Westlake, Florida Impact Fees

Westlake applies its own fee schedule: municipal fees plus the Palm Beach County-levied fees that apply inside city limits. Combined, a new single-family home pays at least $21,199.32 per unit (rates sourced ). This figure includes amounts that have not been confirmed and excludes fees with no published standard amount, so the full cost may be higher; verify before budgeting. The full breakdown is below.

Westlake Impact Fees by Project Type

Westlake: Single-Family Impact Fees

A new single-family home in Westlake pays at least $21,199.32 per unit in impact fees (rates sourced October 27, 2026). Of that, Palm Beach County-levied fees account for $15,917.22 and municipal or utility fees for $5,282.10.

The largest line items are County School (Educational Facilities) Impact Fee (SFR) ($7,905.90), County Road (Fair Share) Impact Fee (SFR) ($5,597.40) and County Parks & Recreation Impact Fee (SFR) ($1,225.26).

Sewer Capacity/Connection Fee (Seminole Improvement District) and Water Capacity/Connection Fee (Seminole Improvement District) are shown at the last published amount but have not been confirmed with the jurisdiction; they are included in the totals here. Verify before budgeting.

Municipal Impact Fee (City of Westlake) is set by the city and has no published standard rate. Contact the levying jurisdiction or utility to verify before budgeting; it is not included as a dollar figure here.

View the Full Westlake Impact Fee Schedule
Water$3,431.70
  • Water Capacity/Connection Fee (Seminole Improvement District)
    Seminole Improvement District
    Water service in Westlake is provided by the Seminole Improvement District, an independent special district. One-time water capital connection contribution per equivalent residential unit (a single-family home is one unit), under the district's developer-builder rate charges effective October 1, 2025. The district's board took up fiscal year 2027 rates on September 30, 2026 (a 2% or 3% increase); the adopted figure is not yet published.
    $3,431.70Requires confirmation
Sewer$1,850.40
  • Sewer Capacity/Connection Fee (Seminole Improvement District)
    Seminole Improvement District
    Wastewater service in Westlake is provided by the Seminole Improvement District, an independent special district. One-time wastewater capital connection contribution per equivalent residential unit (a single-family home is one unit), under the district's developer-builder rate charges effective October 1, 2025. The district's board took up fiscal year 2027 rates on September 30, 2026 (a 2% or 3% increase); the adopted figure is not yet published.
    $1,850.40Requires confirmation
City$0.00
  • Municipal Impact Fee (City of Westlake)
    City of Westlake
    No municipal impact fee is codified for the City of Westlake (incorporated 2016); its planning and building schedule covers permit and review fees only. Palm Beach County impact fees and the Seminole Improvement District utility charges apply.
    Requires confirmation
County$15,917.22
  • County School (Educational Facilities) Impact Fee (SFR)
    School District of Palm Beach County
    Palm Beach County public-school impact fee, single-family home 2,000–3,599 sq ft. Effective January 1, 2026. Applies countywide.
    $7,905.90
  • County Road (Fair Share) Impact Fee (SFR)
    Palm Beach County
    Palm Beach County "Fair Share" road impact fee, single-family detached. Effective January 1, 2026. The County publishes a separate schedule for each municipality and updates them annually on January 1.
    $5,597.40
  • County Parks & Recreation Impact Fee (SFR)
    Palm Beach County
    Palm Beach County parks impact fee, single-family home 2,000–3,599 sq ft. Effective January 1, 2026.
    $1,225.26
  • County Fire Rescue Impact Fee (SFR)
    Palm Beach County Fire Rescue
    Palm Beach County fire-rescue impact fee, single-family home. Effective January 1, 2026. Westlake is served by Palm Beach County Fire Rescue.
    $393.30
  • County Public Buildings Impact Fee (SFR)
    Palm Beach County
    Palm Beach County public buildings impact fee, single-family home 2,000–3,599 sq ft. Effective January 1, 2026.
    $317.30
  • County Library Impact Fee (SFR)
    Palm Beach County
    Palm Beach County library impact fee, single-family home 2,000–3,599 sq ft. Effective January 1, 2026. Westlake lies within the County library service district.
    $295.45
  • County Law Enforcement Impact Fee (SFR)
    Palm Beach County Sheriff's Office (PBSO)
    Palm Beach County law-enforcement (patrol) impact fee, single-family home. Effective January 1, 2026. Westlake is patrolled by the Palm Beach County Sheriff's Office.
    $182.61
Amounts flagged "Requires confirmation" are the last published figures, included in the totals. Confirm them with the jurisdiction or utility before budgeting.

