Balch Springs, Texas Impact Fees

Balch Springs applies its own fee schedule. Dallas County does not currently add county-level impact fees inside city limits. A new single-family home pays at least $12,567.23 per unit (rates sourced ). One additional fee has no published standard amount and is not included, so the full cost may be higher; verify before budgeting. The full breakdown is below.

Balch Springs Impact Fees by Project Type

Balch Springs: Single-Family Impact Fees

A new single-family home in Balch Springs pays at least $12,567.23 per unit in impact fees (rates sourced November 24, 2026). Every line item is levied at the municipal or utility level.

The largest line items are Water Tap Fee (City of Balch Springs) — 1" long tap ($4,000.00), Sewer Tap Fee (City of Balch Springs) — 4" long tap ($4,000.00) and Wastewater Impact Fee (City of Balch Springs) — 5/8" x 3/4" Simple ($3,279.72).

City Impact/Development Fees (City of Balch Springs) is set by the city and has no published standard rate. Contact the levying jurisdiction or utility to verify before budgeting; it is not included as a dollar figure here.

Some fees are tiered by unit size or building type; amounts reflect the representative tier noted in the schedule below.

View the Full Balch Springs Impact Fee Schedule
Water$5,287.51
  • Water Tap Fee (City of Balch Springs) — 1" long tap
    City of Balch Springs
    City-installed water tap with meter, flat fee from the City master fee schedule (September 2025). A long tap (across the street) is shown; a short tap costs $2,000. The 1 in. tap serves a 3/4 or 1 in. meter. Larger taps cost more. A $50 inspection fee also applies.
    $4,000.00
  • Water Impact Fee (City of Balch Springs) — 5/8" x 3/4" Simple
    City of Balch Springs
    Water impact fee by meter size, adopted May 26, 2026 (a typical home's 5/8 x 3/4 in. meter is one service unit). Paid at platting or building permit, whichever comes first, once water service is available. A separate water tap fee also applies.
    $1,287.51
Sewer$7,279.72
  • Sewer Tap Fee (City of Balch Springs) — 4" long tap
    City of Balch Springs
    City-installed 4 in. sewer tap, flat fee from the City master fee schedule (September 2025). A long tap (across the street) is shown; a short tap costs $2,000. A 6 in. tap costs $2,500 short or $5,000 long.
    $4,000.00
  • Wastewater Impact Fee (City of Balch Springs) — 5/8" x 3/4" Simple
    City of Balch Springs
    Wastewater impact fee by meter size, adopted May 26, 2026 (a typical home's 5/8 x 3/4 in. meter is one service unit). Paid at platting or building permit, whichever comes first, once sewer service is available. A separate sewer tap fee also applies.
    $3,279.72
City$0.00
County$0.00
Total (Balch Springs): $12,567.23
Sources last checked Official fee schedules:City of Balch Springs Dallas County
Fees flagged "Requires confirmation" have no confirmed published amount. Confirm them with the jurisdiction or utility before budgeting.

Where in Dallas County Are You Building?

Each jurisdiction applies its own fee schedule. Pick yours. = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.

Balch Springs: Multifamily Impact Fees

A new multifamily unit in Balch Springs pays at least $12,567.23 per unit in impact fees (rates sourced November 24, 2026). Every line item is levied at the municipal or utility level.

The largest line items are Sewer Tap Fee (City of Balch Springs, MF) — 4" long tap ($4,000.00), Water Tap Fee (City of Balch Springs, MF) — 1" long tap ($4,000.00) and Wastewater Impact Fee (City of Balch Springs, MF) — 5/8" x 3/4" Simple ($3,279.72).

City Impact/Development Fees (City of Balch Springs, MF) is set by the city and has no published standard rate. Contact the levying jurisdiction or utility to verify before budgeting; it is not included as a dollar figure here.

Some fees are tiered by unit size or building type; amounts reflect the representative tier noted in the schedule below.

