Jacinto City Impact Fees by Project Type
Jacinto City: Single-Family Impact Fees
A new single-family home in Jacinto City pays $875.00 per unit in impact fees (rates sourced November 22, 2026). Every line item is levied at the municipal or utility level.
The largest line items are Sewer Tap Fee (City of Jacinto City) — over 8" sewer main ($500.00) and Water Connection Fee (City of Jacinto City) — 5/8" x 3/4" meter ($375.00).
Some fees are tiered by unit size or building type; amounts reflect the representative tier noted in the schedule below.
View the Full Jacinto City Impact Fee Schedule
- Water Connection Fee (City of Jacinto City) — 5/8" x 3/4" meter$375.00City of Jacinto CityOne-time water connection fee for a 5/8 inch x 3/4 inch meter, City of Jacinto City Code Chapter 10 (Ordinance 96-5). Includes 20 feet of service line; each added foot is $3.50. A $35 tap inspection fee also applies.
- Sewer Tap Fee (City of Jacinto City) — over 8" sewer main$500.00City of Jacinto CityOne-time sewer tapping fee set by the size of the city sewer line tapped: $200 for a 6 inch line, $300 for 8 inch, $500 for a line over 8 inches (shown here, the highest of three rates). City of Jacinto City Code Chapter 10 (Ordinance 96-5). Street repair for a pavement cut is billed at actual cost. No Chapter 395 wastewater impact fee.
- City Impact Fee (City of Jacinto City)$0.00City of Jacinto CityThe City of Jacinto City levies no municipal impact or parkland dedication fee; only water and sewer connection fees apply.
- County Impact Fee (Harris County)$0.00Harris CountyNo Harris County impact fee applies in Jacinto City. Harris County levies no countywide impact fee; the Harris County Flood Control District's drainage impact fee applies only in two watershed service areas of unincorporated northwest Harris County.
Where in Harris County Are You Building?
Each jurisdiction applies its own fee schedule. Pick yours. = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.
Jacinto City: Multifamily Impact Fees
A new multifamily unit in Jacinto City pays $875.00 per unit in impact fees (rates sourced November 22, 2026). Every line item is levied at the municipal or utility level.
The largest line items are Sewer Tap Fee (City of Jacinto City, MF) — over 8" sewer main ($500.00) and Water Connection Fee (City of Jacinto City, MF) — 5/8" x 3/4" meter ($375.00).
Some fees are tiered by unit size or building type; amounts reflect the representative tier noted in the schedule below.
View the Full Jacinto City Impact Fee Schedule
- Water Connection Fee (City of Jacinto City, MF) — 5/8" x 3/4" meter$375.00City of Jacinto CityOne-time water connection fee for a 5/8 inch x 3/4 inch meter, City of Jacinto City Code Chapter 10 (Ordinance 96-5). Includes 20 feet of service line; each added foot is $3.50. A $35 tap inspection fee also applies. A multifamily building pays by the size of each meter.
- Sewer Tap Fee (City of Jacinto City, MF) — over 8" sewer main$500.00City of Jacinto CityOne-time sewer tapping fee set by the size of the city sewer line tapped: $200 for a 6 inch line, $300 for 8 inch, $500 for a line over 8 inches (shown here, the highest of three rates). City of Jacinto City Code Chapter 10 (Ordinance 96-5). Street repair for a pavement cut is billed at actual cost. No Chapter 395 wastewater impact fee.
- City Impact Fee (City of Jacinto City, MF)$0.00City of Jacinto CityThe City of Jacinto City levies no municipal impact or parkland dedication fee; only water and sewer connection fees apply.
- County Impact Fee (Harris County, MF)$0.00Harris CountyNo Harris County impact fee applies in Jacinto City. Harris County levies no countywide impact fee; the Harris County Flood Control District's drainage impact fee applies only in two watershed service areas of unincorporated northwest Harris County.
Where in Harris County Are You Building?