Where in Palm Beach County Are You Building?

Each jurisdiction applies its own fee schedule. Pick yours. = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.

Westlake: Multifamily Impact Fees

A new multifamily unit in Westlake pays at least $15,896.84 per unit in impact fees (rates sourced October 27, 2026). Of that, Palm Beach County-levied fees account for $10,614.74 and municipal or utility fees for $5,282.10.

The largest line items are County School (Educational Facilities) Impact Fee (MF) ($6,170.25), County Road (Fair Share) Impact Fee (MF, Mid/High-Rise 4+) ($2,554.55) and County Parks & Recreation Impact Fee (MF) ($1,046.35).

Sewer Capacity/Connection Fee (Seminole Improvement District, MF) and Water Capacity/Connection Fee (Seminole Improvement District, MF) are shown at the last published amount but have not been confirmed with the jurisdiction; they are included in the totals here. Verify before budgeting.

Municipal Impact Fee (City of Westlake, MF) is set by the city and has no published standard rate. Contact the levying jurisdiction or utility to verify before budgeting; it is not included as a dollar figure here.

Some fees are tiered by unit size or building type; amounts reflect the representative tier noted in the schedule below.

View the Full Westlake Impact Fee Schedule
Water$3,431.70
  • Water Capacity/Connection Fee (Seminole Improvement District, MF)
    Seminole Improvement District
    Water service in Westlake is provided by the Seminole Improvement District, an independent special district. The district charges a one-time water capital connection contribution per equivalent residential unit (ERU); its rate sheet does not state how many ERUs a multifamily unit counts as. Amount shown is the full per-ERU contribution of $3,431.70 (rates effective October 1, 2025); the district may rate a multifamily unit below one ERU. The district's board took up fiscal year 2027 rates on September 30, 2026 (a 2% or 3% increase); the adopted figure is not yet published.
    $3,431.70Requires confirmation
Sewer$1,850.40
  • Sewer Capacity/Connection Fee (Seminole Improvement District, MF)
    Seminole Improvement District
    Wastewater service in Westlake is provided by the Seminole Improvement District, an independent special district. The district charges a one-time wastewater capital connection contribution per equivalent residential unit (ERU); its rate sheet does not state how many ERUs a multifamily unit counts as. Amount shown is the full per-ERU contribution of $1,850.40 (rates effective October 1, 2025); the district may rate a multifamily unit below one ERU. The district's board took up fiscal year 2027 rates on September 30, 2026 (a 2% or 3% increase); the adopted figure is not yet published.
    $1,850.40Requires confirmation
City$0.00
  • Municipal Impact Fee (City of Westlake, MF)
    City of Westlake
    No municipal impact fee is codified for the City of Westlake; its planning and building schedule covers permit and review fees only. Palm Beach County impact fees and the Seminole Improvement District utility charges apply.
    Requires confirmation
County$10,614.74
  • County School (Educational Facilities) Impact Fee (MF)
    School District of Palm Beach County
    Palm Beach County public-school impact fee, multifamily unit 801–1,399 sq ft. Effective January 1, 2026. Applies countywide.
    $6,170.25
  • County Road (Fair Share) Impact Fee (MF, Mid/High-Rise 4+)
    Mid/High-Rise 4+ stories
    Palm Beach County
    Palm Beach County "Fair Share" road impact fee, multifamily in a building of 4+ stories. Effective January 1, 2026. Low-rise multifamily (1–3 stories) pays a different per-unit rate; see that tier.
    $2,554.55
  • County Parks & Recreation Impact Fee (MF)
    Palm Beach County
    Palm Beach County parks impact fee, multifamily unit 801–1,399 sq ft. Effective January 1, 2026.
    $1,046.35
  • County Fire Rescue Impact Fee (MF)
    Palm Beach County Fire Rescue
    Palm Beach County fire-rescue impact fee, multifamily. Effective January 1, 2026. Westlake is served by Palm Beach County Fire Rescue.
    $264.10
  • County Public Buildings Impact Fee (MF)
    Palm Beach County
    Palm Beach County public buildings impact fee, multifamily unit 801–1,399 sq ft. Effective January 1, 2026.
    $243.20
  • County Library Impact Fee (MF)
    Palm Beach County
    Palm Beach County library impact fee, multifamily unit 801–1,399 sq ft. Effective January 1, 2026. Westlake lies within the County library service district.
    $236.55
  • County Law Enforcement Impact Fee (MF)
    Palm Beach County Sheriff's Office (PBSO)
    Palm Beach County law-enforcement (patrol) impact fee, multifamily. Effective January 1, 2026. Westlake is patrolled by the Palm Beach County Sheriff's Office.
    $99.74
Amounts flagged "Requires confirmation" are the last published figures, included in the totals. Confirm them with the jurisdiction or utility before budgeting.

