North Redington Beach, Florida Impact Fees

North Redington Beach applies its own fee schedule: municipal fees plus the Pinellas County-levied fees that apply inside city limits. Combined, a new single-family home pays $6,663.00 per unit (rates sourced ). This figure includes amounts that have not been confirmed with the jurisdiction; verify before budgeting. The full breakdown is below.

North Redington Beach Impact Fees by Project Type

North Redington Beach: Single-Family Impact Fees

A new single-family home in North Redington Beach pays $6,663.00 per unit in impact fees (rates sourced October 27, 2026). Of that, Pinellas County-levied fees account for $6,313.00 and municipal or utility fees for $350.00.

The largest line items are Multimodal Impact Fee (Pinellas County — Schedule A) ($1,679.00), Water Meter and Meter Box Charge (Pinellas County Utilities) — 5/8" x 3/4" meter ($744.00) and Water Tap and Service Line Charge (Pinellas County Utilities) — 5/8" x 3/4" ($669.00).

Sewer Connection Fee (Pinellas County Utilities) is shown at the last published amount but has not been confirmed with the jurisdiction; it is included in the totals here. Verify before budgeting.

Some fees are tiered by unit size or building type; amounts reflect the representative tier noted in the schedule below.

View the Full North Redington Beach Impact Fee Schedule
Water$1,836.00
  • Water Meter and Meter Box Charge (Pinellas County Utilities) — 5/8" x 3/4" meter
    Pinellas County Utilities
    Pinellas County Utilities charge for a new water meter and meter box: $744 for the standard 5/8" x 3/4" home meter, effective October 1, 2026 (1" $794, 1-1/2" $1,134, 2" $1,255; 4" and larger at cost). The tap and service line are charged separately.
    $744.00
  • Water Tap and Service Line Charge (Pinellas County Utilities) — 5/8" x 3/4"
    Pinellas County Utilities
    Pinellas County Utilities charge for tapping the main and installing the water service line for a 5/8" x 3/4" meter: $669, effective October 1, 2026 (1" $669, 1-1/2" $861, 2" $1,091). Where the developer installs the service line to PCU standards, no PCU tap charge applies (see the developer-installed option).
    $669.00
  • Water Capacity Fee (Pinellas County Utilities)
    5/8" x 3/4" meter
    Pinellas County Utilities
    Pinellas County Utilities supplies water here. Its one-time residential water capacity (impact) fee for a single-family home is $423 on a 5/8 x 3/4 inch meter and $1,056 on a 1 inch meter, under the schedule effective October 1, 2026. Meter, meter box, tap and service line installation are charged separately where the county installs them.
    $423.00
Sewer$2,798.00
  • Sewer Connection Fee (Pinellas County Utilities)
    Pinellas County Utilities
    Pinellas County Utilities provides sanitary sewer service in this jurisdiction. Its one-time sewer connection (impact) fee for a single-family residence is $2,798, effective 10/1/2025.
    $2,798.00Requires confirmation
City$350.00
County$1,679.00
  • Multimodal Impact Fee (Pinellas County — Schedule A)
    Single-family 1,501–2,499 sq ft
    Pinellas County
    Pinellas County's Multimodal (transportation) Impact Fee is the only impact fee Pinellas County itself levies. It applies countywide: every municipality collects and administers it within its limits. The single-family rate is tiered by heated living area: $1,356 (up to 1,500 sq ft), $1,679 (1,501–2,499 sq ft), and $2,066 (2,500 sq ft and over). Reduced Schedule B rates apply within designated downtown redevelopment districts. A credit applies for the highest prior use on the site since 1986. Rates were last set in 2019 and are unchanged.
    $1,679.00
Total (North Redington Beach): $6,663.00
Sources last checked Official fee schedules:Pinellas County Utilities Town of North Redington Beach Pinellas County
Amounts flagged "Requires confirmation" are the last published figures, included in the totals. Confirm them with the jurisdiction or utility before budgeting.

Where in Pinellas County Are You Building?

Each jurisdiction applies its own fee schedule. Pick yours. = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.

North Redington Beach: Multifamily Impact Fees

A new multifamily unit in North Redington Beach pays $4,218.00 per unit in impact fees (rates sourced October 27, 2026). Of that, Pinellas County-levied fees account for $3,868.00 and municipal or utility fees for $350.00.