View the Full Balch Springs Impact Fee Schedule
Water$5,287.51
  • Water Tap Fee (City of Balch Springs, MF) — 1" long tap
    City of Balch Springs
    City-installed water tap with meter, flat fee per tap from the City master fee schedule (September 2025): a building on one connection pays once. A long tap (across the street) is shown; a short tap costs $2,000. Larger taps cost more. A $50 inspection fee also applies.
    $4,000.00
  • Water Impact Fee (City of Balch Springs, MF) — 5/8" x 3/4" Simple
    City of Balch Springs
    Water impact fee by meter size, adopted May 26, 2026, with no per-unit rate: a building on one meter pays once, at its meter size. Larger master meters pay more. Paid at platting or building permit once service is available.
    $1,287.51
Sewer$7,279.72
  • Sewer Tap Fee (City of Balch Springs, MF) — 4" long tap
    City of Balch Springs
    City-installed 4 in. sewer tap, flat fee per tap from the City master fee schedule (September 2025): a building on one connection pays once. A long tap (across the street) is shown; a short tap costs $2,000. A 6 in. tap costs $2,500 short or $5,000 long.
    $4,000.00
  • Wastewater Impact Fee (City of Balch Springs, MF) — 5/8" x 3/4" Simple
    City of Balch Springs
    Wastewater impact fee by meter size, adopted May 26, 2026, with no per-unit rate: a building on one meter pays once, at its meter size. Larger master meters pay more. Paid at platting or building permit once service is available.
    $3,279.72
City$0.00
County$0.00
Total (Balch Springs): $12,567.23
Sources last checked Official fee schedules:City of Balch Springs Dallas County
Fees flagged "Requires confirmation" have no confirmed published amount. Confirm them with the jurisdiction or utility before budgeting.

Where in Dallas County Are You Building?

Each jurisdiction applies its own fee schedule. Pick yours. = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.

Balch Springs: Commercial Impact Fees

Commercial development in Balch Springs pays no per-square-foot impact fees, but owes $15,918.09 in one-time water and sewer connection fees (rates sourced November 24, 2026).

For a 50,000 sq ft building, that comes to about $15,918.09. The calculator below adjusts to your exact square footage.

The largest line items are Sewer Tap Fee (City of Balch Springs) — 4" short tap ($2,000.00 one-time) and Water Tap and Meter Fee (City of Balch Springs) — 1" short tap ($2,000.00 one-time).

Water and sewer connection fees assume a 1-inch meter; larger services pay more. See the meter-size tiers in the source schedules.

Building Permit Impact Fee (City of Balch Springs, Commercial), Water Impact Fee (City of Balch Springs) — 1" meter, and Wastewater Impact Fee (City of Balch Springs) — 1" meter are shown at the last published amount but have not been confirmed with the jurisdiction; they are included in the totals here. Verify before budgeting.

View the Full Balch Springs Impact Fee Schedule
Water$5,218.78 one-time
  • Water Impact Fee (City of Balch Springs) — 1" meter
    City of Balch Springs
    Chapter 395 water impact fee adopted May 26, 2026, charged by meter size at $1,287.51 per equivalent dwelling unit (a 1-inch meter is 2.5 units). Due at subdivision or building permit, whichever comes first, once water service is available. A separate water tap and meter fee also applies.
    $3,218.78 one-timeRequires confirmation
  • Water Tap and Meter Fee (City of Balch Springs) — 1" short tap
    City of Balch Springs
    City water tap and meter fee, a flat charge by tap size and by whether the tap is short or long (a long tap crosses the street). The 1-inch short tap covers 3/4-inch and 1-inch meters; taps over 2 inches are priced by the City's contractor. Charged in addition to the water impact fee.
    $2,000.00 one-time
Sewer$10,199.31 one-time
  • Wastewater Impact Fee (City of Balch Springs) — 1" meter
    City of Balch Springs
    Chapter 395 wastewater impact fee adopted May 26, 2026, charged by water meter size at $3,279.72 per equivalent dwelling unit (a 1-inch meter is 2.5 units). Due at subdivision or building permit, whichever comes first, once sewer service is available. A separate sewer tap fee also applies.
    $8,199.31 one-timeRequires confirmation
  • Sewer Tap Fee (City of Balch Springs) — 4" short tap
    City of Balch Springs
    City sewer tap fee, a flat charge by lateral size and by whether the tap is short or long (a long tap crosses the street). Charged in addition to the wastewater impact fee.
    $2,000.00 one-time
City$500.00 one-time
  • Building Permit Impact Fee (City of Balch Springs, Commercial)
    City of Balch Springs
    The City's master fee schedule lists a flat $500 commercial impact fee among its building permit fees, separate from the water and wastewater impact fees. The City has no roadway impact fee.
    $500.00 one-timeRequires confirmation
County$0.00
  • County Impact Fee (Dallas County, Commercial)
    Dallas County
    Texas counties cannot levy impact fees under Local Government Code Chapter 395, so Dallas County charges no county impact fee on commercial, office or industrial development.
    $0.00
Total (Balch Springs): $15,918.09 one-time (≈ $15,918.09 at 50,000 sq ft)
Sources last checked Official fee schedules:City of Balch Springs Dallas County
Amounts flagged "Requires confirmation" are the last published figures, included in the totals. Confirm them with the jurisdiction or utility before budgeting.
Water/sewer connection fees assume a 1-inch meter; larger services pay more.