Where in Palm Beach County Are You Building?

Each jurisdiction applies its own fee schedule. Pick yours. = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.

Westlake: Commercial Impact Fees

Commercial development in Westlake pays $8.62 per square foot in impact fees (rates sourced October 27, 2026).

For a 50,000 sq ft building, that comes to at least $430,920.50. The calculator below adjusts to your exact square footage.

The largest line items are Road (Fair Share) Impact Fee (Palm Beach County, Commercial) ($7.91/sq ft), Public Buildings Impact Fee (Palm Beach County, Commercial) ($0.47/sq ft) and Fire Rescue Impact Fee (Palm Beach County, Commercial) ($0.16/sq ft).

Wastewater Capital Connection Contribution (Seminole Improvement District) — per reserve gallon and Water Capital Connection Contribution (Seminole Improvement District) — per reserve gallon are set by the utility and not published online. City Impact Fees (City of Westlake, Commercial) is set by the city and has no published standard rate. Contact the levying jurisdiction or utility to verify before budgeting; they are not included as dollar figures here.

View the Full Westlake Impact Fee Schedule
Water$0.00
  • Water Capital Connection Contribution (Seminole Improvement District) — per reserve gallon
    Seminole Improvement District
    Water service in Westlake is provided by the Seminole Improvement District, an independent special district. Nonresidential projects pay a one-time water capital connection contribution of $12.71 per gallon of reserved daily capacity, under the district's developer-builder rate charges effective October 1, 2025. The district's board took up fiscal year 2027 rates on September 30, 2026 (a 2% or 3% increase); the adopted figure is not yet published.
    Requires confirmation
Sewer$0.00
  • Wastewater Capital Connection Contribution (Seminole Improvement District) — per reserve gallon
    Seminole Improvement District
    Wastewater service in Westlake is provided by the Seminole Improvement District, an independent special district. Nonresidential projects pay a one-time wastewater capital connection contribution of $7.71 per gallon of reserved daily capacity, under the district's developer-builder rate charges effective October 1, 2025. The district's board took up fiscal year 2027 rates on September 30, 2026 (a 2% or 3% increase); the adopted figure is not yet published.
    Requires confirmation
City$0.00
  • City Impact Fees (City of Westlake, Commercial)
    The City of Westlake code sets no municipal impact fee on nonresidential development. Nonresidential projects with building construction costs of $1,000,000 or more must contribute 1 percent of construction cost to the City art in public places fund or provide on-site artwork (Code Ch. 103), due before the first building permit. Palm Beach County impact fees apply.
    Requires confirmation
County$8.62/sq ft
Total (Westlake): $8.62/sq ft (≈ $430,920.50 at 50,000 sq ft)
Sources last checked Official fee schedule:Seminole Improvement District
Fees flagged "Requires confirmation" have no confirmed published amount. Confirm them with the jurisdiction or utility before budgeting.

