West Melbourne Impact Fees by Project Type
West Melbourne: Single-Family Impact Fees
A new single-family home in West Melbourne pays $18,964.06 per unit in impact fees (rates sourced August 7, 2026). Of that, Brevard County-levied fees account for $9,838.06 and municipal or utility fees for $9,126.00.
The largest line items are Education Impact Fee (SFR) ($5,096.50), Transportation Impact Fee (SFR) ($4,353.00) and Water Connection Fee (West Melbourne) — West Melbourne component (3/4" meter) ($3,036.00).
Some fees are tiered by unit size or building type; amounts reflect the representative tier noted in the schedule below.
View the Full West Melbourne Impact Fee Schedule
- Water Connection Fee (West Melbourne) — West Melbourne component (3/4" meter)$3,036.00Part 2 of the West Melbourne single-family water connection fee: West Melbourne's own component of $3,036 for a standard 3/4-inch meter (City Code §58-110(b)), in addition to the $2,755 City of Melbourne component — total $5,791.
- Water Connection Fee (West Melbourne) — City of Melbourne component (1.0 ERC, 3/4" meter)$2,755.00City of West MelbournePart 1 of the West Melbourne single-family water connection fee: the City of Melbourne water impact-fee component, $2,755 (City Code §58-110(b)). West Melbourne adds a separate $3,036 component for a standard 3/4-inch meter; the two parts total $5,791.
- Water Meter Installation Fee (West Melbourne)$335.003/4-inch meterWest Melbourne charges a one-time water meter installation fee of $335 for a standard 3/4-inch residential meter (City Code §58-106), separate from the water connection fee.
- Sewer Connection Fee (West Melbourne)$3,000.00City of West MelbourneWest Melbourne charges a one-time sewer connection fee of $3,000 for a typical single-family home (standard 3/4-inch meter), paid before the building permit is issued.
- City Impact Fees (West Melbourne)$0.00City of West MelbourneThe City of West Melbourne does not levy a separate municipal impact fee; its only impact fees are the water and sewer connection charges (shown as separate records). The city has commissioned a water/wastewater impact-fee study ahead of a planned municipal water plant (expected around 2027).
- Education Impact Fee (SFR)$5,096.50Brevard County / Brevard Public SchoolsBrevard County educational facilities (school) impact fee, single-family detached: $5,096.50/unit. Rate effective January 2, 2017 and unchanged as of August 2026; collected by Brevard County before power release / certificate of occupancy under an interlocal agreement with the local government.
- Transportation Impact Fee (SFR)$4,353.00Brevard CountyBrevard County transportation impact fee, single-family detached: $4,353.00/unit. Rate effective January 2, 2017 and unchanged as of August 2026; collected by Brevard County before power release / certificate of occupancy under an interlocal agreement with the local government.
- Solid Waste Impact Fee (SFR)$160.00Brevard CountyBrevard County solid waste impact fee, single-family detached: $160.00/unit. Rate effective January 2, 2017 and unchanged as of August 2026; collected by Brevard County before power release / certificate of occupancy under an interlocal agreement with the local government.
- Correctional Facility Impact Fee (SFR)$71.99Brevard CountyBrevard County correctional facilities impact fee, single-family detached: $71.99/unit. Rate effective January 2, 2017 and unchanged as of August 2026; collected by Brevard County before power release / certificate of occupancy under an interlocal agreement with the local government.
- Library Impact Fee (SFR)$63.84Brevard CountyBrevard County library facilities impact fee, single-family detached: $63.84/unit. Rate effective January 2, 2017 and unchanged as of August 2026; collected by Brevard County before power release / certificate of occupancy under an interlocal agreement with the local government.
- Fire/Rescue Impact Fee (SFR)$54.08Brevard CountyBrevard County fire/rescue impact fee, single-family detached: $54.08/unit. Rate effective January 2, 2017 and unchanged as of August 2026; collected by Brevard County before power release / certificate of occupancy under an interlocal agreement with the local government.
- EMS Impact Fee (SFR)$38.65Brevard CountyBrevard County EMS (emergency medical services) impact fee, single-family detached: $38.65/unit. Rate effective January 2, 2017 and unchanged as of August 2026; collected by Brevard County before power release / certificate of occupancy under an interlocal agreement with the local government.
