Skip to content
IMPACTFEES.ORG

Aubrey, Texas Impact Fees

Aubrey applies its own fee schedule. Denton County does not currently add county-level impact fees inside city limits. A new single-family home pays $28,333.83 per unit (rates sourced ). This figure includes amounts that have not been confirmed with the jurisdiction; verify before budgeting. The full breakdown is below.

Aubrey Impact Fees by Project Type

Aubrey: Single-Family Impact Fees

A new single-family home in Aubrey pays $28,333.83 per unit in impact fees (rates sourced November 25, 2026). Every line item is levied at the municipal or utility level.

The largest line items are Sewer Impact Fee (City of Aubrey) — 1" or smaller meter ($10,586.00), Water Connection Fee — City of Aubrey, 3/4" meter: $5,820 impact + $1,200 tap + $350 meter ($7,370.00) and Roadway Impact Fee (City of Aubrey) — Service Area 2 ($4,177.83).

Park Development Fee (City of Aubrey) is shown at the last published amount but has not been confirmed with the jurisdiction; it is included in the totals here. Verify before budgeting.

Some fees are tiered by unit size or building type; amounts reflect the representative tier noted in the schedule below.

View the Full Aubrey Impact Fee Schedule
Water$7,370.00
Sewer$12,286.00
  • Sewer Impact Fee (City of Aubrey) — 1" or smaller meter
    Wastewater impact fee of $10,586 per living-unit-equivalent, collected at 50% of the maximum assessable rate; a standard single-family home pays $10,586, larger meters proportionally more. A separate one-time sewer tap fee ($1,700 for a 4-inch tap) applies in addition. Effective February 26, 2026.
    $10,586.00
  • Sewer Tap Fee (City of Aubrey) — 4" connection
    City of Aubrey
    One-time City of Aubrey sewer connection (tapping) fee for a 4 inch service line: $1,700; larger lines cost more. Fee schedule adopted February 26, 2026.
    $1,700.00
City$8,677.83
  • Park Development Fee (City of Aubrey)
    City of Aubrey
    Aubrey charges a park development fee of $4,500 per single-family home, collected with the residential building permit and deposited in the City's Park Development Trust Fund. Subdivision ordinance amended December 20, 2022.
    $4,500.00Requires confirmation
  • Roadway Impact Fee (City of Aubrey) — Service Area 2
    Roadway impact fee for a single-family detached home: $4,177.83 in Service Area 2, the higher of Aubrey's two roadway service areas (Service Area 1 is $2,935.62). Rates adopted by Ordinance 897-25 (March 27, 2025) and restated in Ordinance 948-26 (February 26, 2026).
    $4,177.83
County$0.00
  • County Impact Fee (Denton County)
    Denton County
    Texas law lets a county charge an impact fee only for drainage, and only where the county has at least 3.3 million residents or borders one that does. Denton County does not qualify, so no county impact fee applies.
    $0.00
Total (Aubrey): $28,333.83
Sources last checked Official fee schedules:City of Aubrey Denton County
Amounts flagged "Requires confirmation" are the last published figures, included in the totals. Confirm them with the jurisdiction or utility before budgeting.

Where in Denton County Are You Building?

Each jurisdiction applies its own fee schedule. Pick yours. = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.

Aubrey: Multifamily Impact Fees

A new multifamily unit in Aubrey pays $24,422.70 per unit in impact fees (rates sourced November 25, 2026). Every line item is levied at the municipal or utility level.

The largest line items are Sewer Impact Fee (City of Aubrey, MF) — under 2" meter ($10,586.00), Water Connection Fee (MF) — City of Aubrey, 3/4" meter: $5,820 impact + $1,200 tap + $350 meter ($7,370.00) and Roadway Impact Fee (City of Aubrey, MF) — Service Area 2 ($2,266.70).

Park Development Fee (City of Aubrey, MF) is shown at the last published amount but has not been confirmed with the jurisdiction; it is included in the totals here. Verify before budgeting.

Some fees are tiered by unit size or building type; amounts reflect the representative tier noted in the schedule below.

