee Schedule
- Water Impact Fee (City of Webster) — 1" meter$5,901.00 one-timeCity of WebsterCity of Webster water impact fee for a 1 inch meter, Ordinance 22-12, effective November 15, 2022. Meters 3 inches and larger are compound meters. A separate city tap charge also applies.
- Wastewater Impact Fee (City of Webster) — 1" meter$13,945.00 one-timeCity of WebsterCity of Webster wastewater impact fee for a 1 inch water meter, Ordinance 22-12, effective November 15, 2022. A separate city tap charge also applies.
- City Impact Fee (City of Webster, Office)$0.00City of WebsterThe City of Webster charges no roadway, drainage or other city impact fee on commercial, office or industrial development. Its water and wastewater impact fees are listed with the utility fees.
- County Impact Fee (Harris County, Webster, Office)$0.00Harris CountyHarris County charges no county impact fee on development in Webster; the Flood Control District's watershed fees apply only in two service areas of unincorporated northwest Harris County.
- Water and Sewer Tap Fee (City of Webster)Requires confirmationCity of WebsterThe City of Webster collects a separate charge to install water and sewer taps, in addition to its impact fees; the amount is not published.
Where in Harris County Are You Building?
Each jurisdiction applies its own fee schedule. Pick yours. Totals shown are for a 25,000 sq ft building, including water/sewer fees (one-time connection fees assume a 1-inch meter). * = one-time water/sewer connection charges only; no per-sq-ft impact fee schedule sourced for that jurisdiction. = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.
Webster Impact Fee Calculator
Estimate impact fees for your project. Set to single-family. Drop a pin or search an address for site-specific fees.
Location
Select a location to begin
Once you select an address or drop a pin, we'll identify the responsible city and county and generate a fee breakdown.
How Impact Fees Work in Texas
Texas cities, and certain special districts and authorities, assess impact fees under Chapter 395 of the Local Government Code and, with narrow exceptions, may charge one only by following it. A fee rests on adopted land use assumptions and a capital improvements plan, and imposing one takes the votes of two-thirds of the governing body's members.
Impact fees may fund only water supply, treatment and distribution; wastewater collection and treatment; storm water, drainage and flood control; and roadway facilities. Parks, schools, police and fire facilities are not on the chapter's list. The chapter does not treat park land dedication, or a payment in its place, as an impact fee, so a city can require that separately. The fee per service unit is capped at the plan's growth-related cost, less a required credit, divided by the projected service units. Counties generally cannot charge impact fees: the chapter gives that authority only to counties of 3.3 million or more people and the counties bordering them, and only for storm water, drainage and flood control. Since September 2025 a city also may not charge an impact fee where an office, retail or warehouse building at least five years old is converted to multifamily or mixed-use residential use (at least 65 percent of the building and of each usable floor), unless the land was already subject to an impact fee before the conversion's building permit was filed (Section 218.204).
For land platted after a fee is adopted, the fee is assessed no later than when the plat is recorded, which fixes the most that can be charged per service unit. Where water and wastewater capacity is available, it is generally collected when the building permit is issued, or when a water or wastewater meter connection is applied for on land outside city limits or where the entity charging the fee issues no building permits. A fee not spent as the chapter allows within 10 years of payment must generally be refunded with interest, and the land use assumptions and capital improvements plan are updated at least every five years unless the governing body formally determines that no update is needed.
A city may charge water, wastewater and drainage impact fees in its extraterritorial jurisdiction as well as inside its limits, but roadway impact fees stop at the city limits. Where a utility district or another provider supplies water or sewer instead of the city, its charges are separate from the city's, so the total can differ between a city, its neighbors and the unincorporated land around it.
If you're still asking what are impact fees, start with our guide to the definition, common categories, and legal basis.
Summary current as of November 2026. This is an editorial summary, not legal advice; see the official statute text and our terms of use.
Webster Impact Fee FAQs
What are the total impact fees for a single-family home in Webster, Texas?
A new single-family home in Webster pays at least $7,461.00 per unit in combined impact fees (rates sourced November 24, 2026). One additional fee has no published standard amount and is not included, so the full cost may be higher; verify before budgeting.
How much are commercial impact fees in Webster?
Commercial development in Webster pays no per-square-foot impact fees, but owes $19,846.00 in one-time water and sewer connection fees (assuming a 1-inch meter). One additional fee has no published standard amount and is not included, so the full cost may be higher; verify before budgeting.
Does Webster charge its own impact fees?
Yes. Webster levies its own municipal impact or utility fees. Harris County does not currently add county-level impact fees inside Webster. The schedule on this page shows every fee that applies to development in Webster.
Can a Texas impact fee increase at any time?
No. Under Section 395.0515 of the Local Government Code, added in 2025, a city or district may not increase an impact fee for three years from the later of the date the fee was adopted or last increased, although it may phase in collection up to the adopted maximum over no more than ten years. An increase also needs an independent financial audit and a public hearing on its results first (Section 395.059), and the measure approving it cannot be adopted as an emergency measure (Section 395.057). Once a fee is assessed on a tract, it cannot be raised for that tract unless the number of service units increases (Section 395.017). Charges set by a separate water or sewer provider may follow different rules.
Fee amounts on this page are compiled from official published schedules and are provided for planning purposes only. Rates change, and project specifics (unit size, meter size, location within special districts) can alter what applies. Always verify current fees with the jurisdiction and utility before relying on them.
Compare unincorporated rates and every other city on the Harris County impact fees page.