Skip to content
IMPACTFEES.ORG

Denton County, Texas Impact Fees

Impact fees in Denton County depend on where you build. This page details the rates for unincorporated Denton County: at least $6,250.00 per single-family unit as of . One additional fee has no published standard amount and is not included, so the full cost may be higher; verify before budgeting. Lantana is an unincorporated community. In Texas the city whose extraterritorial jurisdiction covers a site can charge water, wastewater and drainage impact fees there, and a utility district can charge its own fees, so new construction outside city limits may still owe them. Inside city limits, each city applies its own schedule and fees may be completely different. Pick your city below.

Denton County Impact Fees by Project Type

Where in Denton County Are You Building?

Each jurisdiction applies its own fee schedule. Pick yours. = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.

Unincorporated Denton County: Single-Family Impact Fees

A new single-family home in unincorporated Denton County pays at least $6,250.00 per unit in impact fees (rates sourced November 25, 2026). Every line item is levied at the municipal or utility level.

The largest line items are Water Connection Fee — Mustang SUD, 5/8" x 3/4" meter: $5,750 + $500 water resource ($6,250.00).

Sewer Connection Fee — On-site septic system is set by the utility and not published online. Contact the levying jurisdiction or utility to verify before budgeting; it is not included as a dollar figure here.

Some fees are tiered by unit size or building type; amounts reflect the representative tier noted in the schedule below.

View the Full Denton County Impact Fee Schedule
Water$6,250.00
  • Water Connection Fee — Mustang SUD, 5/8" x 3/4" meter: $5,750 + $500 water resource
    Mustang Special Utility District
    Mustang Special Utility District, the largest water provider in unincorporated Denton County, charges $5,750 (meter included) plus a $500 water resource fee to connect a home on an existing water line, under its Rate Order effective September 5, 2026. A lot in a new subdivision pays $5,750 plus a $750 meter installation and the $500 fee, and the developer pays a $3,000 service investigation fee per project. Other parts of the county are served by water supply corporations and districts with their own charges.
    $6,250.00
Sewer$0.00
  • Sewer Connection Fee — On-site septic system
    Denton County (OSSF permit, not an impact fee)
    Most unincorporated parcels use private septic systems (no sewer connection fee). In master-planned municipal utility district areas, the district provides sewer and sets its own connection fee.
    Requires confirmation
City$0.00
County$0.00
  • County Impact Fee (Denton County)
    Denton County
    Texas law lets a county charge an impact fee only for drainage, and only where the county has at least 3.3 million residents or borders one that does. Denton County does not qualify, so no county impact fee applies.
    $0.00
Total (unincorporated Denton County): $6,250.00
Sources last checked Official fee schedules:Mustang Special Utility District Denton County (OSSF permit, not an impact fee) Denton County
Fees flagged "Requires confirmation" have no confirmed published amount. Confirm them with the jurisdiction or utility before budgeting.

Where in Denton County Are You Building?

Each jurisdiction applies its own fee schedule. Pick yours. = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.

Unincorporated Denton County: Multifamily Impact Fees

A new multifamily unit in unincorporated Denton County pays at least $3,125.00 per unit in impact fees (rates sourced November 25, 2026). Every line item is levied at the municipal or utility level.

The largest line items are Water Connection Fee (MF) — Mustang SUD: 0.5 ESFU × ($5,750 + $500) ($3,125.00).

Sewer Connection Fee (MF) — On-site septic system is set by the utility and not published online. Contact the levying jurisdiction or utility to verify before budgeting; it is not included as a dollar figure here.

Some fees are tiered by unit size or building type; amounts reflect the representative tier noted in the schedule below.

View the Full Denton County Impact Fee Schedule
Water$3,125.00
  • Water Connection Fee (MF) — Mustang SUD: 0.5 ESFU × ($5,750 + $500)
    Mustang Special Utility District
    Mustang Special Utility District, the largest water provider in unincorporated Denton County, charges multifamily projects 0.5 equivalent unit per apartment: $2,875 connection plus a $250 water resource fee per unit (Rate Order effective September 5, 2026). Other areas are served by water supply corporations and districts with their own charges.
    $3,125.00
Sewer$0.00
City$0.00
County$0.00
  • County Impact Fee (Denton County, MF)
    Denton County
    Texas law lets a county charge an impact fee only for drainage, and only where the county has at least 3.3 million residents or borders one that does. Denton County does not qualify, so no county impact fee applies.
    $0.00
Total (unincorporated Denton County): $3,125.00
Sources last checked Official fee schedules:Mustang Special Utility District Denton County (OSSF permit, not an impact fee) Denton County
Fees flagged "Requires confirmation" have no confirmed published amount. Confirm them with the jurisdiction or utility before budgeting.