Where in Palm Beach County Are You Building?

Each jurisdiction applies its own fee schedule. Pick yours. Totals shown are for a 50,000 sq ft building, including one-time water/sewer fees (assuming a 1-inch meter). * = one-time water/sewer connection charges only; no per-sq-ft impact fee schedule sourced for that jurisdiction. = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.

Unincorporated Palm Beach County$458,180.50Atlantis$418,665.00Includes unconfirmed feesBelle Glade$27,260.00*Boca Raton$428,028.00Boynton Beach$460,065.00Briny Breezes$418,665.00Includes unconfirmed feesCloud Lake$430,920.50Includes unconfirmed feesDelray Beach$421,064.96Glen Ridge$448,196.50Includes unconfirmed feesGolf$422,750.50Includes unconfirmed feesGreenacres$585,925.00Gulf Stream$419,990.00Includes unconfirmed feesHaverhill$446,696.50Includes unconfirmed feesHighland Beach$418,665.00Hypoluxo$429,790.00Includes unconfirmed feesJuno Beach$459,325.00Includes unconfirmed feesJupiter$535,428.35Includes unconfirmed feesJupiter Inlet Colony$430,331.35Includes unconfirmed feesLake Clarke Shores$426,835.00Includes unconfirmed feesLake Park$543,535.00Includes unconfirmed feesLake Worth Beach$442,190.00Includes unconfirmed feesLantana$437,368.00Includes unconfirmed feesLoxahatchee Groves$430,920.50Manalapan$418,665.00Includes unconfirmed feesMangonia Park$501,315.00Includes unconfirmed feesNorth Palm Beach$526,444.00Ocean Ridge$425,415.00Includes unconfirmed feesPahokee$27,260.00*Includes unconfirmed feesPalm Beach$426,758.75Palm Beach Gardens$720,750.00Includes unconfirmed feesPalm Beach Shores$495,425.00Includes unconfirmed feesPalm Springs$641,143.00Includes unconfirmed feesRiviera Beach$673,869.00Includes unconfirmed feesRoyal Palm Beach$609,395.00Includes unconfirmed feesSouth Bay$27,260.00*South Palm Beach$441,313.13Includes unconfirmed feesTequesta$441,099.49Includes unconfirmed feesWellington$841,772.00West Palm Beach$775,090.00
Westlake$430,920.50this pageIncludes unconfirmed fees

Westlake: Industrial Impact Fees

Industrial development in Westlake pays $2.40 per square foot in impact fees (rates sourced October 27, 2026).

For a 50,000 sq ft building, that comes to at least $119,940.00. The calculator below adjusts to your exact square footage.

The largest line items are Road (Fair Share) Impact Fee (Palm Beach County, Industrial) ($2.17/sq ft), Fire Rescue Impact Fee (Palm Beach County, Industrial) ($0.11/sq ft) and Public Buildings Impact Fee (Palm Beach County, Industrial) ($0.10/sq ft).

Wastewater Capital Connection Contribution (Seminole Improvement District) — per reserve gallon and Water Capital Connection Contribution (Seminole Improvement District) — per reserve gallon are set by the utility and not published online. City Impact Fees (City of Westlake, Industrial) is set by the city and has no published standard rate. Contact the levying jurisdiction or utility to verify before budgeting; they are not included as dollar figures here.

