Taylor Impact Fees by Project Type
Taylor: Single-Family Impact Fees
A new single-family home in Taylor pays $15,910.40 per unit in impact fees (rates sourced November 13, 2026). Every line item is levied at the municipal or utility level.
The largest line items are Roadway Impact Fee (City of Taylor) — Service Area 1, 4.38 veh-mi × $1,500/veh-mi ($6,570.00), Water Impact Fee (City of Taylor) — 5/8" × 3/4" meter ($2,919.00) and Wastewater Impact Fee (City of Taylor) — 5/8" × 3/4" meter ($2,799.00).
Some fees are tiered by unit size or building type; amounts reflect the representative tier noted in the schedule below.
View the Full Taylor Impact Fee Schedule
- Water Impact Fee (City of Taylor) — 5/8" × 3/4" meter$2,919.00City of TaylorCity of Taylor water impact fee of $2,919 per living unit equivalent under Ordinance 2023-13 (adopted April 27, 2023), charged by water meter size (5/8 x 3/4 inch 1 LUE, 3/4 inch 1.5, 1 inch 2.5, 1-1/2 inch 5, 2 inch 8). Assessed at final plat approval. The city is preparing an impact fee update in 2026.
- Water Tap Fee (City of Taylor) — 1" tap$1,654.80City of TaylorCity of Taylor water tap fee under the Fiscal Year 2027 fee schedule (Ordinance 2026-29, adopted September 24, 2026). The 1 inch tap is the smallest size listed; the water meter is charged separately.
- Water Meter Fee (City of Taylor) — 5/8" meter$375.00City of TaylorCity of Taylor standard residential 5/8 inch water meter fee under the Fiscal Year 2027 fee schedule, a pass-through of the meter cost that can change. Non-standard meters are priced individually.
- Wastewater Impact Fee (City of Taylor) — 5/8" × 3/4" meter$2,799.00City of TaylorCity of Taylor wastewater impact fee of $2,799 per living unit equivalent under Ordinance 2023-13 (adopted April 27, 2023), charged by water meter size (5/8 x 3/4 inch 1 LUE, 3/4 inch 1.5, 1 inch 2.5, 1-1/2 inch 5, 2 inch 8). Assessed at final plat approval. The city is preparing an impact fee update in 2026.
- Sewer Tap Fee (City of Taylor) — 4" tap$1,592.60City of TaylorCity of Taylor 4 inch sewer tap fee under the Fiscal Year 2027 fee schedule (Ordinance 2026-29). A 6 inch tap costs more.
- Roadway Impact Fee (City of Taylor) — Service Area 1, 4.38 veh-mi × $1,500/veh-mi$6,570.00City of TaylorCity of Taylor roadway impact fee under Ordinance 2023-20 (2023 update): $1,500 per vehicle-mile in Service Area 1 times 4.38 vehicle-miles for a single-family detached home. This is the highest of 3 service areas; Service Areas 2 and 3 collect $710 per vehicle-mile. Assessed at final plat and paid at building permit.
- County Impact Fee (Williamson County)$0.00Williamson CountyTexas counties cannot charge impact fees except certain counties of 3.3 million or more (and their neighbors) for drainage under Local Government Code Sec. 395.079. Williamson County does not qualify.
Where in Williamson County Are You Building?
Each jurisdiction applies its own fee schedule. Pick yours. = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.
Taylor: Multifamily Impact Fees
A new multifamily unit in Taylor pays $12,070.40 per unit in impact fees (rates sourced November 13, 2026). Every line item is levied at the municipal or utility level.
The largest line items are Water Impact Fee (City of Taylor, MF) — 1 LUE × $2,919/LUE ($2,919.00), Wastewater Impact Fee (City of Taylor, MF) — 1 LUE × $2,799/LUE ($2,799.00) and Roadway Impact Fee (City of Taylor, MF) — Service Area 1, 1.82 veh-mi × $1,500/veh-mi ($2,730.00).
Some fees are tiered by unit size or building type; amounts reflect the representative tier noted in the schedule below.
