Parker Impact Fees by Project Type
Parker: Single-Family Impact Fees
A new single-family home in Parker pays $11,269.17 per unit in impact fees (rates sourced November 19, 2026). Every line item is levied at the municipal or utility level.
The largest line items are Water Impact Fee (City of Parker) — 1" meter ($8,269.17) and Water Meter Fee (City of Parker) — 1" meter requiring tap ($3,000.00).
Some fees are tiered by unit size or building type; amounts reflect the representative tier noted in the schedule below.
View the Full Parker Impact Fee Schedule
- Water Impact Fee (City of Parker) — 1" meter$8,269.17City of ParkerWater impact fee per 1 inch meter (1 living unit equivalent, the city's standard home meter); a 2 inch meter pays $33,076.67.
- Water Meter Fee (City of Parker) — 1" meter requiring tap$3,000.001", new tapCity of ParkerOne-time meter fee for a 1 inch meter requiring a new tap, including up to 100 feet of service line; $2,000 where a tap already exists. Road bores are billed at cost plus 10%.
- Sewer Connection Fee (City of Parker) — On-site septic$0.00City of ParkerMost of Parker uses private septic systems, with no sewer connection fee. Homes in the northeast area served by city sewer pay a $1,500 connection fee.
- City Impact Fee (City of Parker)$0.00City of ParkerParker charges no roadway, park or other city impact fee on new homes; its water impact fee is listed separately.
- County Impact Fee (Collin County)$0.00Collin CountyCollin County does not charge impact fees on residential development. Texas counties may levy impact fees only for drainage, and only in or next to counties of 3.3 million or more residents.
Where in Collin County Are You Building?
Each jurisdiction applies its own fee schedule. Pick yours. = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.
Parker: Multifamily Impact Fees
A new multifamily unit in Parker pays $11,269.17 per unit in impact fees (rates sourced November 19, 2026). Every line item is levied at the municipal or utility level.
The largest line items are Water Impact Fee (City of Parker, MF) — 1" meter ($8,269.17) and Water Meter Fee (City of Parker, MF) — 1" meter requiring tap ($3,000.00).
Some fees are tiered by unit size or building type; amounts reflect the representative tier noted in the schedule below.
View the Full Parker Impact Fee Schedule
- Water Impact Fee (City of Parker, MF) — 1" meter$8,269.17City of ParkerWater impact fee by meter size, shown at the 1 inch meter (1 living unit equivalent); a building on one master meter pays by its size (2 inch: $33,076.67).
- Water Meter Fee (City of Parker, MF) — 1" meter requiring tap$3,000.001", new tapCity of ParkerOne-time meter fee per meter, $3,000 for a 1 inch meter requiring a new tap; a building on one meter pays once.
- Sewer Connection Fee (City of Parker, MF) — On-site septic$0.00City of ParkerMost of Parker uses private septic systems, with no sewer connection fee. Buildings in the northeast area served by city sewer pay a $1,500 connection fee per connection.
- City Impact Fee (City of Parker, MF)$0.00City of ParkerParker charges no roadway, park or other city impact fee; its water impact fee is listed separately.
- County Impact Fee (Collin County, MF)$0.00Collin CountyCollin County does not charge impact fees on residential development. Texas counties may levy impact fees only for drainage, and only in or next to counties of 3.3 million or more residents.
Where in Collin County Are You Building?
Each jurisdiction applies its own fee schedule. Pick yours. = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.
Parker: Commercial Impact Fees
Commercial development in Parker pays no per-square-foot impact fees, but owes $11,269.17 in one-time water and sewer connection fees (rates sourced November 19, 2026).
For a 50,000 sq ft building, that comes to about $11,269.17. The calculator below adjusts to your exact square footage.
The largest line items are Water Impact Fee (City of Parker) — 1" meter ($8,269.17 one-time) and Water Meter and Tap Fee (City of Parker) — 1" meter requiring tap ($3,000.00 one-time).
Water and sewer connection fees assume a 1-inch meter; larger services pay more. See the meter-size tiers in the source schedules.
View the Full Parker Impact Fee Schedule
- Water Impact Fee (City of Parker) — 1" meter$8,269.17 one-timeCity of ParkerParker water impact fee for a 1 inch meter (one living unit equivalent), set December 2023; a 2 inch meter (four LUE) pays $33,076.67. The rate in effect when the plat is recorded applies. Charged in addition to the meter and tap fee.
- Water Meter and Tap Fee (City of Parker) — 1" meter requiring tap$3,000.00 one-time1" requiring tapCity of ParkerParker water meter and tap fee for a 1 inch meter requiring a new tap, including up to 100 feet of service line ($4,500 for 2 inch; $2,000 for a 1 inch meter on an existing tap). Road bores are billed at cost plus 10%. Charged in addition to the water impact fee.
