Skip to content
IMPACTFEES.ORG

The Hills, Texas Impact Fees

The Hills applies its own fee schedule. Travis County does not currently add county-level impact fees inside city limits. A new single-family home pays at least $3,391.70 per unit (rates sourced ). One additional fee has no published standard amount and is not included, so the full cost may be higher; verify before budgeting. The full breakdown is below.

The Hills Impact Fees by Project Type

The Hills: Single-Family Impact Fees

A new single-family home in The Hills pays at least $3,391.70 per unit in impact fees (rates sourced November 11, 2026). Every line item is levied at the municipal or utility level.

The largest line items are Sewer Tap Fee (Hurst Creek MUD) ($2,000.00) and Water Tap Fee (Hurst Creek MUD) — 3/4" meter ($1,391.70).

City Impact Fees (Village of The Hills) is set by the city and has no published standard rate. Contact the levying jurisdiction or utility to verify before budgeting; it is not included as a dollar figure here.

Some fees are tiered by unit size or building type; amounts reflect the representative tier noted in the schedule below.

View the Full The Hills Impact Fee Schedule
Water$1,391.70
  • Water Tap Fee (Hurst Creek MUD) — 3/4" meter
    Hurst Creek MUD
    Hurst Creek MUD water tap fee for a new home with a 3/4 in. meter, covering the connection, inspection and the meter (rate order amended effective September 21, 2026). Meters larger than 1 in. are charged three times the actual cost of the tap. The district charges no water impact fee.
    $1,391.70
Sewer$2,000.00
  • Sewer Tap Fee (Hurst Creek MUD)
    Hurst Creek MUD
    Hurst Creek MUD sewer tap fee for each new connection to the district's wastewater system; larger connections pay an added charge. The district charges no wastewater impact fee.
    $2,000.00
City$0.00
  • City Impact Fees (Village of The Hills)
    Village of The Hills
    The Village of The Hills code has no impact, roadway or parkland fee section; water and sewer tap fees are charged by Hurst Creek MUD.
    Requires confirmation
County$0.00
  • County Impact Fees (Travis County)
    Travis County
    Texas counties cannot levy Chapter 395 impact fees; the only county exception is storm water and drainage in a county of 3.3 million or more or one bordering it, which does not reach Travis County.
    $0.00
Total (The Hills): $3,391.70
Sources last checked Official fee schedules:Hurst Creek MUD Village of The Hills Travis County
Fees flagged "Requires confirmation" have no confirmed published amount. Confirm them with the jurisdiction or utility before budgeting.

Where in Travis County Are You Building?

Each jurisdiction applies its own fee schedule. Pick yours. = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.

The Hills: Multifamily Impact Fees

A new multifamily unit in The Hills pays at least $3,391.70 per unit in impact fees (rates sourced November 11, 2026). Every line item is levied at the municipal or utility level.

The largest line items are Sewer Tap Fee (Hurst Creek MUD, MF) ($2,000.00) and Water Tap Fee (Hurst Creek MUD, MF) — 3/4" meter ($1,391.70).

City Impact Fees (Village of The Hills, MF) is set by the city and has no published standard rate. Contact the levying jurisdiction or utility to verify before budgeting; it is not included as a dollar figure here.

Some fees are tiered by unit size or building type; amounts reflect the representative tier noted in the schedule below.

View the Full The Hills Impact Fee Schedule
Water$1,391.70
Sewer$2,000.00
  • Sewer Tap Fee (Hurst Creek MUD, MF)
    Hurst Creek MUD
    Hurst Creek MUD sewer tap fee per connection; a building on one connection pays it once, with an added charge for larger connections.
    $2,000.00
City$0.00
  • City Impact Fees (Village of The Hills, MF)
    Village of The Hills
    The Village of The Hills code has no impact, roadway or parkland fee section; water and sewer tap fees are charged by Hurst Creek MUD.
    Requires confirmation
County$0.00
  • County Impact Fees (Travis County, MF)
    Travis County
    Texas counties cannot levy Chapter 395 impact fees; the only county exception is storm water and drainage in a county of 3.3 million or more or one bordering it, which does not reach Travis County.
    $0.00
Total (The Hills): $3,391.70
Sources last checked Official fee schedules:Hurst Creek MUD Village of The Hills Travis County
Fees flagged "Requires confirmation" have no confirmed published amount. Confirm them with the jurisdiction or utility before budgeting.