Where in Brevard County Are You Building?
Each jurisdiction applies its own fee schedule. Pick yours. = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.
West Melbourne: Multifamily Impact Fees
A new multifamily unit in West Melbourne pays $9,768.80 per unit in impact fees (rates sourced August 7, 2026). Of that, Brevard County-levied fees account for $4,573.80 and municipal or utility fees for $5,195.00.
The largest line items are County Transportation Impact Fee (MF) ($2,381.00), Water Connection Fee (West Melbourne, MF) — City of Melbourne component (0.833 ERC, master-metered) ($2,295.00) and County Education Impact Fee (MF) ($1,940.50).
Some fees are tiered by unit size or building type; amounts reflect the representative tier noted in the schedule below.
View the Full West Melbourne Impact Fee Schedule
- Water Connection Fee (West Melbourne, MF) — City of Melbourne component (0.833 ERC, master-metered)$2,295.00City of MelbournePart 1 of the West Melbourne multifamily water connection fee: the City of Melbourne water impact-fee component, $2,295 for a master-metered unit (City Code §58-110(b)). West Melbourne adds a separate $1,218-per-unit component; the two parts total $3,513.
- Water Connection Fee (West Melbourne, MF) — West Melbourne component ($1,218/unit)$1,218.00Part 2 of the West Melbourne multifamily water connection fee: West Melbourne's own component of $1,218 per unit (City Code §58-110(c)), in addition to the $2,295 City of Melbourne component — total $3,513 per unit.
- Water Meter Installation Fee (West Melbourne, MF)$465.00West Melbourne charges a one-time water meter installation fee of $465 per multifamily unit (City Code §58-106), separate from the water and sewer connection fees.
- Sewer Connection Fee (West Melbourne, MF)$1,217.00City of West MelbourneWest Melbourne charges a one-time sewer connection fee of $1,217 per dwelling unit for multifamily projects, regardless of meter size, paid before the building permit is issued.
- City Impact Fees (West Melbourne, MF)$0.00City of West MelbourneThe City of West Melbourne does not levy a separate municipal impact fee; its only impact fees are the water and sewer connection charges (shown as separate records). The city has commissioned a water/wastewater impact-fee study ahead of a planned municipal water plant (expected around 2027).
- County Transportation Impact Fee (MF)$2,381.00Apartment, 3+ storiesBrevard CountyBrevard County transportation impact fee, per apartment/multifamily unit: $2,381.00/unit for a building of 3 or more stories. Rate effective January 2, 2017 and unchanged as of August 2026; collected by Brevard County before power release / certificate of occupancy under an interlocal agreement with the local government.
- County Education Impact Fee (MF)$1,940.50Apartment, 3+ storiesBrevard County / Brevard Public SchoolsBrevard County educational facilities (school) impact fee, per apartment/multifamily unit: $1,940.50/unit for a building of 3 or more stories. Rate effective January 2, 2017 and unchanged as of August 2026; collected by Brevard County before power release / certificate of occupancy under an interlocal agreement with the local government.
- County Solid Waste Impact Fee (MF)$120.00Apartment, 3+ storiesBrevard CountyBrevard County solid waste impact fee, per apartment/multifamily unit: $120.00/unit for a building of 3 or more stories. Rate effective January 2, 2017 and unchanged as of August 2026; collected by Brevard County before power release / certificate of occupancy under an interlocal agreement with the local government.
- County Correctional Facility Impact Fee (MF)$41.25Apartment, 3+ storiesBrevard CountyBrevard County correctional facilities impact fee, per apartment/multifamily unit: $41.25/unit for a building of 3 or more stories. Rate effective January 2, 2017 and unchanged as of August 2026; collected by Brevard County before power release / certificate of occupancy under an interlocal agreement with the local government.
- County Library Impact Fee (MF)$37.91Apartment, 3+ storiesBrevard CountyBrevard County library facilities impact fee, per apartment/multifamily unit: $37.91/unit for a building of 3 or more stories. Rate effective January 2, 2017 and unchanged as of August 2026; collected by Brevard County before power release / certificate of occupancy under an interlocal agreement with the local government.