- Sewer Connection Fee — On-site septic (no city sewer)$0.00City of ParkerMost of Parker has no city sewer, so commercial, office and industrial sites use on-site septic systems and pay no sewer connection fee. Where city sewer is available (the northeast part of the city), the city sewer connection fee applies instead.
- $0.00
- Roadway Impact Fee (City of Parker, Commercial)$0.00City of ParkerParker does not charge a roadway or other city impact fee on nonresidential development; its only impact fee is for water.
- County Impact Fee (Collin County, Commercial)$0.00Collin CountyCollin County does not charge impact fees on nonresidential development. Texas counties may levy impact fees only for drainage, and only in or next to counties of 3.3 million or more residents.
Where in Collin County Are You Building?
Each jurisdiction applies its own fee schedule. Pick yours. Totals shown are for a 50,000 sq ft building, including water/sewer fees (one-time connection fees assume a 1-inch meter). * = one-time water/sewer connection charges only; no per-sq-ft impact fee schedule sourced for that jurisdiction. = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.
Parker: Industrial Impact Fees
Industrial development in Parker pays no per-square-foot impact fees, but owes $11,269.17 in one-time water and sewer connection fees (rates sourced November 19, 2026).
For a 50,000 sq ft building, that comes to about $11,269.17. The calculator below adjusts to your exact square footage.
The largest line items are Water Impact Fee (City of Parker) — 1" meter ($8,269.17 one-time) and Water Meter and Tap Fee (City of Parker) — 1" meter requiring tap ($3,000.00 one-time).
Water and sewer connection fees assume a 1-inch meter; larger services pay more. See the meter-size tiers in the source schedules.
View the Full Parker Impact Fee Schedule
- Water Impact Fee (City of Parker) — 1" meter$8,269.17 one-timeCity of ParkerParker water impact fee for a 1 inch meter (one living unit equivalent), set December 2023; a 2 inch meter (four LUE) pays $33,076.67. The rate in effect when the plat is recorded applies. Charged in addition to the meter and tap fee.
- Water Meter and Tap Fee (City of Parker) — 1" meter requiring tap$3,000.00 one-time1" requiring tapCity of ParkerParker water meter and tap fee for a 1 inch meter requiring a new tap, including up to 100 feet of service line ($4,500 for 2 inch; $2,000 for a 1 inch meter on an existing tap). Road bores are billed at cost plus 10%. Charged in addition to the water impact fee.
- Sewer Connection Fee — On-site septic (no city sewer)$0.00City of ParkerMost of Parker has no city sewer, so commercial, office and industrial sites use on-site septic systems and pay no sewer connection fee. Where city sewer is available (the northeast part of the city), the city sewer connection fee applies instead.
- $0.00
- Roadway Impact Fee (City of Parker, Industrial)$0.00City of ParkerParker does not charge a roadway or other city impact fee on nonresidential development; its only impact fee is for water.
- County Impact Fee (Collin County, Industrial)$0.00Collin CountyCollin County does not charge impact fees on nonresidential development. Texas counties may levy impact fees only for drainage, and only in or next to counties of 3.3 million or more residents.
Where in Collin County Are You Building?
Each jurisdiction applies its own fee schedule. Pick yours. Totals shown are for a 50,000 sq ft building, including water/sewer fees (one-time connection fees assume a 1-inch meter). * = one-time water/sewer connection charges only; no per-sq-ft impact fee schedule sourced for that jurisdiction. = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.
Parker: Office Impact Fees
Office development in Parker pays no per-square-foot impact fees, but owes $11,269.17 in one-time water and sewer connection fees (rates sourced November 19, 2026).
For a 25,000 sq ft building, that comes to about $11,269.17. The calculator below adjusts to your exact square footage.
The largest line items are Water Impact Fee (City of Parker) — 1" meter ($8,269.17 one-time) and Water Meter and Tap Fee (City of Parker) — 1" meter requiring tap ($3,000.00 one-time).
Water and sewer connection fees assume a 1-inch meter; larger services pay more. See the meter-size tiers in the source schedules.
View the Full Parker Impact Fee Schedule
- Water Impact Fee (City of Parker) — 1" meter$8,269.17 one-timeCity of ParkerParker water impact fee for a 1 inch meter (one living unit equivalent), set December 2023; a 2 inch meter (four LUE) pays $33,076.67. The rate in effect when the plat is recorded applies. Charged in addition to the meter and tap fee.
- Water Meter and Tap Fee (City of Parker) — 1" meter requiring tap$3,000.00 one-time1" requiring tapCity of ParkerParker water meter and tap fee for a 1 inch meter requiring a new tap, including up to 100 feet of service line ($4,500 for 2 inch; $2,000 for a 1 inch meter on an existing tap). Road bores are billed at cost plus 10%. Charged in addition to the water impact fee.