Each jurisdiction applies its own fee schedule. Pick yours. = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.
Jacinto City: Commercial Impact Fees
Commercial development in Jacinto City pays no per-square-foot impact fees, but owes $1,085.00 in one-time water and sewer connection fees (rates sourced November 22, 2026).
For a 50,000 sq ft building, that comes to about $1,085.00. The calculator below adjusts to your exact square footage.
The largest line items are Water Connection Fee (City of Jacinto City) — 1" meter ($550.00 one-time), Sewer Tap Fee (City of Jacinto City) — over 8" sewer main ($500.00 one-time) and Water Tap Inspection Fee (City of Jacinto City) ($35.00 one-time).
Water and sewer connection fees assume a 1-inch meter; larger services pay more. See the meter-size tiers in the source schedules.
View the Full Jacinto City Impact Fee Schedule
- Water Connection Fee (City of Jacinto City) — 1" meter$550.00 one-timeCity of Jacinto CityJacinto City water connection charge for a 1 inch meter, up to 20 feet of service line, set in City Code Chapter 10 (1996). Meters larger than 2 inches and connections that need an open cut or bore under pavement are priced by the city at its cost. A $35 tap inspection fee also applies. The city charges no water impact fee.
- Water Tap Inspection Fee (City of Jacinto City)$35.00 one-timeCity of Jacinto CityJacinto City charges a $35 inspection fee for each water tap, in addition to the water connection charge.
- Sewer Tap Fee (City of Jacinto City) — over 8" sewer main$500.00 one-timeCity of Jacinto CityOne-time sewer tapping fee set by the size of the city sewer line tapped: $200 for a 6 inch line, $300 for an 8 inch line and $500 for a line over 8 inches (shown here, the highest of three rates). City of Jacinto City Code Chapter 10 Sec. 3.M (Ordinance 96-5). Street repair for a pavement cut is billed at actual cost. The city charges no wastewater impact fee.
- City Impact Fee (City of Jacinto City, Commercial)$0.00City of Jacinto CityThe City of Jacinto City charges no city impact fee on commercial, office or industrial development. Its water connection charges are listed with the water fees.
- County Impact Fee (Harris County, Jacinto City, Commercial)$0.00Harris CountyHarris County charges no county impact fee on development in Jacinto City; the Flood Control District's watershed fees apply only in two service areas of unincorporated northwest Harris County.
Where in Harris County Are You Building?
Each jurisdiction applies its own fee schedule. Pick yours. Totals shown are for a 50,000 sq ft building, including water/sewer fees (one-time connection fees assume a 1-inch meter). * = one-time water/sewer connection charges only; no per-sq-ft impact fee schedule sourced for that jurisdiction. = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.
Jacinto City: Industrial Impact Fees
Industrial development in Jacinto City pays no per-square-foot impact fees, but owes $1,085.00 in one-time water and sewer connection fees (rates sourced November 22, 2026).
For a 50,000 sq ft building, that comes to about $1,085.00. The calculator below adjusts to your exact square footage.
The largest line items are Water Connection Fee (City of Jacinto City) — 1" meter ($550.00 one-time), Sewer Tap Fee (City of Jacinto City) — over 8" sewer main ($500.00 one-time) and Water Tap Inspection Fee (City of Jacinto City) ($35.00 one-time).
Water and sewer connection fees assume a 1-inch meter; larger services pay more. See the meter-size tiers in the source schedules.
View the Full Jacinto City Impact Fee Schedule
- Water Connection Fee (City of Jacinto City) — 1" meter$550.00 one-timeCity of Jacinto CityJacinto City water connection charge for a 1 inch meter, up to 20 feet of service line, set in City Code Chapter 10 (1996). Meters larger than 2 inches and connections that need an open cut or bore under pavement are priced by the city at its cost. A $35 tap inspection fee also applies. The city charges no water impact fee.