- County Fire/Rescue Impact Fee (MF)$30.99Apartment, 3+ storiesBrevard CountyBrevard County fire/rescue impact fee, per apartment/multifamily unit: $30.99/unit for a building of 3 or more stories. Rate effective January 2, 2017 and unchanged as of August 2026; collected by Brevard County before power release / certificate of occupancy under an interlocal agreement with the local government.
- County EMS Impact Fee (MF)$22.15Apartment, 3+ storiesBrevard CountyBrevard County EMS (emergency medical services) impact fee, per apartment/multifamily unit: $22.15/unit for a building of 3 or more stories. Rate effective January 2, 2017 and unchanged as of August 2026; collected by Brevard County before power release / certificate of occupancy under an interlocal agreement with the local government.
Where in Brevard County Are You Building?
Each jurisdiction applies its own fee schedule. Pick yours. = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.
West Melbourne: Commercial Impact Fees
Commercial development in West Melbourne pays $6.76 per square foot in impact fees, plus $17,841.00 in one-time water and sewer connection fees (rates sourced August 7, 2026).
For a 50,000 sq ft building, that comes to at least $355,996.50. The calculator below adjusts to your exact square footage.
The largest line items are Water Connection Fee (City of West Melbourne) — 1" meter = $2,755 Melbourne minimum + $7,590 West Melbourne ($10,345.00 one-time), Sewer Connection Fee (City of West Melbourne) — 1" meter ($7,496.00 one-time) and Transportation Impact Fee (Brevard County, Commercial) ($6.40/sq ft).
Water and sewer connection fees assume a 1-inch meter; larger services pay more. See the meter-size tiers in the source schedules.
Solid Waste Impact Fee (Brevard County, Commercial) is set by the county and has no published standard rate. Contact the levying jurisdiction or utility to verify before budgeting; it is not included as a dollar figure here.
View the Full West Melbourne Impact Fee Schedule
- Water Connection Fee (City of West Melbourne) — 1" meter = $2,755 Melbourne minimum + $7,590 West Melbourne$10,345.00 one-timeCity of West Melbourne / City of MelbourneThe West Melbourne water connection fee (Ord. No. 2024-09, effective March 20, 2024) is the sum of two parts: (1) the City of Melbourne component — P.E.-certified GPD × $11.479/gal, minimum $2,755 (Melbourne Ord. No. 2025-59, adopted December 9, 2025) — plus (2) West Melbourne's own meter-size amount ($7,590 for a 1" meter), for the $10,345 shown here. That figure uses the Melbourne minimum, so a project certified above roughly 240 GPD pays more. Melbourne supplies the water under a 2013 interlocal agreement; meters larger than 4 inches are negotiated with the city. No inside/outside-city differential.
- Sewer Connection Fee (City of West Melbourne) — 1" meter$7,496.00 one-timeCity of West MelbourneThe West Melbourne sewer connection fee (Ord. No. 2018-13) is $7,496 for a 1" meter (by meter size). This is West Melbourne's own fee, not an add-on to a Melbourne charge; wastewater treatment is provided under an interlocal agreement with the City of Melbourne. Meters larger than 4 inches are negotiated with the city, and multifamily is $1,217 per unit regardless of meter size. No inside/outside-city differential.
- City Impact Fees (West Melbourne, Commercial) — none$0.00City of West MelbourneThe City of West Melbourne levies no municipal development impact fees; Brevard County overlay impact fees still apply, including the county Fire Rescue impact fee, which is collected in West Melbourne.
- Transportation Impact Fee (Brevard County, Commercial)$6.40/sq ftBrevard CountyBrevard County transportation impact fee — $6,396 per 1,000 sq ft of gross floor area for retail of 50,000–99,999 sq ft (2007 county commercial schedule, adopted under Ord. No. 06-044; still the current adopted rate). Assessed and collected by Brevard County across the county under interlocal agreement, except in Palm Bay and Melbourne, which levy their own transportation impact fees instead.
- Correctional Facilities Impact Fee (Brevard County, Commercial)$0.16/sq ftBrevard CountyBrevard County correctional facilities impact fee — $160.44 per 1,000 sq ft of gross floor area for retail of 50,000–99,999 sq ft (2007 county commercial schedule; still the current adopted rate). Collected countywide across all municipalities and the unincorporated area.