View the Full Taylor Impact Fee Schedule
- Water Impact Fee (City of Taylor, MF) — 1 LUE × $2,919/LUE$2,919.00City of TaylorCity of Taylor water impact fee of $2,919 per living unit equivalent under Ordinance 2023-13, charged by water meter size: shown per 5/8 x 3/4 inch meter (one LUE), the amount for a unit on its own meter. A building on one master meter pays by that meter's LUE count instead (1 inch 2.5, 2 inch 8 LUEs).
- Water Tap Fee (City of Taylor, MF) — 1" tap$1,654.80City of TaylorCity of Taylor water tap fee under the Fiscal Year 2027 fee schedule (Ordinance 2026-29), charged per tap, so a building on one tap pays it once. The 1 inch tap is the smallest size listed.
- Water Meter Fee (City of Taylor, MF) — 5/8" meter$375.00City of TaylorCity of Taylor standard 5/8 inch water meter fee under the Fiscal Year 2027 fee schedule, a pass-through of the meter cost; a building on one meter pays once, and larger meters are priced individually.
- Wastewater Impact Fee (City of Taylor, MF) — 1 LUE × $2,799/LUE$2,799.00City of TaylorCity of Taylor wastewater impact fee of $2,799 per living unit equivalent under Ordinance 2023-13, charged by water meter size: shown per 5/8 x 3/4 inch meter (one LUE), the amount for a unit on its own meter. A building on one master meter pays by that meter's LUE count instead.
- Sewer Tap Fee (City of Taylor, MF) — 4" tap$1,592.60City of TaylorCity of Taylor 4 inch sewer tap fee under the Fiscal Year 2027 fee schedule, charged per tap, so a building on one tap pays it once.
- Roadway Impact Fee (City of Taylor, MF) — Service Area 1, 1.82 veh-mi × $1,500/veh-mi$2,730.00City of TaylorCity of Taylor roadway impact fee under Ordinance 2023-20: $1,500 per vehicle-mile in Service Area 1 times 1.82 vehicle-miles per mid-rise multifamily unit. This is the highest of 3 service areas; Service Areas 2 and 3 collect $710 per vehicle-mile. Low-rise units are rated at 2.38 vehicle-miles and high-rise units at 1.49.
- County Impact Fee (Williamson County, MF)$0.00Williamson CountyTexas counties cannot charge impact fees except certain counties of 3.3 million or more (and their neighbors) for drainage under Local Government Code Sec. 395.079. Williamson County does not qualify.
Where in Williamson County Are You Building?
Each jurisdiction applies its own fee schedule. Pick yours. = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.
Taylor: Commercial Impact Fees
Commercial development in Taylor pays $11.56 per square foot in impact fees, plus $17,542.40 in one-time water and sewer connection fees (rates sourced November 13, 2026).
For a 50,000 sq ft building, that comes to about $595,792.40. The calculator below adjusts to your exact square footage.
The largest line items are Water Impact Fee (City of Taylor) — 1" meter ($7,297.00 one-time), Wastewater Impact Fee (City of Taylor) — 1" meter ($6,998.00 one-time) and Water Tap Fee (City of Taylor) — 1" tap ($1,654.80 one-time).
Water and sewer connection fees assume a 1-inch meter; larger services pay more. See the meter-size tiers in the source schedules.
View the Full Taylor Impact Fee Schedule
- Water Impact Fee (City of Taylor) — 1" meter$7,297.00 one-timeCity of TaylorCity of Taylor water impact fee for a 1 inch meter: $7,297 (Ordinance 2023-13). The fee scales by meter type and size, from $2,919 for a 5/8 by 3/4 inch meter to $963,252 for a 12 inch turbine meter. A water tap fee and the meter cost are charged separately. An update of the water and wastewater impact fees is under study in 2026.
- Water Tap Fee (City of Taylor) — 1" tap$1,654.80 one-timeCity of TaylorCity of Taylor water tap fee for a 1 inch tap: $1,654.80 (1-1/2 inch $2,205, 2 inch $2,388.75), FY 2027 fee schedule. The meter is billed separately at the city's cost.