- Water Tap Inspection Fee (City of Jacinto City)$35.00 one-timeCity of Jacinto CityJacinto City charges a $35 inspection fee for each water tap, in addition to the water connection charge.
- Sewer Tap Fee (City of Jacinto City) — over 8" sewer main$500.00 one-timeCity of Jacinto CityOne-time sewer tapping fee set by the size of the city sewer line tapped: $200 for a 6 inch line, $300 for an 8 inch line and $500 for a line over 8 inches (shown here, the highest of three rates). City of Jacinto City Code Chapter 10 Sec. 3.M (Ordinance 96-5). Street repair for a pavement cut is billed at actual cost. The city charges no wastewater impact fee.
- City Impact Fee (City of Jacinto City, Industrial)$0.00City of Jacinto CityThe City of Jacinto City charges no city impact fee on commercial, office or industrial development. Its water connection charges are listed with the water fees.
- County Impact Fee (Harris County, Jacinto City, Industrial)$0.00Harris CountyHarris County charges no county impact fee on development in Jacinto City; the Flood Control District's watershed fees apply only in two service areas of unincorporated northwest Harris County.
Where in Harris County Are You Building?
Each jurisdiction applies its own fee schedule. Pick yours. Totals shown are for a 50,000 sq ft building, including water/sewer fees (one-time connection fees assume a 1-inch meter). * = one-time water/sewer connection charges only; no per-sq-ft impact fee schedule sourced for that jurisdiction. = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.
Jacinto City: Office Impact Fees
Office development in Jacinto City pays no per-square-foot impact fees, but owes $1,085.00 in one-time water and sewer connection fees (rates sourced November 22, 2026).
For a 25,000 sq ft building, that comes to about $1,085.00. The calculator below adjusts to your exact square footage.
The largest line items are Water Connection Fee (City of Jacinto City) — 1" meter ($550.00 one-time), Sewer Tap Fee (City of Jacinto City) — over 8" sewer main ($500.00 one-time) and Water Tap Inspection Fee (City of Jacinto City) ($35.00 one-time).
Water and sewer connection fees assume a 1-inch meter; larger services pay more. See the meter-size tiers in the source schedules.
View the Full Jacinto City Impact Fee Schedule
- Water Connection Fee (City of Jacinto City) — 1" meter$550.00 one-timeCity of Jacinto CityJacinto City water connection charge for a 1 inch meter, up to 20 feet of service line, set in City Code Chapter 10 (1996). Meters larger than 2 inches and connections that need an open cut or bore under pavement are priced by the city at its cost. A $35 tap inspection fee also applies. The city charges no water impact fee.
- Water Tap Inspection Fee (City of Jacinto City)$35.00 one-timeCity of Jacinto CityJacinto City charges a $35 inspection fee for each water tap, in addition to the water connection charge.
- Sewer Tap Fee (City of Jacinto City) — over 8" sewer main$500.00 one-timeCity of Jacinto CityOne-time sewer tapping fee set by the size of the city sewer line tapped: $200 for a 6 inch line, $300 for an 8 inch line and $500 for a line over 8 inches (shown here, the highest of three rates). City of Jacinto City Code Chapter 10 Sec. 3.M (Ordinance 96-5). Street repair for a pavement cut is billed at actual cost. The city charges no wastewater impact fee.
- City Impact Fee (City of Jacinto City, Office)$0.00City of Jacinto CityThe City of Jacinto City charges no city impact fee on commercial, office or industrial development. Its water connection charges are listed with the water fees.
- County Impact Fee (Harris County, Jacinto City, Office)$0.00Harris CountyHarris County charges no county impact fee on development in Jacinto City; the Flood Control District's watershed fees apply only in two service areas of unincorporated northwest Harris County.
Where in Harris County Are You Building?
Each jurisdiction applies its own fee schedule. Pick yours. Totals shown are for a 25,000 sq ft building, including water/sewer fees (one-time connection fees assume a 1-inch meter). * = one-time water/sewer connection charges only; no per-sq-ft impact fee schedule sourced for that jurisdiction. = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.