Where in Travis County Are You Building?

Each jurisdiction applies its own fee schedule. Pick yours. = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.

The Hills: Commercial Impact Fees

Commercial development in The Hills pays no per-square-foot impact fees, but owes $3,571.70 in one-time water and sewer connection fees (rates sourced November 11, 2026).

For a 50,000 sq ft building, that comes to at least $3,571.70. The calculator below adjusts to your exact square footage.

The largest line items are Sewer Tap Fee (Hurst Creek MUD) ($2,000.00 one-time) and Water Tap Fee (Hurst Creek MUD) — 1" meter ($1,571.70 one-time).

Water and sewer connection fees assume a 1-inch meter; larger services pay more. See the meter-size tiers in the source schedules.

City Impact Fees (Village of The Hills, Commercial) is set by the city and has no published standard rate. Contact the levying jurisdiction or utility to verify before budgeting; it is not included as a dollar figure here.

View the Full The Hills Impact Fee Schedule
Water$1,571.70 one-time
  • Water Tap Fee (Hurst Creek MUD) — 1" meter
    Hurst Creek MUD
    Hurst Creek MUD water tap fee for a 1 in. meter, covering the connection, inspection and the meter (rate order amended effective September 21, 2026). Meters of 1-1/2 in. and larger are charged three times the actual cost of the tap, service line and meter. The district charges no water impact fee.
    $1,571.70 one-time
Sewer$2,000.00 one-time
  • Sewer Tap Fee (Hurst Creek MUD)
    Hurst Creek MUD
    Hurst Creek MUD sewer tap fee for each connection to the district's wastewater system; larger connections pay an added charge set by the district. The district charges no wastewater impact fee.
    $2,000.00 one-time
City$0.00
County$0.00
  • County Impact Fees (Travis County, Commercial)
    Travis County
    Texas counties cannot levy Chapter 395 impact fees; the only county exception is storm water and drainage in a county of 3.3 million or more or one bordering it, which does not reach Travis County.
    $0.00
Total (The Hills): $3,571.70 one-time (≈ $3,571.70 at 50,000 sq ft)
Sources last checked Official fee schedules:Hurst Creek MUD Village of The Hills Travis County
Fees flagged "Requires confirmation" have no confirmed published amount. Confirm them with the jurisdiction or utility before budgeting.
Water/sewer connection fees assume a 1-inch meter; larger services pay more.

Where in Travis County Are You Building?

Each jurisdiction applies its own fee schedule. Pick yours. Totals shown are for a 50,000 sq ft building, including water/sewer fees (one-time connection fees assume a 1-inch meter). * = one-time water/sewer connection charges only; no per-sq-ft impact fee schedule sourced for that jurisdiction. = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.

The Hills: Industrial Impact Fees

Industrial development in The Hills pays no per-square-foot impact fees, but owes $3,571.70 in one-time water and sewer connection fees (rates sourced November 11, 2026).

For a 50,000 sq ft building, that comes to at least $3,571.70. The calculator below adjusts to your exact square footage.

The largest line items are Sewer Tap Fee (Hurst Creek MUD) ($2,000.00 one-time) and Water Tap Fee (Hurst Creek MUD) — 1" meter ($1,571.70 one-time).

Water and sewer connection fees assume a 1-inch meter; larger services pay more. See the meter-size tiers in the source schedules.

City Impact Fees (Village of The Hills, Industrial) is set by the city and has no published standard rate. Contact the levying jurisdiction or utility to verify before budgeting; it is not included as a dollar figure here.

