Skip to content
IMPACTFEES.ORG

Lady Lake, Florida Impact Fees

Lady Lake applies its own fee schedule: municipal fees plus the Lake County-levied fees that apply inside city limits. Combined, a new single-family home pays $25,747.00 per unit (rates sourced ). The full breakdown is below.

Lady Lake Impact Fees by Project Type

Lady Lake: Single-Family Impact Fees

A new single-family home in Lady Lake pays $25,747.00 per unit in impact fees (rates sourced August 4, 2026). Of that, Lake County-levied fees account for $16,337.00 and municipal or utility fees for $9,410.00.

The largest line items are School Impact Fee (Lake County, SFR) ($11,247.00), Roads Impact Fee (Lake County, SFR) ($3,928.00) and Sewer Connection/Capacity Fee (Town of Lady Lake, SFR) ($3,322.00).

Some fees are tiered by unit size or building type; amounts reflect the representative tier noted in the schedule below.

View the Full Lady Lake Impact Fee Schedule
Water$1,435.00
Sewer$3,322.00
  • Sewer Connection/Capacity Fee (Town of Lady Lake, SFR)
    Town of Lady Lake
    The Town of Lady Lake charges a one-time wastewater (sewer) impact fee of $3,322 for each new single-family home connecting to town sewer. A small reclaimed-water fee of $152 may also apply where reclaimed service is provided.
    $3,322.00
City$4,653.00
County$16,337.00
  • School Impact Fee (Lake County, SFR)
    801+ sq ft
    Lake County
    Lake County school impact fee (Ord. 2023-39). The $11,247 rate applies to a single-family detached home larger than 800 sq ft; homes 800 sq ft or smaller pay $6,897. Rate in effect Jan 2–Sep 30, 2026; the county re-adopts its residential impact-fee schedule annually, with the next version effective Oct 1, 2026.
    $11,247.00
  • Roads Impact Fee (Lake County, SFR)
    1,500–2,499 sq ft
    Lake County
    Lake County road impact fee — Central & North Central Transportation Benefit District rate. The $3,928 rate is for a single-family detached home of 1,500–2,499 sq ft (other sizes in this district: ≤800 $1,441, 801–1,499 $3,601, 2,500+ $4,459). The Northeast/Wekiva district charges more ($4,356) and the rural West and South districts less. In effect Jan 2–Sep 30, 2026; the county re-adopts its road impact-fee schedule annually, with the next version effective Oct 1, 2026.
    $3,928.00
  • Fire Impact Fee (Lake County, SFR)
    1,500+ sq ft
    Lake County
    Lake County fire impact fee (Ord. 2023-53). The $536 rate applies to a single-family detached home of 1,500 sq ft or larger; smaller homes pay ≤800 sq ft $276 and 801–1,499 sq ft $334. Rate in effect Jan 2–Sep 30, 2026; the county re-adopts its residential impact-fee schedule annually, with the next version effective Oct 1, 2026.
    $536.00
  • Parks Impact Fee (Lake County, SFR)
    1,500–2,499 sq ft
    Lake County
    Lake County parks impact fee (Ord. 2023-52). The $263 rate applies to a single-family detached home of 1,500–2,499 sq ft; other sizes pay ≤800 sq ft $136, 801–1,499 sq ft $165, and 2,500+ sq ft $305. Rate in effect Jan 2–Sep 30, 2026; the county re-adopts its residential impact-fee schedule annually, with the next version effective Oct 1, 2026.
    $263.00
  • Library Impact Fee (Lake County, SFR)
    801+ sq ft
    Lake County
    Lake County library impact fee (Ord. 2023-51). The $263 rate applies to a single-family detached home larger than 800 sq ft; homes 800 sq ft or smaller pay $217. Rate in effect Jan 2–Sep 30, 2026; Lake County re-adopts its residential impact-fee schedule annually, with the next version effective Oct 1, 2026.
    $263.00
  • Administrative Impact Fee (Lake County, SFR)
    Lake County
    Lake County administrative impact fee — a flat $100 charge applied to county impact-fee assessments (F.S. 163.31801). Same amount regardless of home size. Rate in effect under Lake County's residential impact-fee schedule for Jan 2–Sep 30, 2026; the county re-adopts the schedule annually, with the next version effective Oct 1, 2026.
    $100.00
Total (Lady Lake): $25,747.00
Sources last checked Official fee schedules:Town of Lady Lake Lake County

Lady Lake: Multifamily Impact Fees

A new multifamily unit in Lady Lake pays $21,247.00 per unit in impact fees (rates sourced August 4, 2026). Of that, Lake County-levied fees account for $12,609.00 and municipal or utility fees for $8,638.00.

The largest line items are School Impact Fee - Multifamily 801+ sf ($9,543.00), Park Impact Fee (Town of Lady Lake, MF) ($2,332.00) and Roads Impact Fee - Multifamily 801+ sf, 4+ Stories ($2,216.00).