- Wastewater Impact Fee (City of Taylor) — 1" meter$6,998.00 one-timeCity of TaylorCity of Taylor wastewater impact fee for a 1 inch meter: $6,998 (Ordinance 2023-13). The fee scales by meter type and size, from $2,799 for a 5/8 by 3/4 inch meter to $923,680 for a 12 inch turbine meter. A sewer tap fee is charged separately. An update of the water and wastewater impact fees is under study in 2026.
- Sewer Tap Fee (City of Taylor) — 4" tap$1,592.60 one-timeCity of TaylorCity of Taylor sewer tap fee for a 4 inch tap: $1,592.60 (6 inch $1,768.70), FY 2027 fee schedule.
- Roadway Impact Fee (City of Taylor, Commercial) — Service Area 1, 7.71 veh-mi × $1,500/veh-mi$11.56/sq ftCity of TaylorCity of Taylor roadway impact fee for a shopping center, $1,500 per vehicle-mile in Service Area 1 (the highest of 3 areas; Areas 2 and 3 charge $710) times 7.71 vehicle-miles per 1,000 sq ft. Assessed at final plat approval and paid before the building permit is issued. Impact fees are under review in 2026.
- County Impact Fee (Williamson County, Commercial)$0.00Williamson CountyTexas counties cannot levy impact fees under Local Government Code Chapter 395, so no county impact fee applies to development in the City of Taylor.
Where in Williamson County Are You Building?
Each jurisdiction applies its own fee schedule. Pick yours. Totals shown are for a 50,000 sq ft building, including water/sewer fees (one-time connection fees assume a 1-inch meter). * = one-time water/sewer connection charges only; no per-sq-ft impact fee schedule sourced for that jurisdiction. = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.
Taylor: Industrial Impact Fees
Industrial development in Taylor pays $5.85 per square foot in impact fees, plus $17,542.40 in one-time water and sewer connection fees (rates sourced November 13, 2026).
For a 50,000 sq ft building, that comes to about $310,042.40. The calculator below adjusts to your exact square footage.
The largest line items are Water Impact Fee (City of Taylor) — 1" meter ($7,297.00 one-time), Wastewater Impact Fee (City of Taylor) — 1" meter ($6,998.00 one-time) and Water Tap Fee (City of Taylor) — 1" tap ($1,654.80 one-time).
Water and sewer connection fees assume a 1-inch meter; larger services pay more. See the meter-size tiers in the source schedules.
View the Full Taylor Impact Fee Schedule
- Water Impact Fee (City of Taylor) — 1" meter$7,297.00 one-timeCity of TaylorCity of Taylor water impact fee for a 1 inch meter: $7,297 (Ordinance 2023-13). The fee scales by meter type and size, from $2,919 for a 5/8 by 3/4 inch meter to $963,252 for a 12 inch turbine meter. A water tap fee and the meter cost are charged separately. An update of the water and wastewater impact fees is under study in 2026.
- Water Tap Fee (City of Taylor) — 1" tap$1,654.80 one-timeCity of TaylorCity of Taylor water tap fee for a 1 inch tap: $1,654.80 (1-1/2 inch $2,205, 2 inch $2,388.75), FY 2027 fee schedule. The meter is billed separately at the city's cost.
- Wastewater Impact Fee (City of Taylor) — 1" meter$6,998.00 one-timeCity of TaylorCity of Taylor wastewater impact fee for a 1 inch meter: $6,998 (Ordinance 2023-13). The fee scales by meter type and size, from $2,799 for a 5/8 by 3/4 inch meter to $923,680 for a 12 inch turbine meter. A sewer tap fee is charged separately. An update of the water and wastewater impact fees is under study in 2026.
- Sewer Tap Fee (City of Taylor) — 4" tap$1,592.60 one-timeCity of TaylorCity of Taylor sewer tap fee for a 4 inch tap: $1,592.60 (6 inch $1,768.70), FY 2027 fee schedule.