View the Full Westlake Impact Fee Schedule
Water$0.00
  • Water Capital Connection Contribution (Seminole Improvement District) — per reserve gallon
    Seminole Improvement District
    Water service in Westlake is provided by the Seminole Improvement District, an independent special district. Nonresidential projects pay a one-time water capital connection contribution of $12.71 per gallon of reserved daily capacity, under the district's developer-builder rate charges effective October 1, 2025. The district's board took up fiscal year 2027 rates on September 30, 2026 (a 2% or 3% increase); the adopted figure is not yet published.
    Requires confirmation
Sewer$0.00
  • Wastewater Capital Connection Contribution (Seminole Improvement District) — per reserve gallon
    Seminole Improvement District
    Wastewater service in Westlake is provided by the Seminole Improvement District, an independent special district. Nonresidential projects pay a one-time wastewater capital connection contribution of $7.71 per gallon of reserved daily capacity, under the district's developer-builder rate charges effective October 1, 2025. The district's board took up fiscal year 2027 rates on September 30, 2026 (a 2% or 3% increase); the adopted figure is not yet published.
    Requires confirmation
City$0.00
  • City Impact Fees (City of Westlake, Industrial)
    The City of Westlake code sets no municipal impact fee on nonresidential development. Nonresidential projects with building construction costs of $1,000,000 or more must contribute 1 percent of construction cost to the City art in public places fund or provide on-site artwork (Code Ch. 103), due before the first building permit. Palm Beach County impact fees apply.
    Requires confirmation
County$2.40/sq ft
Total (Westlake): $2.40/sq ft (≈ $119,940.00 at 50,000 sq ft)
Sources last checked Official fee schedule:Seminole Improvement District
Fees flagged "Requires confirmation" have no confirmed published amount. Confirm them with the jurisdiction or utility before budgeting.

Where in Palm Beach County Are You Building?

Each jurisdiction applies its own fee schedule. Pick yours. Totals shown are for a 50,000 sq ft building, including one-time water/sewer fees (assuming a 1-inch meter). * = one-time water/sewer connection charges only; no per-sq-ft impact fee schedule sourced for that jurisdiction. = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.

Unincorporated Palm Beach County$147,200.00Atlantis$113,715.00Includes unconfirmed feesBelle Glade$27,260.00*Boca Raton$123,078.00Boynton Beach$123,815.00Briny Breezes$113,715.00Includes unconfirmed feesCloud Lake$119,940.00Includes unconfirmed feesDelray Beach$116,114.96Glen Ridge$135,716.00Includes unconfirmed feesGolf$114,240.00Includes unconfirmed feesGreenacres$140,975.00Includes unconfirmed feesGulf Stream$115,040.00Includes unconfirmed feesHaverhill$135,716.00Includes unconfirmed feesHighland Beach$113,715.00Hypoluxo$124,840.00Includes unconfirmed feesJuno Beach$151,905.00Includes unconfirmed feesJupiter$139,077.35Includes unconfirmed feesJupiter Inlet Colony$117,211.35Includes unconfirmed feesLake Clarke Shores$119,415.00Includes unconfirmed feesLake Park$153,615.00Includes unconfirmed feesLake Worth Beach$134,770.00Includes unconfirmed feesLantana$129,948.00Includes unconfirmed feesLoxahatchee Groves$119,940.00Manalapan$113,715.00Includes unconfirmed feesMangonia Park$124,565.00Includes unconfirmed feesNorth Palm Beach$209,893.50Ocean Ridge$120,465.00Includes unconfirmed feesPahokee$27,260.00*Includes unconfirmed feesPalm Beach$121,808.75Palm Beach Gardens$265,500.00Includes unconfirmed feesPalm Beach Shores$190,475.00Includes unconfirmed feesPalm Springs$222,625.00Includes unconfirmed feesRiviera Beach$165,035.00Includes unconfirmed feesRoyal Palm Beach$177,125.00South Bay$27,260.00*South Palm Beach$133,893.13Includes unconfirmed feesTequesta$136,149.49Includes unconfirmed feesWellington$199,702.00West Palm Beach$217,090.00
Westlake$119,940.00this pageIncludes unconfirmed fees

Westlake: Office Impact Fees

Office development in Westlake pays $5.14 per square foot in impact fees (rates sourced October 27, 2026).