Where in Denton County Are You Building?

Each jurisdiction applies its own fee schedule. Pick yours. Totals shown are for a 50,000 sq ft building, including water/sewer fees (one-time connection fees assume a 1-inch meter). * = one-time water/sewer connection charges only; no per-sq-ft impact fee schedule sourced for that jurisdiction. = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.

Unincorporated Denton County: Commercial Impact Fees

Commercial development in unincorporated Denton County pays no per-square-foot impact fees, but owes $19,375.00 in one-time water and sewer connection fees (rates sourced November 25, 2026).

For a 50,000 sq ft building, that comes to at least $19,375.00. The calculator below adjusts to your exact square footage.

The largest line items are Water Connection Fee — Mustang SUD, 1" meter: 2.5 LUE × ($5,750 + $500) + $750 meter + $3,000 investigation ($19,375.00 one-time).

Water and sewer connection fees assume a 1-inch meter; larger services pay more. See the meter-size tiers in the source schedules.

Sewer Connection Fee — No public sewer (on-site septic) is set by the utility and not published online. Contact the levying jurisdiction or utility to verify before budgeting; it is not included as a dollar figure here.

View the Full Denton County Impact Fee Schedule
Water$19,375.00 one-time
  • Water Connection Fee — Mustang SUD, 1" meter: 2.5 LUE × ($5,750 + $500) + $750 meter + $3,000 investigation
    Mustang Special Utility District
    Mustang Special Utility District, the largest water provider in unincorporated Denton County, treats most nonresidential service as non-standard: $5,750 per LUE connection fee plus a $500 per LUE water resource fee, a $750 meter installation and a $3,000 service investigation fee per project (projects over 250 meter equivalents add $10 each). LUEs follow AWWA meter factors (1 inch = 2.5). Rate Order effective September 5, 2026. Other parts of the unincorporated county are served by other water supply corporations and districts with their own charges, and line extensions or road bores are billed at cost.
    $19,375.00 one-time
Sewer$0.00
  • Sewer Connection Fee — No public sewer (on-site septic)
    No public sewer (septic)
    Denton County
    Much of unincorporated Denton County has no public sewer and relies on on-site septic systems. In master-planned areas a utility district provides sewer and charges its own connection fee; Mustang Special Utility District's charges are listed as options.
    Requires confirmation
City$0.00
County$0.00
  • County Impact Fee (Denton County, Commercial)
    Denton County
    Texas counties cannot levy impact fees under Local Government Code Chapter 395, so Denton County charges no county impact fee on commercial, office or industrial development.
    $0.00
Total (unincorporated Denton County): $19,375.00 one-time (≈ $19,375.00 at 50,000 sq ft)
Sources last checked Official fee schedules:Mustang Special Utility District Denton County
Fees flagged "Requires confirmation" have no confirmed published amount. Confirm them with the jurisdiction or utility before budgeting.
Water/sewer connection fees assume a 1-inch meter; larger services pay more.

Where in Denton County Are You Building?

Each jurisdiction applies its own fee schedule. Pick yours. Totals shown are for a 50,000 sq ft building, including water/sewer fees (one-time connection fees assume a 1-inch meter). * = one-time water/sewer connection charges only; no per-sq-ft impact fee schedule sourced for that jurisdiction. = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.

Unincorporated Denton County: Industrial Impact Fees

Industrial development in unincorporated Denton County pays no per-square-foot impact fees, but owes $19,375.00 in one-time water and sewer connection fees (rates sourced November 25, 2026).

For a 50,000 sq ft building, that comes to at least $19,375.00. The calculator below adjusts to your exact square footage.

The largest line items are Water Connection Fee — Mustang SUD, 1" meter: 2.5 LUE × ($5,750 + $500) + $750 meter + $3,000 investigation ($19,375.00 one-time).

Water and sewer connection fees assume a 1-inch meter; larger services pay more. See the meter-size tiers in the source schedules.

Sewer Connection Fee — No public sewer (on-site septic) is set by the utility and not published online. Contact the levying jurisdiction or utility to verify before budgeting; it is not included as a dollar figure here.