Jacinto City Impact Fee Calculator
Estimate impact fees for your project. Set to single-family. Drop a pin or search an address for site-specific fees.
Location
Select a location to begin
Once you select an address or drop a pin, we'll identify the responsible city and county and generate a fee breakdown.
How Impact Fees Work in Texas
Texas cities, and certain special districts and authorities, assess impact fees under Chapter 395 of the Local Government Code and, with narrow exceptions, may charge one only by following it. A fee rests on adopted land use assumptions and a capital improvements plan, and imposing one takes the votes of two-thirds of the governing body's members.
Impact fees may fund only water supply, treatment and distribution; wastewater collection and treatment; storm water, drainage and flood control; and roadway facilities. Parks, schools, police and fire facilities are not on the chapter's list. The chapter does not treat park land dedication, or a payment in its place, as an impact fee, so a city can require that separately. The fee per service unit is capped at the plan's growth-related cost, less a required credit, divided by the projected service units. Counties generally cannot charge impact fees: the chapter gives that authority only to counties of 3.3 million or more people and the counties bordering them, and only for storm water, drainage and flood control. Since September 2025 a city also may not charge an impact fee where an office, retail or warehouse building at least five years old is converted to multifamily or mixed-use residential use (at least 65 percent of the building and of each usable floor), unless the land was already subject to an impact fee before the conversion's building permit was filed (Section 218.204).
For land platted after a fee is adopted, the fee is assessed no later than when the plat is recorded, which fixes the most that can be charged per service unit. Where water and wastewater capacity is available, it is generally collected when the building permit is issued, or when a water or wastewater meter connection is applied for on land outside city limits or where the entity charging the fee issues no building permits. A fee not spent as the chapter allows within 10 years of payment must generally be refunded with interest, and the land use assumptions and capital improvements plan are updated at least every five years unless the governing body formally determines that no update is needed.
A city may charge water, wastewater and drainage impact fees in its extraterritorial jurisdiction as well as inside its limits, but roadway impact fees stop at the city limits. Where a utility district or another provider supplies water or sewer instead of the city, its charges are separate from the city's, so the total can differ between a city, its neighbors and the unincorporated land around it.
If you're still asking what are impact fees, start with our guide to the definition, common categories, and legal basis.
Summary current as of November 2026. This is an editorial summary, not legal advice; see the official statute text and our terms of use.
Jacinto City Impact Fee FAQs
What are the total impact fees for a single-family home in Jacinto City, Texas?
A new single-family home in Jacinto City pays $875.00 per unit in combined impact fees (rates sourced November 22, 2026).
How much are commercial impact fees in Jacinto City?
Commercial development in Jacinto City pays no per-square-foot impact fees, but owes $1,085.00 in one-time water and sewer connection fees (assuming a 1-inch meter).
Does Jacinto City charge its own impact fees?
Yes. Jacinto City levies its own municipal impact or utility fees. Harris County does not currently add county-level impact fees inside Jacinto City. The schedule on this page shows every fee that applies to development in Jacinto City.
Can a Texas impact fee increase at any time?
No. Under Section 395.0515 of the Local Government Code, added in 2025, a city or district may not increase an impact fee for three years from the later of the date the fee was adopted or last increased, although it may phase in collection up to the adopted maximum over no more than ten years. An increase also needs an independent financial audit and a public hearing on its results first (Section 395.059), and the measure approving it cannot be adopted as an emergency measure (Section 395.057). Once a fee is assessed on a tract, it cannot be raised for that tract unless the number of service units increases (Section 395.017). Charges set by a separate water or sewer provider may follow different rules.
Fee amounts on this page are compiled from official published schedules and are provided for planning purposes only. Rates change, and project specifics (unit size, meter size, location within special districts) can alter what applies. Always verify current fees with the jurisdiction and utility before relying on them.
Compare unincorporated rates and every other city on the Harris County impact fees page.