For a 25,000 sq ft building, that comes to at least $128,575.50. The calculator below adjusts to your exact square footage.

The largest line items are Road (Fair Share) Impact Fee (Palm Beach County, Office) ($4.87/sq ft), Public Buildings Impact Fee (Palm Beach County, Office) ($0.19/sq ft) and Fire Rescue Impact Fee (Palm Beach County, Office) ($0.07/sq ft).

Wastewater Capital Connection Contribution (Seminole Improvement District) — per reserve gallon and Water Capital Connection Contribution (Seminole Improvement District) — per reserve gallon are set by the utility and not published online. City Impact Fees (City of Westlake, Office) is set by the city and has no published standard rate. Contact the levying jurisdiction or utility to verify before budgeting; they are not included as dollar figures here.

View the Full Westlake Impact Fee Schedule
Water$0.00
  • Water Capital Connection Contribution (Seminole Improvement District) — per reserve gallon
    Seminole Improvement District
    Water service in Westlake is provided by the Seminole Improvement District, an independent special district. Nonresidential projects pay a one-time water capital connection contribution of $12.71 per gallon of reserved daily capacity, under the district's developer-builder rate charges effective October 1, 2025. The district's board took up fiscal year 2027 rates on September 30, 2026 (a 2% or 3% increase); the adopted figure is not yet published.
    Requires confirmation
Sewer$0.00
  • Wastewater Capital Connection Contribution (Seminole Improvement District) — per reserve gallon
    Seminole Improvement District
    Wastewater service in Westlake is provided by the Seminole Improvement District, an independent special district. Nonresidential projects pay a one-time wastewater capital connection contribution of $7.71 per gallon of reserved daily capacity, under the district's developer-builder rate charges effective October 1, 2025. The district's board took up fiscal year 2027 rates on September 30, 2026 (a 2% or 3% increase); the adopted figure is not yet published.
    Requires confirmation
City$0.00
  • City Impact Fees (City of Westlake, Office)
    The City of Westlake code sets no municipal impact fee on nonresidential development. Nonresidential projects with building construction costs of $1,000,000 or more must contribute 1 percent of construction cost to the City art in public places fund or provide on-site artwork (Code Ch. 103), due before the first building permit. Palm Beach County impact fees apply.
    Requires confirmation
County$5.14/sq ft
Total (Westlake): $5.14/sq ft (≈ $128,575.50 at 25,000 sq ft)
Sources last checked Official fee schedule:Seminole Improvement District
Fees flagged "Requires confirmation" have no confirmed published amount. Confirm them with the jurisdiction or utility before budgeting.

Where in Palm Beach County Are You Building?

Each jurisdiction applies its own fee schedule. Pick yours. Totals shown are for a 25,000 sq ft building, including one-time water/sewer fees (assuming a 1-inch meter). * = one-time water/sewer connection charges only; no per-sq-ft impact fee schedule sourced for that jurisdiction. = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.