View the Full Denton County Impact Fee Schedule
Water$19,375.00 one-time
  • Water Connection Fee — Mustang SUD, 1" meter: 2.5 LUE × ($5,750 + $500) + $750 meter + $3,000 investigation
    Mustang Special Utility District
    Mustang Special Utility District, the largest water provider in unincorporated Denton County, treats most nonresidential service as non-standard: $5,750 per LUE connection fee plus a $500 per LUE water resource fee, a $750 meter installation and a $3,000 service investigation fee per project (projects over 250 meter equivalents add $10 each). LUEs follow AWWA meter factors (1 inch = 2.5). Rate Order effective September 5, 2026. Other parts of the unincorporated county are served by other water supply corporations and districts with their own charges, and line extensions or road bores are billed at cost.
    $19,375.00 one-time
Sewer$0.00
  • Sewer Connection Fee — No public sewer (on-site septic)
    No public sewer (septic)
    Denton County
    Much of unincorporated Denton County has no public sewer and relies on on-site septic systems. In master-planned areas a utility district provides sewer and charges its own connection fee; Mustang Special Utility District's charges are listed as options.
    Requires confirmation
City$0.00
County$0.00
  • County Impact Fee (Denton County, Industrial)
    Denton County
    Texas counties cannot levy impact fees under Local Government Code Chapter 395, so Denton County charges no county impact fee on commercial, office or industrial development.
    $0.00
Total (unincorporated Denton County): $19,375.00 one-time (≈ $19,375.00 at 50,000 sq ft)
Sources last checked Official fee schedules:Mustang Special Utility District Denton County
Fees flagged "Requires confirmation" have no confirmed published amount. Confirm them with the jurisdiction or utility before budgeting.
Water/sewer connection fees assume a 1-inch meter; larger services pay more.

Where in Denton County Are You Building?

Each jurisdiction applies its own fee schedule. Pick yours. Totals shown are for a 25,000 sq ft building, including water/sewer fees (one-time connection fees assume a 1-inch meter). * = one-time water/sewer connection charges only; no per-sq-ft impact fee schedule sourced for that jurisdiction. = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.

Unincorporated Denton County: Office Impact Fees

Office development in unincorporated Denton County pays no per-square-foot impact fees, but owes $19,375.00 in one-time water and sewer connection fees (rates sourced November 25, 2026).

For a 25,000 sq ft building, that comes to at least $19,375.00. The calculator below adjusts to your exact square footage.

The largest line items are Water Connection Fee — Mustang SUD, 1" meter: 2.5 LUE × ($5,750 + $500) + $750 meter + $3,000 investigation ($19,375.00 one-time).

Water and sewer connection fees assume a 1-inch meter; larger services pay more. See the meter-size tiers in the source schedules.

Sewer Connection Fee — No public sewer (on-site septic) is set by the utility and not published online. Contact the levying jurisdiction or utility to verify before budgeting; it is not included as a dollar figure here.

View the Full Denton County Impact Fee Schedule
Water$19,375.00 one-time
  • Water Connection Fee — Mustang SUD, 1" meter: 2.5 LUE × ($5,750 + $500) + $750 meter + $3,000 investigation
    Mustang Special Utility District
    Mustang Special Utility District, the largest water provider in unincorporated Denton County, treats most nonresidential service as non-standard: $5,750 per LUE connection fee plus a $500 per LUE water resource fee, a $750 meter installation and a $3,000 service investigation fee per project (projects over 250 meter equivalents add $10 each). LUEs follow AWWA meter factors (1 inch = 2.5). Rate Order effective September 5, 2026. Other parts of the unincorporated county are served by other water supply corporations and districts with their own charges, and line extensions or road bores are billed at cost.
    $19,375.00 one-time
Sewer$0.00
  • Sewer Connection Fee — No public sewer (on-site septic)
    No public sewer (septic)
    Denton County
    Much of unincorporated Denton County has no public sewer and relies on on-site septic systems. In master-planned areas a utility district provides sewer and charges its own connection fee; Mustang Special Utility District's charges are listed as options.
    Requires confirmation
City$0.00
County$0.00
  • County Impact Fee (Denton County, Office)
    Denton County
    Texas counties cannot levy impact fees under Local Government Code Chapter 395, so Denton County charges no county impact fee on commercial, office or industrial development.
    $0.00
Total (unincorporated Denton County): $19,375.00 one-time (≈ $19,375.00 at 25,000 sq ft)
Sources last checked Official fee schedules:Mustang Special Utility District Denton County
Fees flagged "Requires confirmation" have no confirmed published amount. Confirm them with the jurisdiction or utility before budgeting.
Water/sewer connection fees assume a 1-inch meter; larger services pay more.

Denton County Impact Fee Calculator

Estimate impact fees for your project. Set to single-family. Drop a pin or search an address for site-specific fees.

Location

Select a location to begin

Once you select an address or drop a pin, we'll identify the responsible city and county and generate a fee breakdown.