- Sewer Connection Fee — On-site septic (no city sewer)$0.00City of ParkerMost of Parker has no city sewer, so commercial, office and industrial sites use on-site septic systems and pay no sewer connection fee. Where city sewer is available (the northeast part of the city), the city sewer connection fee applies instead.
- $0.00
- Roadway Impact Fee (City of Parker, Office)$0.00City of ParkerParker does not charge a roadway or other city impact fee on nonresidential development; its only impact fee is for water.
- County Impact Fee (Collin County, Office)$0.00Collin CountyCollin County does not charge impact fees on nonresidential development. Texas counties may levy impact fees only for drainage, and only in or next to counties of 3.3 million or more residents.
Where in Collin County Are You Building?
Each jurisdiction applies its own fee schedule. Pick yours. Totals shown are for a 25,000 sq ft building, including water/sewer fees (one-time connection fees assume a 1-inch meter). * = one-time water/sewer connection charges only; no per-sq-ft impact fee schedule sourced for that jurisdiction. = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.
Parker Impact Fee Calculator
Estimate impact fees for your project. Set to single-family. Drop a pin or search an address for site-specific fees.
Location
Select a location to begin
Once you select an address or drop a pin, we'll identify the responsible city and county and generate a fee breakdown.
How Impact Fees Work in Texas
Texas cities, and certain special districts and authorities, assess impact fees under Chapter 395 of the Local Government Code and, with narrow exceptions, may charge one only by following it. A fee rests on adopted land use assumptions and a capital improvements plan, and imposing one takes the votes of two-thirds of the governing body's members.
Impact fees may fund only water supply, treatment and distribution; wastewater collection and treatment; storm water, drainage and flood control; and roadway facilities. Parks, schools, police and fire facilities are not on the chapter's list. The chapter does not treat park land dedication, or a payment in its place, as an impact fee, so a city can require that separately. The fee per service unit is capped at the plan's growth-related cost, less a required credit, divided by the projected service units. Counties generally cannot charge impact fees: the chapter gives that authority only to counties of 3.3 million or more people and the counties bordering them, and only for storm water, drainage and flood control. Since September 2025 a city also may not charge an impact fee where an office, retail or warehouse building at least five years old is converted to multifamily or mixed-use residential use (at least 65 percent of the building and of each usable floor), unless the land was already subject to an impact fee before the conversion's building permit was filed (Section 218.204).
For land platted after a fee is adopted, the fee is assessed no later than when the plat is recorded, which fixes the most that can be charged per service unit. Where water and wastewater capacity is available, it is generally collected when the building permit is issued, or when a water or wastewater meter connection is applied for on land outside city limits or where the entity charging the fee issues no building permits. A fee not spent as the chapter allows within 10 years of payment must generally be refunded with interest, and the land use assumptions and capital improvements plan are updated at least every five years unless the governing body formally determines that no update is needed.
A city may charge water, wastewater and drainage impact fees in its extraterritorial jurisdiction as well as inside its limits, but roadway impact fees stop at the city limits. Where a utility district or another provider supplies water or sewer instead of the city, its charges are separate from the city's, so the total can differ between a city, its neighbors and the unincorporated land around it.
For a primer on how impact fees work, see our plain-English guide.
Summary current as of November 2026. This is an editorial summary, not legal advice; see the official statute text and our terms of use.
Parker Impact Fee FAQs
What are the total impact fees for a single-family home in Parker, Texas?
A new single-family home in Parker pays $11,269.17 per unit in combined impact fees (rates sourced November 19, 2026).
How much are commercial impact fees in Parker?
Commercial development in Parker pays no per-square-foot impact fees, but owes $11,269.17 in one-time water and sewer connection fees (assuming a 1-inch meter).
Does Parker charge its own impact fees?
Yes. Parker levies its own municipal impact or utility fees. Collin County does not currently add county-level impact fees inside Parker. The schedule on this page shows every fee that applies to development in Parker.
Can a Texas impact fee increase at any time?
No. Under Section 395.0515 of the Local Government Code, added in 2025, a city or district may not increase an impact fee for three years from the later of the date the fee was adopted or last increased, although it may phase in collection up to the adopted maximum over no more than ten years. An increase also needs an independent financial audit and a public hearing on its results first (Section 395.059), and the measure approving it cannot be adopted as an emergency measure (Section 395.057). Once a fee is assessed on a tract, it cannot be raised for that tract unless the number of service units increases (Section 395.017). Charges set by a separate water or sewer provider may follow different rules.
Fee amounts on this page are compiled from official published schedules and are provided for planning purposes only. Rates change, and project specifics (unit size, meter size, location within special districts) can alter what applies. Always verify current fees with the jurisdiction and utility before relying on them.
Compare unincorporated rates and every other city on the Collin County impact fees page.