Unincorporated Palm Beach County$155,835.50Atlantis$126,421.25Includes unconfirmed feesBelle Glade$27,260.00*Boca Raton$135,784.25Boynton Beach$140,996.25Briny Breezes$126,421.25Includes unconfirmed feesCloud Lake$128,575.50Includes unconfirmed feesDelray Beach$128,821.21Glen Ridge$145,851.50Includes unconfirmed feesGolf$126,794.25Includes unconfirmed feesGreenacres$223,681.25Gulf Stream$127,746.25Includes unconfirmed feesHaverhill$144,351.50Includes unconfirmed feesHighland Beach$126,421.25Hypoluxo$137,546.25Includes unconfirmed feesJuno Beach$145,797.50Includes unconfirmed feesJupiter$156,256.35Includes unconfirmed feesJupiter Inlet Colony$129,917.60Includes unconfirmed feesLake Clarke Shores$128,202.50Includes unconfirmed feesLake Park$162,152.50Includes unconfirmed feesLake Worth Beach$143,557.50Includes unconfirmed feesLantana$138,735.50Includes unconfirmed feesLoxahatchee Groves$128,575.50Manalapan$126,421.25Includes unconfirmed feesMangonia Park$135,021.25Includes unconfirmed feesNorth Palm Beach$184,051.00Ocean Ridge$133,171.25Includes unconfirmed feesPahokee$27,260.00*Includes unconfirmed feesPalm Beach$134,515.00Palm Beach Gardens$221,475.00Includes unconfirmed feesPalm Beach Shores$178,431.25Includes unconfirmed feesPalm Springs$240,732.50Includes unconfirmed feesRiviera Beach$179,624.50Includes unconfirmed feesRoyal Palm Beach$174,658.50South Bay$27,260.00*South Palm Beach$142,680.63Includes unconfirmed feesTequesta$144,605.74Includes unconfirmed feesWellington$228,089.50West Palm Beach$251,096.25
Westlake$128,575.50this pageIncludes unconfirmed fees

Westlake Impact Fee Calculator

Estimate impact fees for your project. Set to single-family. Drop a pin or search an address for site-specific fees.

Location

Select a location to begin

Once you select an address or drop a pin, we'll identify the responsible city and county and generate a fee breakdown.

Water & Sewer
Transportation
Parks
Schools
Fire & Police
General

How Impact Fees Work in Florida

Florida impact fees are one-time charges on new development, governed by Section 163.31801, Florida Statutes (the Florida Impact Fee Act). The statute requires fees to be based on the most recent and localized data, spent on the infrastructure category they were collected for, and adopted by ordinance.

Since a 2021 amendment (Ch. 2021-63, Laws of Florida), the law also limits how fast fees can rise: increases up to 25% phase in over two years, increases of 25–50% phase in over four years, and increases above 50% are allowed only with a demonstrated extraordinary-circumstances study and at least a two-thirds vote of the governing body.

Counties and cities can both levy impact fees. Inside an incorporated city, a project typically pays the county's countywide fees plus any municipal fees the city has adopted, which is why totals differ between a city and the unincorporated county around it.

New to impact fees? Our plain-English guide explains what they cover, who pays them, and why they exist.

Summary current as of September 2026. This is an editorial summary, not legal advice; see the official statute text and our terms of use.

Westlake Impact Fee FAQs

What are the total impact fees for a single-family home in Westlake, Florida?

A new single-family home in Westlake pays at least $21,199.32 per unit in combined impact fees (rates sourced October 27, 2026). This figure includes amounts that have not been confirmed and excludes fees with no published standard amount, so the full cost may be higher; verify before budgeting.

How much are commercial impact fees in Westlake?

Commercial development in Westlake pays $8.62 per square foot in impact fees, at least $430,920.50 for a 50,000 sq ft building. 3 additional fees have no published standard amounts and are not included, so the full cost may be higher; verify before budgeting.

Does Westlake charge its own impact fees?

Yes. Westlake levies its own municipal impact or utility fees, and county-levied fees also apply inside city limits. The schedule on this page shows every fee that applies to development in Westlake, with the combined total.

Can Florida impact fees increase at any time?

No. Section 163.31801, Florida Statutes limits increases to 50% at most, phased in over two to four years, unless the local government makes extraordinary-circumstances findings and approves the increase by at least a two-thirds vote.

Fee amounts on this page are compiled from official published schedules and are provided for planning purposes only. Rates change, and project specifics (unit size, meter size, location within special districts) can alter what applies. Always verify current fees with the jurisdiction and utility before relying on them.

Compare unincorporated rates and every other city on the Palm Beach County impact fees page.

Missing a jurisdiction? Get in touch.

Request coverage for a city or county, report an issue, ask about enterprise access, or inquire about sponsorship opportunities. We typically reply within one business day.

0/1000