Where in Dallas County Are You Building?

Each jurisdiction applies its own fee schedule. Pick yours. Totals shown are for a 50,000 sq ft building, including water/sewer fees (one-time connection fees assume a 1-inch meter). * = one-time water/sewer connection charges only; no per-sq-ft impact fee schedule sourced for that jurisdiction. = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.

Balch Springs: Industrial Impact Fees

Industrial development in Balch Springs pays no per-square-foot impact fees, but owes $15,918.09 in one-time water and sewer connection fees (rates sourced November 24, 2026).

For a 50,000 sq ft building, that comes to about $15,918.09. The calculator below adjusts to your exact square footage.

The largest line items are Sewer Tap Fee (City of Balch Springs) — 4" short tap ($2,000.00 one-time) and Water Tap and Meter Fee (City of Balch Springs) — 1" short tap ($2,000.00 one-time).

Water and sewer connection fees assume a 1-inch meter; larger services pay more. See the meter-size tiers in the source schedules.

Building Permit Impact Fee (City of Balch Springs, Industrial), Water Impact Fee (City of Balch Springs) — 1" meter, and Wastewater Impact Fee (City of Balch Springs) — 1" meter are shown at the last published amount but have not been confirmed with the jurisdiction; they are included in the totals here. Verify before budgeting.

View the Full Balch Springs Impact Fee Schedule
Water$5,218.78 one-time
  • Water Impact Fee (City of Balch Springs) — 1" meter
    City of Balch Springs
    Chapter 395 water impact fee adopted May 26, 2026, charged by meter size at $1,287.51 per equivalent dwelling unit (a 1-inch meter is 2.5 units). Due at subdivision or building permit, whichever comes first, once water service is available. A separate water tap and meter fee also applies.
    $3,218.78 one-timeRequires confirmation
  • Water Tap and Meter Fee (City of Balch Springs) — 1" short tap
    City of Balch Springs
    City water tap and meter fee, a flat charge by tap size and by whether the tap is short or long (a long tap crosses the street). The 1-inch short tap covers 3/4-inch and 1-inch meters; taps over 2 inches are priced by the City's contractor. Charged in addition to the water impact fee.
    $2,000.00 one-time
Sewer$10,199.31 one-time
  • Wastewater Impact Fee (City of Balch Springs) — 1" meter
    City of Balch Springs
    Chapter 395 wastewater impact fee adopted May 26, 2026, charged by water meter size at $3,279.72 per equivalent dwelling unit (a 1-inch meter is 2.5 units). Due at subdivision or building permit, whichever comes first, once sewer service is available. A separate sewer tap fee also applies.
    $8,199.31 one-timeRequires confirmation
  • Sewer Tap Fee (City of Balch Springs) — 4" short tap
    City of Balch Springs
    City sewer tap fee, a flat charge by lateral size and by whether the tap is short or long (a long tap crosses the street). Charged in addition to the wastewater impact fee.
    $2,000.00 one-time
City$500.00 one-time
  • Building Permit Impact Fee (City of Balch Springs, Industrial)
    City of Balch Springs
    The City's master fee schedule lists a flat $500 commercial impact fee among its building permit fees, separate from the water and wastewater impact fees. The City has no roadway impact fee.
    $500.00 one-timeRequires confirmation
County$0.00
  • County Impact Fee (Dallas County, Industrial)
    Dallas County
    Texas counties cannot levy impact fees under Local Government Code Chapter 395, so Dallas County charges no county impact fee on commercial, office or industrial development.
    $0.00
Total (Balch Springs): $15,918.09 one-time (≈ $15,918.09 at 50,000 sq ft)
Sources last checked Official fee schedules:City of Balch Springs Dallas County
Amounts flagged "Requires confirmation" are the last published figures, included in the totals. Confirm them with the jurisdiction or utility before budgeting.
Water/sewer connection fees assume a 1-inch meter; larger services pay more.