The largest line items are Multimodal Impact Fee (Pinellas County — Schedule A, MF) ($1,420.00), Park Facilities Fee (Town of North Redington Beach, MF) ($350.00) and Water Capacity Fee (Pinellas County Utilities, MF) ($211.00).

Sewer Connection Fee (Pinellas County Utilities, MF) is shown at the last published amount but has not been confirmed with the jurisdiction; it is included in the totals here. Verify before budgeting.

Some fees are tiered by unit size or building type; amounts reflect the representative tier noted in the schedule below.

View the Full North Redington Beach Impact Fee Schedule
Water$211.00
  • Water Capacity Fee (Pinellas County Utilities, MF)
    2 bedroom (master-metered apt)
    Pinellas County Utilities
    Pinellas County Utilities supplies water here. Its one-time water capacity (impact) fee for master-metered apartments is charged per unit by bedroom count: $169 (1 bedroom), $211 (2 bedrooms) and $253 (3 bedrooms), with a loft or den counted as a bedroom. A master-metered duplex pays $592 and a triplex $761 per building. Schedule effective October 1, 2026. The building’s water meter and tap are charged once, by the master meter’s size, under the Pinellas County Utilities meter and tap schedule (5/8" x 3/4" meter $744 plus $669 tap; 2" $1,255 plus $1,091), effective October 1, 2026.
    $211.00
Sewer$2,237.00
  • Sewer Connection Fee (Pinellas County Utilities, MF)
    Pinellas County Utilities
    Pinellas County Utilities provides sanitary sewer service in this jurisdiction. Its one-time sewer connection (impact) fee is $2,237 per multifamily dwelling unit, effective 10/1/2025.
    $2,237.00Requires confirmation
City$350.00
County$1,420.00
  • Multimodal Impact Fee (Pinellas County — Schedule A, MF)
    Pinellas County
    Pinellas County's Multimodal (transportation) Impact Fee is the only impact fee Pinellas County itself levies. It applies countywide: every municipality collects and administers it within its limits. The multifamily rate is a flat $1,420 per dwelling unit (single-family rates are tiered by home size). Reduced Schedule B rates apply within designated downtown redevelopment districts. A credit applies for the highest prior use on the site since 1986. Rates were last set in 2019 and are unchanged.
    $1,420.00
Total (North Redington Beach): $4,218.00
Sources last checked Official fee schedules:Pinellas County Utilities Town of North Redington Beach Pinellas County
Amounts flagged "Requires confirmation" are the last published figures, included in the totals. Confirm them with the jurisdiction or utility before budgeting.

Where in Pinellas County Are You Building?

Each jurisdiction applies its own fee schedule. Pick yours. = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.

North Redington Beach: Commercial Impact Fees

Commercial development in North Redington Beach pays $3.40 per square foot in impact fees, plus $1,056.00 in one-time water and sewer connection fees (rates sourced October 27, 2026).

For a 50,000 sq ft building, that comes to at least $170,856.00. The calculator below adjusts to your exact square footage.

The largest line items are Water Capacity Fee (Pinellas County Utilities, Nonresidential) — 1" meter ($1,056.00 one-time) and Multimodal Impact Fee (Pinellas County, Commercial) ($3.40/sq ft).

Water and sewer connection fees assume a 1-inch meter; larger services pay more. See the meter-size tiers in the source schedules.

Sewer Connection Fee (Pinellas County Utilities, Nonresidential) — per gallon of flow is set by the utility and not published online. Contact the levying jurisdiction or utility to verify before budgeting; it is not included as a dollar figure here.