Water & Sewer
Transportation
Parks
Schools
Fire & Police
General

How Impact Fees Work in Texas

Texas cities, and certain special districts and authorities, assess impact fees under Chapter 395 of the Local Government Code and, with narrow exceptions, may charge one only by following it. A fee rests on adopted land use assumptions and a capital improvements plan, and imposing one takes the votes of two-thirds of the governing body's members.

Impact fees may fund only water supply, treatment and distribution; wastewater collection and treatment; storm water, drainage and flood control; and roadway facilities. Parks, schools, police and fire facilities are not on the chapter's list. The chapter does not treat park land dedication, or a payment in its place, as an impact fee, so a city can require that separately. The fee per service unit is capped at the plan's growth-related cost, less a required credit, divided by the projected service units. Counties generally cannot charge impact fees: the chapter gives that authority only to counties of 3.3 million or more people and the counties bordering them, and only for storm water, drainage and flood control. Since September 2025 a city also may not charge an impact fee where an office, retail or warehouse building at least five years old is converted to multifamily or mixed-use residential use (at least 65 percent of the building and of each usable floor), unless the land was already subject to an impact fee before the conversion's building permit was filed (Section 218.204).

For land platted after a fee is adopted, the fee is assessed no later than when the plat is recorded, which fixes the most that can be charged per service unit. Where water and wastewater capacity is available, it is generally collected when the building permit is issued, or when a water or wastewater meter connection is applied for on land outside city limits or where the entity charging the fee issues no building permits. A fee not spent as the chapter allows within 10 years of payment must generally be refunded with interest, and the land use assumptions and capital improvements plan are updated at least every five years unless the governing body formally determines that no update is needed.

A city may charge water, wastewater and drainage impact fees in its extraterritorial jurisdiction as well as inside its limits, but roadway impact fees stop at the city limits. Where a utility district or another provider supplies water or sewer instead of the city, its charges are separate from the city's, so the total can differ between a city, its neighbors and the unincorporated land around it.

If you're still asking what are impact fees, start with our guide to the definition, common categories, and legal basis.

Summary current as of November 2026. This is an editorial summary, not legal advice; see the official statute text and our terms of use.

Denton County Impact Fee FAQs

What are single-family impact fees in Denton County, Texas?

A new single-family home in unincorporated Denton County pays at least $6,250.00 per unit in impact fees (rates sourced November 25, 2026). One additional fee has no published standard amount and is not included, so the full cost may be higher; verify before budgeting. Inside city limits, fees are set by each city's own schedule and may be completely different. See the city pages for their rates.

How much are multifamily impact fees in Denton County?

Multifamily development in unincorporated Denton County pays at least $3,125.00 per unit in impact fees (rates sourced November 25, 2026). One additional fee has no published standard amount and is not included, so the full cost may be higher; verify before budgeting. Rates inside city limits depend on the municipality. Pick your city on this page.

How much are commercial impact fees in Denton County?

Commercial development in unincorporated Denton County pays no per-square-foot impact fees, but owes $19,375.00 in one-time water and sewer connection fees (assuming a 1-inch meter). One additional fee has no published standard amount and is not included, so the full cost may be higher; verify before budgeting.

Does Lantana pay Denton County impact fees?

Lantana is unincorporated, so the Denton County charges on this page apply there. In Texas the city whose extraterritorial jurisdiction covers a site can charge water, wastewater and drainage impact fees there, and a utility district can charge its own fees, so new construction outside city limits may still owe them. Search a specific address in the calculator below to confirm it sits outside every city limit.

Do cities in Denton County charge their own impact fees?

Yes. Every incorporated city applies its own fee schedule. 32 of 32 cities in Denton County levy municipal impact or utility fees; each city page shows the full schedule that applies inside its limits.

Can a Texas impact fee increase at any time?

No. Under Section 395.0515 of the Local Government Code, added in 2025, a city or district may not increase an impact fee for three years from the later of the date the fee was adopted or last increased, although it may phase in collection up to the adopted maximum over no more than ten years. An increase also needs an independent financial audit and a public hearing on its results first (Section 395.059), and the measure approving it cannot be adopted as an emergency measure (Section 395.057). Once a fee is assessed on a tract, it cannot be raised for that tract unless the number of service units increases (Section 395.017). Charges set by a separate water or sewer provider may follow different rules.

Fee amounts on this page are compiled from official published schedules and are provided for planning purposes only. Rates change, and project specifics (unit size, meter size, location within special districts) can alter what applies. Always verify current fees with the jurisdiction and utility before relying on them.

Missing a jurisdiction, or want to sponsor one?

Request coverage for a city or county, ask about sponsoring its page, or report an issue. We typically reply within one business day.