- Roadway Impact Fee (City of Taylor, Industrial) — Service Area 1, 3.90 veh-mi × $1,500/veh-mi$5.85/sq ftCity of TaylorCity of Taylor roadway impact fee for general light industrial space, $1,500 per vehicle-mile in Service Area 1 (the highest of 3 areas; Areas 2 and 3 charge $710) times 3.90 vehicle-miles per 1,000 sq ft. Assessed at final plat approval and paid before the building permit is issued. Impact fees are under review in 2026.
- County Impact Fee (Williamson County, Industrial)$0.00Williamson CountyTexas counties cannot levy impact fees under Local Government Code Chapter 395, so no county impact fee applies to development in the City of Taylor.
Where in Williamson County Are You Building?
Each jurisdiction applies its own fee schedule. Pick yours. Totals shown are for a 50,000 sq ft building, including water/sewer fees (one-time connection fees assume a 1-inch meter). * = one-time water/sewer connection charges only; no per-sq-ft impact fee schedule sourced for that jurisdiction. = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.
Taylor: Office Impact Fees
Office development in Taylor pays $12.96 per square foot in impact fees, plus $17,542.40 in one-time water and sewer connection fees (rates sourced November 13, 2026).
For a 25,000 sq ft building, that comes to about $341,542.40. The calculator below adjusts to your exact square footage.
The largest line items are Water Impact Fee (City of Taylor) — 1" meter ($7,297.00 one-time), Wastewater Impact Fee (City of Taylor) — 1" meter ($6,998.00 one-time) and Water Tap Fee (City of Taylor) — 1" tap ($1,654.80 one-time).
Water and sewer connection fees assume a 1-inch meter; larger services pay more. See the meter-size tiers in the source schedules.
View the Full Taylor Impact Fee Schedule
- Water Impact Fee (City of Taylor) — 1" meter$7,297.00 one-timeCity of TaylorCity of Taylor water impact fee for a 1 inch meter: $7,297 (Ordinance 2023-13). The fee scales by meter type and size, from $2,919 for a 5/8 by 3/4 inch meter to $963,252 for a 12 inch turbine meter. A water tap fee and the meter cost are charged separately. An update of the water and wastewater impact fees is under study in 2026.
- Water Tap Fee (City of Taylor) — 1" tap$1,654.80 one-timeCity of TaylorCity of Taylor water tap fee for a 1 inch tap: $1,654.80 (1-1/2 inch $2,205, 2 inch $2,388.75), FY 2027 fee schedule. The meter is billed separately at the city's cost.
- Wastewater Impact Fee (City of Taylor) — 1" meter$6,998.00 one-timeCity of TaylorCity of Taylor wastewater impact fee for a 1 inch meter: $6,998 (Ordinance 2023-13). The fee scales by meter type and size, from $2,799 for a 5/8 by 3/4 inch meter to $923,680 for a 12 inch turbine meter. A sewer tap fee is charged separately. An update of the water and wastewater impact fees is under study in 2026.
- Sewer Tap Fee (City of Taylor) — 4" tap$1,592.60 one-timeCity of TaylorCity of Taylor sewer tap fee for a 4 inch tap: $1,592.60 (6 inch $1,768.70), FY 2027 fee schedule.
- Roadway Impact Fee (City of Taylor, Office) — Service Area 1, 8.64 veh-mi × $1,500/veh-mi$12.96/sq ftCity of TaylorCity of Taylor roadway impact fee for a general office building, $1,500 per vehicle-mile in Service Area 1 (the highest of 3 areas; Areas 2 and 3 charge $710) times 8.64 vehicle-miles per 1,000 sq ft. Assessed at final plat approval and paid before the building permit is issued. Impact fees are under review in 2026.
- County Impact Fee (Williamson County, Office)$0.00Williamson CountyTexas counties cannot levy impact fees under Local Government Code Chapter 395, so no county impact fee applies to development in the City of Taylor.
Where in Williamson County Are You Building?
Each jurisdiction applies its own fee schedule. Pick yours. Totals shown are for a 25,000 sq ft building, including water/sewer fees (one-time connection fees assume a 1-inch meter). * = one-time water/sewer connection charges only; no per-sq-ft impact fee schedule sourced for that jurisdiction. = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.