View the Full The Hills Impact Fee Schedule
Water$1,571.70 one-time
  • Water Tap Fee (Hurst Creek MUD) — 1" meter
    Hurst Creek MUD
    Hurst Creek MUD water tap fee for a 1 in. meter, covering the connection, inspection and the meter (rate order amended effective September 21, 2026). Meters of 1-1/2 in. and larger are charged three times the actual cost of the tap, service line and meter. The district charges no water impact fee.
    $1,571.70 one-time
Sewer$2,000.00 one-time
  • Sewer Tap Fee (Hurst Creek MUD)
    Hurst Creek MUD
    Hurst Creek MUD sewer tap fee for each connection to the district's wastewater system; larger connections pay an added charge set by the district. The district charges no wastewater impact fee.
    $2,000.00 one-time
City$0.00
County$0.00
  • County Impact Fees (Travis County, Industrial)
    Travis County
    Texas counties cannot levy Chapter 395 impact fees; the only county exception is storm water and drainage in a county of 3.3 million or more or one bordering it, which does not reach Travis County.
    $0.00
Total (The Hills): $3,571.70 one-time (≈ $3,571.70 at 50,000 sq ft)
Sources last checked Official fee schedules:Hurst Creek MUD Village of The Hills Travis County
Fees flagged "Requires confirmation" have no confirmed published amount. Confirm them with the jurisdiction or utility before budgeting.
Water/sewer connection fees assume a 1-inch meter; larger services pay more.

Where in Travis County Are You Building?

Each jurisdiction applies its own fee schedule. Pick yours. Totals shown are for a 50,000 sq ft building, including water/sewer fees (one-time connection fees assume a 1-inch meter). * = one-time water/sewer connection charges only; no per-sq-ft impact fee schedule sourced for that jurisdiction. = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.

The Hills: Office Impact Fees

Office development in The Hills pays no per-square-foot impact fees, but owes $3,571.70 in one-time water and sewer connection fees (rates sourced November 11, 2026).

For a 25,000 sq ft building, that comes to at least $3,571.70. The calculator below adjusts to your exact square footage.

The largest line items are Sewer Tap Fee (Hurst Creek MUD) ($2,000.00 one-time) and Water Tap Fee (Hurst Creek MUD) — 1" meter ($1,571.70 one-time).

Water and sewer connection fees assume a 1-inch meter; larger services pay more. See the meter-size tiers in the source schedules.

City Impact Fees (Village of The Hills, Office) is set by the city and has no published standard rate. Contact the levying jurisdiction or utility to verify before budgeting; it is not included as a dollar figure here.

View the Full The Hills Impact Fee Schedule
Water$1,571.70 one-time
  • Water Tap Fee (Hurst Creek MUD) — 1" meter
    Hurst Creek MUD
    Hurst Creek MUD water tap fee for a 1 in. meter, covering the connection, inspection and the meter (rate order amended effective September 21, 2026). Meters of 1-1/2 in. and larger are charged three times the actual cost of the tap, service line and meter. The district charges no water impact fee.
    $1,571.70 one-time
Sewer$2,000.00 one-time
  • Sewer Tap Fee (Hurst Creek MUD)
    Hurst Creek MUD
    Hurst Creek MUD sewer tap fee for each connection to the district's wastewater system; larger connections pay an added charge set by the district. The district charges no wastewater impact fee.
    $2,000.00 one-time
City$0.00
County$0.00
  • County Impact Fees (Travis County, Office)
    Travis County
    Texas counties cannot levy Chapter 395 impact fees; the only county exception is storm water and drainage in a county of 3.3 million or more or one bordering it, which does not reach Travis County.
    $0.00
Total (The Hills): $3,571.70 one-time (≈ $3,571.70 at 25,000 sq ft)
Sources last checked Official fee schedules:Hurst Creek MUD Village of The Hills Travis County
Fees flagged "Requires confirmation" have no confirmed published amount. Confirm them with the jurisdiction or utility before budgeting.
Water/sewer connection fees assume a 1-inch meter; larger services pay more.

Where in Travis County Are You Building?

Each jurisdiction applies its own fee schedule. Pick yours. Totals shown are for a 25,000 sq ft building, including water/sewer fees (one-time connection fees assume a 1-inch meter). * = one-time water/sewer connection charges only; no per-sq-ft impact fee schedule sourced for that jurisdiction. = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.

The Hills Impact Fee Calculator

Estimate impact fees for your project. Set to single-family. Drop a pin or search an address for site-specific fees.