Where in Dallas County Are You Building?

Each jurisdiction applies its own fee schedule. Pick yours. Totals shown are for a 50,000 sq ft building, including water/sewer fees (one-time connection fees assume a 1-inch meter). * = one-time water/sewer connection charges only; no per-sq-ft impact fee schedule sourced for that jurisdiction. = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.

Balch Springs: Office Impact Fees

Office development in Balch Springs pays no per-square-foot impact fees, but owes $15,918.09 in one-time water and sewer connection fees (rates sourced November 24, 2026).

For a 25,000 sq ft building, that comes to about $15,918.09. The calculator below adjusts to your exact square footage.

The largest line items are Sewer Tap Fee (City of Balch Springs) — 4" short tap ($2,000.00 one-time) and Water Tap and Meter Fee (City of Balch Springs) — 1" short tap ($2,000.00 one-time).

Water and sewer connection fees assume a 1-inch meter; larger services pay more. See the meter-size tiers in the source schedules.

Building Permit Impact Fee (City of Balch Springs, Office), Water Impact Fee (City of Balch Springs) — 1" meter, and Wastewater Impact Fee (City of Balch Springs) — 1" meter are shown at the last published amount but have not been confirmed with the jurisdiction; they are included in the totals here. Verify before budgeting.

View the Full Balch Springs Impact Fee Schedule
Water$5,218.78 one-time
  • Water Impact Fee (City of Balch Springs) — 1" meter
    City of Balch Springs
    Chapter 395 water impact fee adopted May 26, 2026, charged by meter size at $1,287.51 per equivalent dwelling unit (a 1-inch meter is 2.5 units). Due at subdivision or building permit, whichever comes first, once water service is available. A separate water tap and meter fee also applies.
    $3,218.78 one-timeRequires confirmation
  • Water Tap and Meter Fee (City of Balch Springs) — 1" short tap
    City of Balch Springs
    City water tap and meter fee, a flat charge by tap size and by whether the tap is short or long (a long tap crosses the street). The 1-inch short tap covers 3/4-inch and 1-inch meters; taps over 2 inches are priced by the City's contractor. Charged in addition to the water impact fee.
    $2,000.00 one-time
Sewer$10,199.31 one-time
  • Wastewater Impact Fee (City of Balch Springs) — 1" meter
    City of Balch Springs
    Chapter 395 wastewater impact fee adopted May 26, 2026, charged by water meter size at $3,279.72 per equivalent dwelling unit (a 1-inch meter is 2.5 units). Due at subdivision or building permit, whichever comes first, once sewer service is available. A separate sewer tap fee also applies.
    $8,199.31 one-timeRequires confirmation
  • Sewer Tap Fee (City of Balch Springs) — 4" short tap
    City of Balch Springs
    City sewer tap fee, a flat charge by lateral size and by whether the tap is short or long (a long tap crosses the street). Charged in addition to the wastewater impact fee.
    $2,000.00 one-time
City$500.00 one-time
  • Building Permit Impact Fee (City of Balch Springs, Office)
    City of Balch Springs
    The City's master fee schedule lists a flat $500 commercial impact fee among its building permit fees, separate from the water and wastewater impact fees. The City has no roadway impact fee.
    $500.00 one-timeRequires confirmation
County$0.00
  • County Impact Fee (Dallas County, Office)
    Dallas County
    Texas counties cannot levy impact fees under Local Government Code Chapter 395, so Dallas County charges no county impact fee on commercial, office or industrial development.
    $0.00
Total (Balch Springs): $15,918.09 one-time (≈ $15,918.09 at 25,000 sq ft)
Sources last checked Official fee schedules:City of Balch Springs Dallas County
Amounts flagged "Requires confirmation" are the last published figures, included in the totals. Confirm them with the jurisdiction or utility before budgeting.
Water/sewer connection fees assume a 1-inch meter; larger services pay more.

Where in Dallas County Are You Building?

Each jurisdiction applies its own fee schedule. Pick yours. Totals shown are for a 25,000 sq ft building, including water/sewer fees (one-time connection fees assume a 1-inch meter). * = one-time water/sewer connection charges only; no per-sq-ft impact fee schedule sourced for that jurisdiction. = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.