Taylor Impact Fee Calculator
Estimate impact fees for your project. Set to single-family. Drop a pin or search an address for site-specific fees.
Location
Select a location to begin
Once you select an address or drop a pin, we'll identify the responsible city and county and generate a fee breakdown.
How Impact Fees Work in Texas
Texas cities, and certain special districts and authorities, assess impact fees under Chapter 395 of the Local Government Code and, with narrow exceptions, may charge one only by following it. A fee rests on adopted land use assumptions and a capital improvements plan, and imposing one takes the votes of two-thirds of the governing body's members.
Impact fees may fund only water supply, treatment and distribution; wastewater collection and treatment; storm water, drainage and flood control; and roadway facilities. Parks, schools, police and fire facilities are not on the chapter's list. The chapter does not treat park land dedication, or a payment in its place, as an impact fee, so a city can require that separately. The fee per service unit is capped at the plan's growth-related cost, less a required credit, divided by the projected service units. Counties generally cannot charge impact fees: the chapter gives that authority only to counties of 3.3 million or more people and the counties bordering them, and only for storm water, drainage and flood control. Since September 2025 a city also may not charge an impact fee where an office, retail or warehouse building at least five years old is converted to multifamily or mixed-use residential use (at least 65 percent of the building and of each usable floor), unless the land was already subject to an impact fee before the conversion's building permit was filed (Section 218.204).
For land platted after a fee is adopted, the fee is assessed no later than when the plat is recorded, which fixes the most that can be charged per service unit. Where water and wastewater capacity is available, it is generally collected when the building permit is issued, or when a water or wastewater meter connection is applied for on land outside city limits or where the entity charging the fee issues no building permits. A fee not spent as the chapter allows within 10 years of payment must generally be refunded with interest, and the land use assumptions and capital improvements plan are updated at least every five years unless the governing body formally determines that no update is needed.
A city may charge water, wastewater and drainage impact fees in its extraterritorial jurisdiction as well as inside its limits, but roadway impact fees stop at the city limits. Where a utility district or another provider supplies water or sewer instead of the city, its charges are separate from the city's, so the total can differ between a city, its neighbors and the unincorporated land around it.
New to impact fees? Our plain-English guide explains what they cover, who pays them, and why they exist.
Summary current as of November 2026. This is an editorial summary, not legal advice; see the official statute text and our terms of use.
Taylor Impact Fee FAQs
What are the total impact fees for a single-family home in Taylor, Texas?
A new single-family home in Taylor pays $15,910.40 per unit in combined impact fees (rates sourced November 13, 2026).
How much are commercial impact fees in Taylor?
Commercial development in Taylor pays $11.56 per square foot in impact fees, plus $17,542.40 in one-time water and sewer connection fees (assuming a 1-inch meter), about $595,792.40 for a 50,000 sq ft building.
Does Taylor charge its own impact fees?
Yes. Taylor levies its own municipal impact or utility fees. Williamson County does not currently add county-level impact fees inside Taylor. The schedule on this page shows every fee that applies to development in Taylor.
Can a Texas impact fee increase at any time?
No. Under Section 395.0515 of the Local Government Code, added in 2025, a city or district may not increase an impact fee for three years from the later of the date the fee was adopted or last increased, although it may phase in collection up to the adopted maximum over no more than ten years. An increase also needs an independent financial audit and a public hearing on its results first (Section 395.059), and the measure approving it cannot be adopted as an emergency measure (Section 395.057). Once a fee is assessed on a tract, it cannot be raised for that tract unless the number of service units increases (Section 395.017). Charges set by a separate water or sewer provider may follow different rules.
Fee amounts on this page are compiled from official published schedules and are provided for planning purposes only. Rates change, and project specifics (unit size, meter size, location within special districts) can alter what applies. Always verify current fees with the jurisdiction and utility before relying on them.
Compare unincorporated rates and every other city on the Williamson County impact fees page.