Providence Village Impact Fees by Project Type
Providence Village: Single-Family Impact Fees
A new single-family home in Providence Village pays at least $1,500.00 per unit in impact fees (rates sourced November 25, 2026). Every line item is levied at the municipal or utility level.
The largest line items are Water Connection Fee — Town of Providence Village, 3/4" x 5/8" residential tap ($1,500.00).
Sewer Connection Fee (Town of Providence Village) is set by the utility and not published online. Contact the levying jurisdiction or utility to verify before budgeting; it is not included as a dollar figure here.
Some fees are tiered by unit size or building type; amounts reflect the representative tier noted in the schedule below.
View the Full Providence Village Impact Fee Schedule
- Water Connection Fee — Town of Providence Village, 3/4" x 5/8" residential tap$1,500.00Town of Providence VillageIn the Town of Providence Village water service area, a standard 3/4 by 5/8 inch residential tap is $1,500 (Fee Schedule, Ordinance 2026-335); a 1 inch tap is $1,750. Parts of the Town to the north are served by Mustang Special Utility District instead.
- Sewer Connection Fee (Town of Providence Village)Requires confirmationTown of Providence VillageThe Town of Providence Village publishes no separate sewer connection or capacity fee for a new home; a $75 residential sanitary sewer inspection applies.
- City (Town of Providence Village)$0.00Town of Providence VillageThe Town of Providence Village charges no roadway, drainage, park, water or wastewater impact fee on new homes.
- County Impact Fee (Denton County)$0.00Denton CountyTexas law lets a county charge an impact fee only for drainage, and only where the county has at least 3.3 million residents or borders one that does. Denton County does not qualify, so no county impact fee applies.
Where in Denton County Are You Building?
Each jurisdiction applies its own fee schedule. Pick yours. = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.
Providence Village: Multifamily Impact Fees
A new multifamily unit in Providence Village pays at least $1,500.00 per unit in impact fees (rates sourced November 25, 2026). Every line item is levied at the municipal or utility level.
The largest line items are Water Connection Fee (MF) — Town of Providence Village, 3/4" x 5/8" residential tap ($1,500.00).
Sewer Connection Fee (Town of Providence Village, MF) is set by the utility and not published online. Contact the levying jurisdiction or utility to verify before budgeting; it is not included as a dollar figure here.
Some fees are tiered by unit size or building type; amounts reflect the representative tier noted in the schedule below.
View the Full Providence Village Impact Fee Schedule
- Water Connection Fee (MF) — Town of Providence Village, 3/4" x 5/8" residential tap$1,500.00Town of Providence VillageTown of Providence Village water tap, charged per connection: $1,500 for a 3/4 by 5/8 inch residential tap. A building on one connection pays once; commercial connections are priced at approved plan cost plus 200%. Parts of the Town to the north are served by Mustang Special Utility District instead.
- Sewer Connection Fee (Town of Providence Village, MF)Requires confirmationTown of Providence VillageThe Town of Providence Village publishes no separate sewer connection or capacity fee; a sanitary sewer inspection fee applies.
- City (Town of Providence Village) (MF)$0.00Town of Providence VillageThe Town of Providence Village charges no roadway, drainage, park, water or wastewater impact fee on apartments.
- County Impact Fee (Denton County, MF)$0.00Denton CountyTexas law lets a county charge an impact fee only for drainage, and only where the county has at least 3.3 million residents or borders one that does. Denton County does not qualify, so no county impact fee applies.
Where in Denton County Are You Building?
Each jurisdiction applies its own fee schedule. Pick yours. = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.
Providence Village: Commercial Impact Fees
Commercial development in Providence Village pays no per-square-foot impact fees (rates sourced November 25, 2026).
Water and sewer connection fees assume a 1-inch meter; larger services pay more. See the meter-size tiers in the source schedules.
Water Tap Fee — Town of Providence Village, commercial connection (approved plan cost plus 200%) and Sewer Connection Fee (Town of Providence Village) are set by the utility and not published online. Contact the levying jurisdiction or utility to verify before budgeting; they are not included as dollar figures here.
View the Full Providence Village Impact Fee Schedule
- Water Tap Fee — Town of Providence Village, commercial connection (approved plan cost plus 200%)Requires confirmationTown of Providence VillageIn the Town of Providence Village water service area, a commercial water connection is charged at the approved plan cost plus 200%, which includes the meter and its installation (Fee Schedule, Ordinance 2026-335). Residential-size taps are $1,500 (3/4 by 5/8 inch) and $1,750 (1 inch). Parts of the Town north along FM 2931 are served by Mustang Special Utility District instead.