Balch Springs Impact Fee Calculator

Estimate impact fees for your project. Set to single-family. Drop a pin or search an address for site-specific fees.

Location

Select a location to begin

Once you select an address or drop a pin, we'll identify the responsible city and county and generate a fee breakdown.

Water & Sewer
Transportation
Parks
Schools
Fire & Police
General

How Impact Fees Work in Texas

Texas cities, and certain special districts and authorities, assess impact fees under Chapter 395 of the Local Government Code and, with narrow exceptions, may charge one only by following it. A fee rests on adopted land use assumptions and a capital improvements plan, and imposing one takes the votes of two-thirds of the governing body's members.

Impact fees may fund only water supply, treatment and distribution; wastewater collection and treatment; storm water, drainage and flood control; and roadway facilities. Parks, schools, police and fire facilities are not on the chapter's list. The chapter does not treat park land dedication, or a payment in its place, as an impact fee, so a city can require that separately. The fee per service unit is capped at the plan's growth-related cost, less a required credit, divided by the projected service units. Counties generally cannot charge impact fees: the chapter gives that authority only to counties of 3.3 million or more people and the counties bordering them, and only for storm water, drainage and flood control. Since September 2025 a city also may not charge an impact fee where an office, retail or warehouse building at least five years old is converted to multifamily or mixed-use residential use (at least 65 percent of the building and of each usable floor), unless the land was already subject to an impact fee before the conversion's building permit was filed (Section 218.204).

For land platted after a fee is adopted, the fee is assessed no later than when the plat is recorded, which fixes the most that can be charged per service unit. Where water and wastewater capacity is available, it is generally collected when the building permit is issued, or when a water or wastewater meter connection is applied for on land outside city limits or where the entity charging the fee issues no building permits. A fee not spent as the chapter allows within 10 years of payment must generally be refunded with interest, and the land use assumptions and capital improvements plan are updated at least every five years unless the governing body formally determines that no update is needed.

A city may charge water, wastewater and drainage impact fees in its extraterritorial jurisdiction as well as inside its limits, but roadway impact fees stop at the city limits. Where a utility district or another provider supplies water or sewer instead of the city, its charges are separate from the city's, so the total can differ between a city, its neighbors and the unincorporated land around it.

For a primer on how impact fees work, see our plain-English guide.

Summary current as of November 2026. This is an editorial summary, not legal advice; see the official statute text and our terms of use.

Balch Springs Impact Fee FAQs

What are the total impact fees for a single-family home in Balch Springs, Texas?

A new single-family home in Balch Springs pays at least $12,567.23 per unit in combined impact fees (rates sourced November 24, 2026). One additional fee has no published standard amount and is not included, so the full cost may be higher; verify before budgeting.

How much are commercial impact fees in Balch Springs?

Commercial development in Balch Springs pays no per-square-foot impact fees, but owes $15,918.09 in one-time water and sewer connection fees (assuming a 1-inch meter). This figure includes amounts that have not been confirmed with the jurisdiction; verify before budgeting.

Does Balch Springs charge its own impact fees?

Yes. Balch Springs levies its own municipal impact or utility fees. Dallas County does not currently add county-level impact fees inside Balch Springs. The schedule on this page shows every fee that applies to development in Balch Springs.

Can a Texas impact fee increase at any time?

No. Under Section 395.0515 of the Local Government Code, added in 2025, a city or district may not increase an impact fee for three years from the later of the date the fee was adopted or last increased, although it may phase in collection up to the adopted maximum over no more than ten years. An increase also needs an independent financial audit and a public hearing on its results first (Section 395.059), and the measure approving it cannot be adopted as an emergency measure (Section 395.057). Once a fee is assessed on a tract, it cannot be raised for that tract unless the number of service units increases (Section 395.017). Charges set by a separate water or sewer provider may follow different rules.

Fee amounts on this page are compiled from official published schedules and are provided for planning purposes only. Rates change, and project specifics (unit size, meter size, location within special districts) can alter what applies. Always verify current fees with the jurisdiction and utility before relying on them.

Compare unincorporated rates and every other city on the Dallas County impact fees page.

Missing a jurisdiction, or want to sponsor one?

Request coverage for a city or county, ask about sponsoring its page, or report an issue. We typically reply within one business day.