View the Full North Redington Beach Impact Fee Schedule
Water$1,056.00 one-time
Sewer$0.00
City$0.00
  • Municipal Impact Fee (Town of North Redington Beach, Commercial)
    Town of North Redington Beach
    The Town of North Redington Beach levies no municipal impact fee on nonresidential development; its park facilities fee applies only to residential and tourist dwelling units. The countywide multimodal impact fee applies and is listed separately.
    $0.00
County$3.40/sq ft
  • Multimodal Impact Fee (Pinellas County, Commercial)
    Pinellas County
    Pinellas County multimodal (transportation) impact fee, levied countywide; each city collects it within its limits. Rate per 1,000 sq ft of gross leasable area for general commercial under 100,000 sq ft; larger centers pay $3,627 to $4,192 per 1,000 sq ft by size, and restaurants, banks and other listed uses have their own rates. Charged on the net increase over the highest prior use. Rates unchanged since 2019.
    $3.40/sq ft
Total (North Redington Beach): $3.40/sq ft + $1,056.00 one-time (≈ $170,856.00 at 50,000 sq ft)
Sources last checked Official fee schedules:Pinellas County Utilities Town of North Redington Beach Pinellas County
Water/sewer connection fees assume a 1-inch meter; larger services pay more.

Where in Pinellas County Are You Building?

Each jurisdiction applies its own fee schedule. Pick yours. Totals shown are for a 50,000 sq ft building, including one-time water/sewer fees (assuming a 1-inch meter). = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.

North Redington Beach: Industrial Impact Fees

Industrial development in North Redington Beach pays $1.41 per square foot in impact fees, plus $1,056.00 in one-time water and sewer connection fees (rates sourced October 27, 2026).

For a 50,000 sq ft building, that comes to at least $71,756.00. The calculator below adjusts to your exact square footage.

The largest line items are Water Capacity Fee (Pinellas County Utilities, Nonresidential) — 1" meter ($1,056.00 one-time) and Multimodal Impact Fee (Pinellas County, Industrial) ($1.41/sq ft).

Water and sewer connection fees assume a 1-inch meter; larger services pay more. See the meter-size tiers in the source schedules.

Sewer Connection Fee (Pinellas County Utilities, Nonresidential) — per gallon of flow is set by the utility and not published online. Contact the levying jurisdiction or utility to verify before budgeting; it is not included as a dollar figure here.

View the Full North Redington Beach Impact Fee Schedule
Water$1,056.00 one-time
Sewer$0.00
City$0.00
  • Municipal Impact Fee (Town of North Redington Beach, Industrial)
    Town of North Redington Beach
    The Town of North Redington Beach levies no municipal impact fee on nonresidential development; its park facilities fee applies only to residential and tourist dwelling units. The countywide multimodal impact fee applies and is listed separately.
    $0.00
County$1.41/sq ft
  • Multimodal Impact Fee (Pinellas County, Industrial)
    Pinellas County
    Pinellas County multimodal (transportation) impact fee, levied countywide; each city collects it within its limits. Rate per 1,000 sq ft for general industrial and industrial parks; manufacturing and warehousing pay lower listed rates. Charged on the net increase over the highest prior use. Rates unchanged since 2019.
    $1.41/sq ft
Total (North Redington Beach): $1.41/sq ft + $1,056.00 one-time (≈ $71,756.00 at 50,000 sq ft)
Sources last checked Official fee schedules:Pinellas County Utilities Town of North Redington Beach Pinellas County
Water/sewer connection fees assume a 1-inch meter; larger services pay more.

Where in Pinellas County Are You Building?

Each jurisdiction applies its own fee schedule. Pick yours. Totals shown are for a 50,000 sq ft building, including one-time water/sewer fees (assuming a 1-inch meter). = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.

North Redington Beach: Office Impact Fees

Office development in North Redington Beach pays $3.29 per square foot in impact fees, plus $1,056.00 in one-time water and sewer connection fees (rates sourced October 27, 2026).

For a 25,000 sq ft building, that comes to at least $83,356.00. The calculator below adjusts to your exact square footage.

The largest line items are Water Capacity Fee (Pinellas County Utilities, Nonresidential) — 1" meter ($1,056.00 one-time) and Multimodal Impact Fee (Pinellas County, Office) ($3.29/sq ft).

Water and sewer connection fees assume a 1-inch meter; larger services pay more. See the meter-size tiers in the source schedules.

Sewer Connection Fee (Pinellas County Utilities, Nonresidential) — per gallon of flow is set by the utility and not published online. Contact the levying jurisdiction or utility to verify before budgeting; it is not included as a dollar figure here.