- Fire Rescue Impact Fee (Brevard County, Commercial)$0.12/sq ftBrevard CountyBrevard County fire rescue impact fee — $120.54 per 1,000 sq ft of gross floor area for retail of 50,000–99,999 sq ft (2007 county commercial schedule; still the current adopted rate). This county fire fee is collected only in unincorporated Brevard, West Melbourne, Palm Shores, Grant-Valkaria, and Melbourne Village; the other cities run their own fire departments and the county fee does not apply there.
- EMS Impact Fee (Brevard County, Commercial)$0.09/sq ftBrevard CountyBrevard County EMS impact fee — $86.13 per 1,000 sq ft of gross floor area for retail of 50,000–99,999 sq ft (2007 county commercial schedule; still the current adopted rate). Collected countywide across all municipalities and the unincorporated area.
- Solid Waste Impact Fee (Brevard County, Commercial)Requires confirmationBrevard CountyBrevard County's solid waste impact fee is not a flat per-sq-ft rate — it is set per project from estimated annual waste volume (× $4.06/cu yd non-compacted or $15.30/cu yd compacted), subject to a minimum of one billing unit ($467.20). Retail at any size, office over 20,000 sq ft, warehouse over 15,000 sq ft, and restaurants over 9,000 sq ft each require an individual volume determination. It applies in both incorporated and unincorporated Brevard.
Where in Brevard County Are You Building?
Each jurisdiction applies its own fee schedule. Pick yours. Totals shown are for a 50,000 sq ft building, including one-time water/sewer fees (assuming a 1-inch meter). = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.
West Melbourne: Industrial Impact Fees
Industrial development in West Melbourne pays no per-square-foot impact fees, but owes $17,841.00 in one-time water and sewer connection fees (rates sourced August 7, 2026).
For a 50,000 sq ft building, that comes to at least $17,841.00. The calculator below adjusts to your exact square footage.
The largest line items are Water Connection Fee (City of West Melbourne) — 1" meter = $2,755 Melbourne minimum + $7,590 West Melbourne ($10,345.00 one-time) and Sewer Connection Fee (City of West Melbourne) — 1" meter ($7,496.00 one-time).
Water and sewer connection fees assume a 1-inch meter; larger services pay more. See the meter-size tiers in the source schedules.
Solid Waste Impact Fee (Brevard County, Industrial) is set by the county and has no published standard rate. Contact the levying jurisdiction or utility to verify before budgeting; it is not included as a dollar figure here.
View the Full West Melbourne Impact Fee Schedule
- Water Connection Fee (City of West Melbourne) — 1" meter = $2,755 Melbourne minimum + $7,590 West Melbourne$10,345.00 one-timeCity of West Melbourne / City of MelbourneThe West Melbourne water connection fee (Ord. No. 2024-09, effective March 20, 2024) is the sum of two parts: (1) the City of Melbourne component — P.E.-certified GPD × $11.479/gal, minimum $2,755 (Melbourne Ord. No. 2025-59, adopted December 9, 2025) — plus (2) West Melbourne's own meter-size amount ($7,590 for a 1" meter), for the $10,345 shown here. That figure uses the Melbourne minimum, so a project certified above roughly 240 GPD pays more. Melbourne supplies the water under a 2013 interlocal agreement; meters larger than 4 inches are negotiated with the city. No inside/outside-city differential.
- Sewer Connection Fee (City of West Melbourne) — 1" meter$7,496.00 one-timeCity of West MelbourneThe West Melbourne sewer connection fee (Ord. No. 2018-13) is $7,496 for a 1" meter (by meter size). This is West Melbourne's own fee, not an add-on to a Melbourne charge; wastewater treatment is provided under an interlocal agreement with the City of Melbourne. Meters larger than 4 inches are negotiated with the city, and multifamily is $1,217 per unit regardless of meter size. No inside/outside-city differential.
- City Impact Fees (West Melbourne, Industrial) — none$0.00City of West MelbourneThe City of West Melbourne levies no municipal development impact fees; Brevard County overlay impact fees still apply, including the county Fire Rescue impact fee, which is collected in West Melbourne.
- County Impact Fees (Brevard County, Industrial) — exempt$0.00Brevard CountyBrevard County exempts all industrial land uses (NAICS sectors 21, 22, 23, 31–33, 48–49, and subsector 562 — covering general industrial, manufacturing, warehouse, and mini-warehouse) from its Transportation, Fire Rescue, EMS, and Correctional impact fees, so the county nonresidential impact fee for industrial development is $0. Any applicable city impact fees still apply.