Water Connection/Capacity Fee (Town of Lady Lake, MF) and Sewer Connection/Capacity Fee (Town of Lady Lake, MF) are shown at the last published amount but have not been confirmed with the jurisdiction; they are included in the totals here. Verify before budgeting.

Some fees are tiered by unit size or building type; amounts reflect the representative tier noted in the schedule below.

View the Full Lady Lake Impact Fee Schedule
Water$1,435.00
  • Water Connection/Capacity Fee (Town of Lady Lake, MF)
    Town of Lady Lake
    Town of Lady Lake water impact fee, $1,435 per ERU under Code Sec. 13-59 Exhibit A (Ordinance 2020-03). The multifamily per-unit ERU factor is not stated in the adopted schedule.
    $1,435.00Requires confirmation
Sewer$3,322.00
  • Sewer Connection/Capacity Fee (Town of Lady Lake, MF)
    Town of Lady Lake
    Town of Lady Lake wastewater impact fee, $3,322 per ERU under Code Sec. 13-59 Exhibit A (Ordinance 2020-03). The multifamily per-unit ERU factor is not stated in the adopted schedule.
    $3,322.00Requires confirmation
City$3,881.00
County$12,609.00
  • School Impact Fee - Multifamily 801+ sf
    Lake County
    Lake County school impact fee assessed on multifamily development in Lady Lake, tiered by unit size (801+ sf); the rate is the same regardless of building height. Current county schedule effective January 2, 2026 through September 30, 2026; a scheduled increase takes effect October 1, 2026.
    $9,543.00
  • Roads Impact Fee - Multifamily 801+ sf, 4+ Stories
    Lake County
    Lake County road (mobility) impact fee assessed on multifamily development in Lady Lake, tiered by unit size (801+ sf), building height (4+ Stories), and by geographic road district (the Central road district). Current county schedule effective January 2, 2026 through September 30, 2026; a scheduled increase takes effect October 1, 2026.
    $2,216.00
  • Fire Impact Fee - Multifamily 801+ sf
    Lake County
    Lake County fire rescue impact fee assessed on multifamily development in Lady Lake, tiered by unit size (801+ sf). Current county schedule effective January 2, 2026 through September 30, 2026; a scheduled increase takes effect October 1, 2026.
    $336.00
  • Parks Impact Fee - Multifamily 801+ sf
    Lake County
    Lake County parks and recreation impact fee assessed on multifamily development in Lady Lake, tiered by unit size (801+ sf). Current county schedule effective January 2, 2026 through September 30, 2026; a scheduled increase takes effect October 1, 2026.
    $213.00
  • Library Impact Fee - Multifamily (per unit)
    Lake County
    Lake County library impact fee, a flat per-unit charge on multifamily development in Lady Lake. Current county schedule effective January 2, 2026 through September 30, 2026; a scheduled increase takes effect October 1, 2026.
    $201.00
  • Administrative Fee - Multifamily (all sizes/stories)
    Lake County
    Lake County impact fee administrative charge (Fla. Stat. 163.31801), a flat per-unit charge applied to all residential development in Lady Lake. Current county schedule effective January 2, 2026 through September 30, 2026; a scheduled increase takes effect October 1, 2026.
    $100.00
Total (Lady Lake): $21,247.00
Sources last checked Official fee schedules:Town of Lady Lake Lake County
Amounts flagged "Requires confirmation" are the last published figures, included in the totals. Confirm them with the jurisdiction or utility before budgeting.

Lady Lake: Commercial Impact Fees

Commercial development in Lady Lake pays $5.06 per square foot in impact fees (rates sourced August 4, 2026).

For a 50,000 sq ft building, that comes to at least $253,100.00. The calculator below adjusts to your exact square footage.

The largest line items are County Transportation Impact Fee (Lake County, Commercial) ($4.20/sq ft) and County Fire Rescue Impact Fee (Lake County, Commercial) ($0.86/sq ft).

Sewer Impact Fee (Town of Lady Lake) — 1 ERU (250 gpd) and Water Impact Fee (Town of Lady Lake) — 1 ERU (250 gpd) are set by the utility and not published online. Contact the levying jurisdiction or utility to verify before budgeting; they are not included as dollar figures here.

View the Full Lady Lake Impact Fee Schedule
Water$0.00
Sewer$0.00
Total (Lady Lake): $5.06/sq ft (≈ $253,100.00 at 50,000 sq ft)
Sources last checked Official fee schedules:Town of Lady Lake Lake County
Fees flagged "Requires confirmation" have no confirmed published amount. Confirm them with the jurisdiction or utility before budgeting.

Where in Lake County Are You Building?

Each jurisdiction applies its own fee schedule. Pick yours. Totals shown are for a 50,000 sq ft building, including one-time water/sewer fees (assuming a 1-inch meter). = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.

Lady Lake: Industrial Impact Fees

Industrial development in Lady Lake pays $1.80 per square foot in impact fees (rates sourced August 4, 2026).

For a 50,000 sq ft building, that comes to at least $90,050.00. The calculator below adjusts to your exact square footage.

The largest line items are County Transportation Impact Fee (Lake County, Industrial) ($1.64/sq ft) and County Fire Rescue Impact Fee (Lake County, Industrial) ($0.16/sq ft).