Location

Select a location to begin

Once you select an address or drop a pin, we'll identify the responsible city and county and generate a fee breakdown.

Water & Sewer
Transportation
Parks
Schools
Fire & Police
General

How Impact Fees Work in Texas

Texas cities, and certain special districts and authorities, assess impact fees under Chapter 395 of the Local Government Code and, with narrow exceptions, may charge one only by following it. A fee rests on adopted land use assumptions and a capital improvements plan, and imposing one takes the votes of two-thirds of the governing body's members.

Impact fees may fund only water supply, treatment and distribution; wastewater collection and treatment; storm water, drainage and flood control; and roadway facilities. Parks, schools, police and fire facilities are not on the chapter's list. The chapter does not treat park land dedication, or a payment in its place, as an impact fee, so a city can require that separately. The fee per service unit is capped at the plan's growth-related cost, less a required credit, divided by the projected service units. Counties generally cannot charge impact fees: the chapter gives that authority only to counties of 3.3 million or more people and the counties bordering them, and only for storm water, drainage and flood control. Since September 2025 a city also may not charge an impact fee where an office, retail or warehouse building at least five years old is converted to multifamily or mixed-use residential use (at least 65 percent of the building and of each usable floor), unless the land was already subject to an impact fee before the conversion's building permit was filed (Section 218.204).

For land platted after a fee is adopted, the fee is assessed no later than when the plat is recorded, which fixes the most that can be charged per service unit. Where water and wastewater capacity is available, it is generally collected when the building permit is issued, or when a water or wastewater meter connection is applied for on land outside city limits or where the entity charging the fee issues no building permits. A fee not spent as the chapter allows within 10 years of payment must generally be refunded with interest, and the land use assumptions and capital improvements plan are updated at least every five years unless the governing body formally determines that no update is needed.

A city may charge water, wastewater and drainage impact fees in its extraterritorial jurisdiction as well as inside its limits, but roadway impact fees stop at the city limits. Where a utility district or another provider supplies water or sewer instead of the city, its charges are separate from the city's, so the total can differ between a city, its neighbors and the unincorporated land around it.

Brush up on impact fee basics before you budget your next project.

Summary current as of November 2026. This is an editorial summary, not legal advice; see the official statute text and our terms of use.

The Hills Impact Fee FAQs

What are the total impact fees for a single-family home in The Hills, Texas?

A new single-family home in The Hills pays at least $3,391.70 per unit in combined impact fees (rates sourced November 11, 2026). One additional fee has no published standard amount and is not included, so the full cost may be higher; verify before budgeting.

How much are commercial impact fees in The Hills?

Commercial development in The Hills pays no per-square-foot impact fees, but owes $3,571.70 in one-time water and sewer connection fees (assuming a 1-inch meter). One additional fee has no published standard amount and is not included, so the full cost may be higher; verify before budgeting.

Does The Hills charge its own impact fees?

Yes. The Hills levies its own municipal impact or utility fees. Travis County does not currently add county-level impact fees inside The Hills. The schedule on this page shows every fee that applies to development in The Hills.

Can a Texas impact fee increase at any time?

No. Under Section 395.0515 of the Local Government Code, added in 2025, a city or district may not increase an impact fee for three years from the later of the date the fee was adopted or last increased, although it may phase in collection up to the adopted maximum over no more than ten years. An increase also needs an independent financial audit and a public hearing on its results first (Section 395.059), and the measure approving it cannot be adopted as an emergency measure (Section 395.057). Once a fee is assessed on a tract, it cannot be raised for that tract unless the number of service units increases (Section 395.017). Charges set by a separate water or sewer provider may follow different rules.

Fee amounts on this page are compiled from official published schedules and are provided for planning purposes only. Rates change, and project specifics (unit size, meter size, location within special districts) can alter what applies. Always verify current fees with the jurisdiction and utility before relying on them.

Compare unincorporated rates and every other city on the Travis County impact fees page.

Missing a jurisdiction, or want to sponsor one?

Request coverage for a city or county, ask about sponsoring its page, or report an issue. We typically reply within one business day.