- Sewer Connection Fee (Town of Providence Village)Requires confirmationTown of Providence VillageThe Town of Providence Village publishes no separate sewer connection or capacity fee; commercial sewer service requires an inspection priced from the approved plans.
- City Impact Fee (Town of Providence Village, Commercial)$0.00Town of Providence VillageThe Town of Providence Village charges no roadway, drainage, water or wastewater impact fee on commercial development.
- County Impact Fee (Denton County, Commercial)$0.00Denton CountyTexas counties cannot levy impact fees under Local Government Code Chapter 395, so Denton County charges no county impact fee on commercial, office or industrial development.
Where in Denton County Are You Building?
Each jurisdiction applies its own fee schedule. Pick yours. Totals shown are for a 50,000 sq ft building, including water/sewer fees (one-time connection fees assume a 1-inch meter). * = one-time water/sewer connection charges only; no per-sq-ft impact fee schedule sourced for that jurisdiction. = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.
Providence Village: Industrial Impact Fees
Industrial development in Providence Village pays no per-square-foot impact fees (rates sourced November 25, 2026).
Water and sewer connection fees assume a 1-inch meter; larger services pay more. See the meter-size tiers in the source schedules.
Water Tap Fee — Town of Providence Village, commercial connection (approved plan cost plus 200%) and Sewer Connection Fee (Town of Providence Village) are set by the utility and not published online. Contact the levying jurisdiction or utility to verify before budgeting; they are not included as dollar figures here.
View the Full Providence Village Impact Fee Schedule
- Water Tap Fee — Town of Providence Village, commercial connection (approved plan cost plus 200%)Requires confirmationTown of Providence VillageIn the Town of Providence Village water service area, a commercial water connection is charged at the approved plan cost plus 200%, which includes the meter and its installation (Fee Schedule, Ordinance 2026-335). Residential-size taps are $1,500 (3/4 by 5/8 inch) and $1,750 (1 inch). Parts of the Town north along FM 2931 are served by Mustang Special Utility District instead.
- Sewer Connection Fee (Town of Providence Village)Requires confirmationTown of Providence VillageThe Town of Providence Village publishes no separate sewer connection or capacity fee; commercial sewer service requires an inspection priced from the approved plans.
- City Impact Fee (Town of Providence Village, Industrial)$0.00Town of Providence VillageThe Town of Providence Village charges no roadway, drainage, water or wastewater impact fee on industrial development.
- County Impact Fee (Denton County, Industrial)$0.00Denton CountyTexas counties cannot levy impact fees under Local Government Code Chapter 395, so Denton County charges no county impact fee on commercial, office or industrial development.
Where in Denton County Are You Building?
Each jurisdiction applies its own fee schedule. Pick yours. Totals shown are for a 50,000 sq ft building, including water/sewer fees (one-time connection fees assume a 1-inch meter). * = one-time water/sewer connection charges only; no per-sq-ft impact fee schedule sourced for that jurisdiction. = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.
Providence Village: Office Impact Fees
Office development in Providence Village pays no per-square-foot impact fees (rates sourced November 25, 2026).
Water and sewer connection fees assume a 1-inch meter; larger services pay more. See the meter-size tiers in the source schedules.
Water Tap Fee — Town of Providence Village, commercial connection (approved plan cost plus 200%) and Sewer Connection Fee (Town of Providence Village) are set by the utility and not published online. Contact the levying jurisdiction or utility to verify before budgeting; they are not included as dollar figures here.
View the Full Providence Village Impact Fee Schedule
- Water Tap Fee — Town of Providence Village, commercial connection (approved plan cost plus 200%)Requires confirmationTown of Providence VillageIn the Town of Providence Village water service area, a commercial water connection is charged at the approved plan cost plus 200%, which includes the meter and its installation (Fee Schedule, Ordinance 2026-335). Residential-size taps are $1,500 (3/4 by 5/8 inch) and $1,750 (1 inch). Parts of the Town north along FM 2931 are served by Mustang Special Utility District instead.
- Sewer Connection Fee (Town of Providence Village)Requires confirmationTown of Providence VillageThe Town of Providence Village publishes no separate sewer connection or capacity fee; commercial sewer service requires an inspection priced from the approved plans.