- Solid Waste Impact Fee (Brevard County, Industrial)Requires confirmationBrevard CountyBrevard County's solid waste impact fee is not a flat per-sq-ft rate — it is set per project from estimated annual waste volume (× $4.06/cu yd non-compacted or $15.30/cu yd compacted), subject to a minimum of one billing unit ($467.20). Retail at any size, office over 20,000 sq ft, warehouse over 15,000 sq ft, and restaurants over 9,000 sq ft each require an individual volume determination. It applies in both incorporated and unincorporated Brevard.
Where in Brevard County Are You Building?
Each jurisdiction applies its own fee schedule. Pick yours. Totals shown are for a 50,000 sq ft building, including one-time water/sewer fees (assuming a 1-inch meter). * = one-time water/sewer connection charges only; no per-sq-ft impact fee schedule sourced for that jurisdiction. = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.
West Melbourne: Office Impact Fees
Office development in West Melbourne pays $5.14 per square foot in impact fees, plus $17,841.00 in one-time water and sewer connection fees (rates sourced August 7, 2026).
For a 25,000 sq ft building, that comes to at least $146,245.75. The calculator below adjusts to your exact square footage.
The largest line items are Water Connection Fee (City of West Melbourne) — 1" meter = $2,755 Melbourne minimum + $7,590 West Melbourne ($10,345.00 one-time), Sewer Connection Fee (City of West Melbourne) — 1" meter ($7,496.00 one-time) and Transportation Impact Fee (Brevard County, Office) ($5.06/sq ft).
Water and sewer connection fees assume a 1-inch meter; larger services pay more. See the meter-size tiers in the source schedules.
Solid Waste Impact Fee (Brevard County, Office) is set by the county and has no published standard rate. Contact the levying jurisdiction or utility to verify before budgeting; it is not included as a dollar figure here.
View the Full West Melbourne Impact Fee Schedule
- Water Connection Fee (City of West Melbourne) — 1" meter = $2,755 Melbourne minimum + $7,590 West Melbourne$10,345.00 one-timeCity of West Melbourne / City of MelbourneThe West Melbourne water connection fee (Ord. No. 2024-09, effective March 20, 2024) is the sum of two parts: (1) the City of Melbourne component — P.E.-certified GPD × $11.479/gal, minimum $2,755 (Melbourne Ord. No. 2025-59, adopted December 9, 2025) — plus (2) West Melbourne's own meter-size amount ($7,590 for a 1" meter), for the $10,345 shown here. That figure uses the Melbourne minimum, so a project certified above roughly 240 GPD pays more. Melbourne supplies the water under a 2013 interlocal agreement; meters larger than 4 inches are negotiated with the city. No inside/outside-city differential.
- Sewer Connection Fee (City of West Melbourne) — 1" meter$7,496.00 one-timeCity of West MelbourneThe West Melbourne sewer connection fee (Ord. No. 2018-13) is $7,496 for a 1" meter (by meter size). This is West Melbourne's own fee, not an add-on to a Melbourne charge; wastewater treatment is provided under an interlocal agreement with the City of Melbourne. Meters larger than 4 inches are negotiated with the city, and multifamily is $1,217 per unit regardless of meter size. No inside/outside-city differential.
- City Impact Fees (West Melbourne, Office) — none$0.00City of West MelbourneThe City of West Melbourne levies no municipal development impact fees; Brevard County overlay impact fees still apply, including the county Fire Rescue impact fee, which is collected in West Melbourne.
- Transportation Impact Fee (Brevard County, Office)$5.06/sq ftBrevard CountyBrevard County transportation impact fee — $5,058 per 1,000 sq ft of gross floor area for office of 10,000 sq ft and over (2007 county commercial schedule, adopted under Ord. No. 06-044; still the current adopted rate). Assessed and collected by Brevard County across the county under interlocal agreement, except in Palm Bay and Melbourne, which levy their own transportation impact fees instead.