View the Full North Redington Beach Impact Fee Schedule
Water$1,056.00 one-time
Sewer$0.00
City$0.00
  • Municipal Impact Fee (Town of North Redington Beach, Office)
    Town of North Redington Beach
    The Town of North Redington Beach levies no municipal impact fee on nonresidential development; its park facilities fee applies only to residential and tourist dwelling units. The countywide multimodal impact fee applies and is listed separately.
    $0.00
County$3.29/sq ft
  • Multimodal Impact Fee (Pinellas County, Office)
    Pinellas County
    Pinellas County multimodal (transportation) impact fee, levied countywide; each city collects it within its limits. Rate per 1,000 sq ft for general office under 50,000 sq ft; larger buildings pay $1,656 to $2,767 per 1,000 sq ft by size, and medical office has its own rate. Charged on the net increase over the highest prior use. Rates unchanged since 2019.
    $3.29/sq ft
Total (North Redington Beach): $3.29/sq ft + $1,056.00 one-time (≈ $83,356.00 at 25,000 sq ft)
Sources last checked Official fee schedules:Pinellas County Utilities Town of North Redington Beach Pinellas County
Water/sewer connection fees assume a 1-inch meter; larger services pay more.

Where in Pinellas County Are You Building?

Each jurisdiction applies its own fee schedule. Pick yours. Totals shown are for a 25,000 sq ft building, including one-time water/sewer fees (assuming a 1-inch meter). = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.

North Redington Beach Impact Fee Calculator

Estimate impact fees for your project. Set to single-family. Drop a pin or search an address for site-specific fees.

Location

Select a location to begin

Once you select an address or drop a pin, we'll identify the responsible city and county and generate a fee breakdown.

Water & Sewer
Transportation
Parks
Schools
Fire & Police
General

How Impact Fees Work in Florida

Florida impact fees are one-time charges on new development, governed by Section 163.31801, Florida Statutes (the Florida Impact Fee Act). The statute requires fees to be based on the most recent and localized data, spent on the infrastructure category they were collected for, and adopted by ordinance.

Since a 2021 amendment (Ch. 2021-63, Laws of Florida), the law also limits how fast fees can rise: increases up to 25% phase in over two years, increases of 25–50% phase in over four years, and increases above 50% are allowed only with a demonstrated extraordinary-circumstances study and at least a two-thirds vote of the governing body.

Counties and cities can both levy impact fees. Inside an incorporated city, a project typically pays the county's countywide fees plus any municipal fees the city has adopted, which is why totals differ between a city and the unincorporated county around it.

New to impact fees? Our plain-English guide explains what they cover, who pays them, and why they exist.

Summary current as of September 2026. This is an editorial summary, not legal advice; see the official statute text and our terms of use.

North Redington Beach Impact Fee FAQs

What are the total impact fees for a single-family home in North Redington Beach, Florida?

A new single-family home in North Redington Beach pays $6,663.00 per unit in combined impact fees (rates sourced October 27, 2026). This figure includes amounts that have not been confirmed with the jurisdiction; verify before budgeting.

How much are commercial impact fees in North Redington Beach?

Commercial development in North Redington Beach pays $3.40 per square foot in impact fees, plus $1,056.00 in one-time water and sewer connection fees (assuming a 1-inch meter), at least $170,856.00 for a 50,000 sq ft building. One additional fee has no published standard amount and is not included, so the full cost may be higher; verify before budgeting.

Does North Redington Beach charge its own impact fees?

Yes. North Redington Beach levies its own municipal impact or utility fees, and county-levied fees also apply inside city limits. The schedule on this page shows every fee that applies to development in North Redington Beach, with the combined total.

Can Florida impact fees increase at any time?

No. Section 163.31801, Florida Statutes limits increases to 50% at most, phased in over two to four years, unless the local government makes extraordinary-circumstances findings and approves the increase by at least a two-thirds vote.

Fee amounts on this page are compiled from official published schedules and are provided for planning purposes only. Rates change, and project specifics (unit size, meter size, location within special districts) can alter what applies. Always verify current fees with the jurisdiction and utility before relying on them.

Compare unincorporated rates and every other city on the Pinellas County impact fees page.

Missing a jurisdiction? Get in touch.

Request coverage for a city or county, report an issue, ask about enterprise access, or inquire about sponsorship opportunities. We typically reply within one business day.