- City Impact Fee (Town of Providence Village, Office)$0.00Town of Providence VillageThe Town of Providence Village charges no roadway, drainage, water or wastewater impact fee on office development.
- County Impact Fee (Denton County, Office)$0.00Denton CountyTexas counties cannot levy impact fees under Local Government Code Chapter 395, so Denton County charges no county impact fee on commercial, office or industrial development.
Where in Denton County Are You Building?
Each jurisdiction applies its own fee schedule. Pick yours. Totals shown are for a 25,000 sq ft building, including water/sewer fees (one-time connection fees assume a 1-inch meter). * = one-time water/sewer connection charges only; no per-sq-ft impact fee schedule sourced for that jurisdiction. = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.
Providence Village Impact Fee Calculator
Estimate impact fees for your project. Set to single-family. Drop a pin or search an address for site-specific fees.
Location
Select a location to begin
Once you select an address or drop a pin, we'll identify the responsible city and county and generate a fee breakdown.
How Impact Fees Work in Texas
Texas cities, and certain special districts and authorities, assess impact fees under Chapter 395 of the Local Government Code and, with narrow exceptions, may charge one only by following it. A fee rests on adopted land use assumptions and a capital improvements plan, and imposing one takes the votes of two-thirds of the governing body's members.
Impact fees may fund only water supply, treatment and distribution; wastewater collection and treatment; storm water, drainage and flood control; and roadway facilities. Parks, schools, police and fire facilities are not on the chapter's list. The chapter does not treat park land dedication, or a payment in its place, as an impact fee, so a city can require that separately. The fee per service unit is capped at the plan's growth-related cost, less a required credit, divided by the projected service units. Counties generally cannot charge impact fees: the chapter gives that authority only to counties of 3.3 million or more people and the counties bordering them, and only for storm water, drainage and flood control. Since September 2025 a city also may not charge an impact fee where an office, retail or warehouse building at least five years old is converted to multifamily or mixed-use residential use (at least 65 percent of the building and of each usable floor), unless the land was already subject to an impact fee before the conversion's building permit was filed (Section 218.204).
For land platted after a fee is adopted, the fee is assessed no later than when the plat is recorded, which fixes the most that can be charged per service unit. Where water and wastewater capacity is available, it is generally collected when the building permit is issued, or when a water or wastewater meter connection is applied for on land outside city limits or where the entity charging the fee issues no building permits. A fee not spent as the chapter allows within 10 years of payment must generally be refunded with interest, and the land use assumptions and capital improvements plan are updated at least every five years unless the governing body formally determines that no update is needed.
A city may charge water, wastewater and drainage impact fees in its extraterritorial jurisdiction as well as inside its limits, but roadway impact fees stop at the city limits. Where a utility district or another provider supplies water or sewer instead of the city, its charges are separate from the city's, so the total can differ between a city, its neighbors and the unincorporated land around it.
For a primer on how impact fees work, see our plain-English guide.
Summary current as of November 2026. This is an editorial summary, not legal advice; see the official statute text and our terms of use.
Providence Village Impact Fee FAQs
What are the total impact fees for a single-family home in Providence Village, Texas?
A new single-family home in Providence Village pays at least $1,500.00 per unit in combined impact fees (rates sourced November 25, 2026). One additional fee has no published standard amount and is not included, so the full cost may be higher; verify before budgeting.
How much are commercial impact fees in Providence Village?
Providence Village does not currently levy impact fees on commercial development.
Does Providence Village charge its own impact fees?
Yes. Providence Village levies its own municipal impact or utility fees. Denton County does not currently add county-level impact fees inside Providence Village. The schedule on this page shows every fee that applies to development in Providence Village.
Can a Texas impact fee increase at any time?
No. Under Section 395.0515 of the Local Government Code, added in 2025, a city or district may not increase an impact fee for three years from the later of the date the fee was adopted or last increased, although it may phase in collection up to the adopted maximum over no more than ten years. An increase also needs an independent financial audit and a public hearing on its results first (Section 395.059), and the measure approving it cannot be adopted as an emergency measure (Section 395.057). Once a fee is assessed on a tract, it cannot be raised for that tract unless the number of service units increases (Section 395.017). Charges set by a separate water or sewer provider may follow different rules.
Fee amounts on this page are compiled from official published schedules and are provided for planning purposes only. Rates change, and project specifics (unit size, meter size, location within special districts) can alter what applies. Always verify current fees with the jurisdiction and utility before relying on them.
Compare unincorporated rates and every other city on the Denton County impact fees page.