Sewer Impact Fee (Town of Lady Lake) — 1 ERU (250 gpd) and Water Impact Fee (Town of Lady Lake) — 1 ERU (250 gpd) are set by the utility and not published online. Contact the levying jurisdiction or utility to verify before budgeting; they are not included as dollar figures here.

View the Full Lady Lake Impact Fee Schedule
Water$0.00
Sewer$0.00
Total (Lady Lake): $1.80/sq ft (≈ $90,050.00 at 50,000 sq ft)
Sources last checked Official fee schedules:Town of Lady Lake Lake County
Fees flagged "Requires confirmation" have no confirmed published amount. Confirm them with the jurisdiction or utility before budgeting.

Where in Lake County Are You Building?

Each jurisdiction applies its own fee schedule. Pick yours. Totals shown are for a 50,000 sq ft building, including one-time water/sewer fees (assuming a 1-inch meter). = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.

Lady Lake: Office Impact Fees

Office development in Lady Lake pays $3.92 per square foot in impact fees (rates sourced August 4, 2026).

For a 25,000 sq ft building, that comes to at least $97,950.00. The calculator below adjusts to your exact square footage.

The largest line items are County Transportation Impact Fee (Lake County, Office) ($3.60/sq ft) and County Fire Rescue Impact Fee (Lake County, Office) ($0.32/sq ft).

Sewer Impact Fee (Town of Lady Lake) — 1 ERU (250 gpd) and Water Impact Fee (Town of Lady Lake) — 1 ERU (250 gpd) are set by the utility and not published online. Contact the levying jurisdiction or utility to verify before budgeting; they are not included as dollar figures here.

View the Full Lady Lake Impact Fee Schedule
Water$0.00
Sewer$0.00
Total (Lady Lake): $3.92/sq ft (≈ $97,950.00 at 25,000 sq ft)
Sources last checked Official fee schedules:Town of Lady Lake Lake County
Fees flagged "Requires confirmation" have no confirmed published amount. Confirm them with the jurisdiction or utility before budgeting.

Where in Lake County Are You Building?

Each jurisdiction applies its own fee schedule. Pick yours. Totals shown are for a 25,000 sq ft building, including one-time water/sewer fees (assuming a 1-inch meter). = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.

Lady Lake Impact Fee Calculator

Estimate impact fees for your project. Set to single-family. Drop a pin or search an address for site-specific fees.

Location

Select a location to begin

Once you select an address or drop a pin, we'll identify the responsible city and county and generate a fee breakdown.

Water & Sewer
Transportation
Parks
Schools
Fire & Police
General

How Impact Fees Work in Florida

Florida impact fees are one-time charges on new development, governed by Section 163.31801, Florida Statutes (the Florida Impact Fee Act). The statute requires fees to be based on the most recent and localized data, spent on the infrastructure category they were collected for, and adopted by ordinance.

Since a 2021 amendment (Ch. 2021-63, Laws of Florida), the law also limits how fast fees can rise: increases up to 25% phase in over two years, increases of 25–50% phase in over four years, and increases above 50% are allowed only with a demonstrated extraordinary-circumstances study and at least a two-thirds vote of the governing body.

Counties and cities can both levy impact fees. Inside an incorporated city, a project typically pays the county's countywide fees plus any municipal fees the city has adopted, which is why totals differ between a city and the unincorporated county around it.

If you're still asking what are impact fees, start with our guide to the definition, common categories, and legal basis.

Summary current as of September 2026. This is an editorial summary, not legal advice; see the official statute text and our terms of use.

Lady Lake Impact Fee FAQs

What are the total impact fees for a single-family home in Lady Lake, Florida?

A new single-family home in Lady Lake pays $25,747.00 per unit in combined impact fees (rates sourced August 4, 2026).

How much are commercial impact fees in Lady Lake?

Commercial development in Lady Lake pays $5.06 per square foot in impact fees, at least $253,100.00 for a 50,000 sq ft building. 2 additional fees have no published standard amounts and are not included, so the full cost may be higher; verify before budgeting.

Does Lady Lake charge its own impact fees?

Yes. Lady Lake levies its own municipal impact or utility fees, and county-levied fees also apply inside city limits. The schedule on this page shows every fee that applies to development in Lady Lake, with the combined total.

Can Florida impact fees increase at any time?

No. Section 163.31801, Florida Statutes limits increases to 50% at most, phased in over two to four years, unless the local government makes extraordinary-circumstances findings and approves the increase by at least a two-thirds vote.

Fee amounts on this page are compiled from official published schedules and are provided for planning purposes only. Rates change, and project specifics (unit size, meter size, location within special districts) can alter what applies. Always verify current fees with the jurisdiction and utility before relying on them.

Compare unincorporated rates and every other city on the Lake County impact fees page.

Missing a jurisdiction? Get in touch.

Request coverage for a city or county, report an issue, ask about enterprise access, or inquire about sponsorship opportunities. We typically reply within one business day.

0/1000