- Correctional Facilities Impact Fee (Brevard County, Office)$0.03/sq ftBrevard CountyBrevard County correctional facilities impact fee — $34.17 per 1,000 sq ft of gross floor area for office of 10,000 sq ft and over (2007 county commercial schedule; still the current adopted rate). Collected countywide across all municipalities and the unincorporated area.
- Fire Rescue Impact Fee (Brevard County, Office)$0.03/sq ftBrevard CountyBrevard County fire rescue impact fee — $25.67 per 1,000 sq ft of gross floor area for office of 10,000 sq ft and over (2007 county commercial schedule; still the current adopted rate). This county fire fee is collected only in unincorporated Brevard, West Melbourne, Palm Shores, Grant-Valkaria, and Melbourne Village; the other cities run their own fire departments and the county fee does not apply there.
- EMS Impact Fee (Brevard County, Office)$0.02/sq ftBrevard CountyBrevard County EMS impact fee — $18.35 per 1,000 sq ft of gross floor area for office of 10,000 sq ft and over (2007 county commercial schedule; still the current adopted rate). Collected countywide across all municipalities and the unincorporated area.
- Solid Waste Impact Fee (Brevard County, Office)Requires confirmationBrevard CountyBrevard County's solid waste impact fee is not a flat per-sq-ft rate — it is set per project from estimated annual waste volume (× $4.06/cu yd non-compacted or $15.30/cu yd compacted), subject to a minimum of one billing unit ($467.20). Retail at any size, office over 20,000 sq ft, warehouse over 15,000 sq ft, and restaurants over 9,000 sq ft each require an individual volume determination. It applies in both incorporated and unincorporated Brevard.
Where in Brevard County Are You Building?
Each jurisdiction applies its own fee schedule. Pick yours. Totals shown are for a 25,000 sq ft building, including one-time water/sewer fees (assuming a 1-inch meter). = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.
West Melbourne Impact Fee Calculator
Estimate impact fees for your project. Set to single-family. Drop a pin or search an address for site-specific fees.
Location
Select a location to begin
Once you select an address or drop a pin, we'll identify the responsible city and county and generate a fee breakdown.
How Impact Fees Work in Florida
Florida impact fees are one-time charges on new development, governed by Section 163.31801, Florida Statutes (the Florida Impact Fee Act). The statute requires fees to be based on the most recent and localized data, spent on the infrastructure category they were collected for, and adopted by ordinance.
Since a 2021 amendment (Ch. 2021-63, Laws of Florida), the law also limits how fast fees can rise: increases up to 25% phase in over two years, increases of 25–50% phase in over four years, and increases above 50% are allowed only with a demonstrated extraordinary-circumstances study and at least a two-thirds vote of the governing body.
Counties and cities can both levy impact fees. Inside an incorporated city, a project typically pays the county's countywide fees plus any municipal fees the city has adopted, which is why totals differ between a city and the unincorporated county around it.
Brush up on impact fee basics before you budget your next project.
Summary current as of September 2026. This is an editorial summary, not legal advice; see the official statute text and our terms of use.
West Melbourne Impact Fee FAQs
What are the total impact fees for a single-family home in West Melbourne, Florida?
A new single-family home in West Melbourne pays $18,964.06 per unit in combined impact fees (rates sourced August 7, 2026).
How much are commercial impact fees in West Melbourne?
Commercial development in West Melbourne pays $6.76 per square foot in impact fees, plus $17,841.00 in one-time water and sewer connection fees (assuming a 1-inch meter), at least $355,996.50 for a 50,000 sq ft building. One additional fee has no published standard amount and is not included, so the full cost may be higher; verify before budgeting.
Does West Melbourne charge its own impact fees?
Yes. West Melbourne levies its own municipal impact or utility fees, and county-levied fees also apply inside city limits. The schedule on this page shows every fee that applies to development in West Melbourne, with the combined total.
Can Florida impact fees increase at any time?
No. Section 163.31801, Florida Statutes limits increases to 50% at most, phased in over two to four years, unless the local government makes extraordinary-circumstances findings and approves the increase by at least a two-thirds vote.
Fee amounts on this page are compiled from official published schedules and are provided for planning purposes only. Rates change, and project specifics (unit size, meter size, location within special districts) can alter what applies. Always verify current fees with the jurisdiction and utility before relying on them.
Compare unincorporated rates and every other city on the Brevard County impact fees page.