View the Full Aubrey Impact Fee Schedule
Water$7,370.00
Sewer$12,286.00
  • Sewer Impact Fee (City of Aubrey, MF) — under 2" meter
    Wastewater impact fee is charged per meter size. A master-metered multifamily building pays by its meter size, starting at $10,586 for a 1-inch-or-smaller meter and scaling up. Collected at 50% of the maximum rate. A separate sewer tap fee applies. Effective February 26, 2026.
    $10,586.00
  • Sewer Tap Fee (City of Aubrey, MF) — 4" connection
    City of Aubrey
    City of Aubrey sewer tapping fee for a 4 inch service line: $1,700; larger lines cost more, and a building on one connection pays once.
    $1,700.00
City$4,766.70
  • Park Development Fee (City of Aubrey, MF)
    City of Aubrey
    Aubrey charges a park development fee of $2,500 per multifamily dwelling unit, deposited in the City's Park Development Trust Fund. Subdivision ordinance amended December 20, 2022.
    $2,500.00Requires confirmation
  • Roadway Impact Fee (City of Aubrey, MF) — Service Area 2
    Roadway impact fee for an apartment unit: $2,266.70 per dwelling unit in Service Area 2, the higher of Aubrey's two roadway service areas (Service Area 1 is $1,592.73). Rates adopted by Ordinance 897-25 (March 27, 2025) and restated in Ordinance 948-26 (February 26, 2026).
    $2,266.70
County$0.00
  • County Impact Fee (Denton County, MF)
    Denton County
    Texas law lets a county charge an impact fee only for drainage, and only where the county has at least 3.3 million residents or borders one that does. Denton County does not qualify, so no county impact fee applies.
    $0.00
Total (Aubrey): $24,422.70
Sources last checked Official fee schedules:City of Aubrey Denton County
Amounts flagged "Requires confirmation" are the last published figures, included in the totals. Confirm them with the jurisdiction or utility before budgeting.

Where in Denton County Are You Building?

Each jurisdiction applies its own fee schedule. Pick yours. = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.

Aubrey: Commercial Impact Fees

Commercial development in Aubrey pays $10.73 per square foot in impact fees, plus $19,886.00 in one-time water and sewer connection fees (rates sourced November 25, 2026).

For a 50,000 sq ft building, that comes to about $556,189.00. The calculator below adjusts to your exact square footage.

The largest line items are Wastewater Impact Fee (City of Aubrey) — under 2" simple meter ($10,586.00 one-time), Water Impact Fee (City of Aubrey) — under 2" simple meter ($5,820.00 one-time) and Sewer Tap Fee (City of Aubrey) — 4" line ($1,700.00 one-time).

Water and sewer connection fees assume a 1-inch meter; larger services pay more. See the meter-size tiers in the source schedules.

View the Full Aubrey Impact Fee Schedule
Water$7,600.00 one-time
  • Water Impact Fee (City of Aubrey) — under 2" simple meter
    City of Aubrey
    Aubrey's water impact fee is collected at 50% of the maximum, $5,820 per living unit equivalent, and is set by meter size and type. A commercial simple meter under 2 inches (including the 1 inch meter) pays 1 LUE. The rate is in the FY2026 fee schedule adopted February 26, 2026; a separate water tap fee and meter fee are also charged.
    $5,820.00 one-time
  • Water Tap Fee (City of Aubrey) — 1" meter
    City of Aubrey
    Aubrey's water connection (tapping) fee for a 1 inch service is $1,300 under the FY2026 fee schedule adopted February 26, 2026, charged in addition to the water impact fee and the meter fee.
    $1,300.00 one-time
  • Water Meter Fee (City of Aubrey) — 1" meter
    City of Aubrey
    Aubrey's water meter fee for a 1 inch meter is $480 under the FY2026 fee schedule adopted February 26, 2026, charged with the water tap fee.
    $480.00 one-time
Sewer$12,286.00 one-time
  • Wastewater Impact Fee (City of Aubrey) — under 2" simple meter
    City of Aubrey
    Aubrey's wastewater impact fee is collected at 50% of the maximum, $10,586 per living unit equivalent, and is set by meter size and type. A commercial simple meter under 2 inches (including the 1 inch meter) pays 1 LUE. The rate is in the FY2026 fee schedule adopted February 26, 2026; a separate sewer tap fee is also charged.
    $10,586.00 one-time
  • Sewer Tap Fee (City of Aubrey) — 4" line
    City of Aubrey
    Aubrey's sewer connection (tapping) fee is set by line size: $1,700 for a 4 inch line, up to $2,050 for a 10 inch line, under the FY2026 fee schedule adopted February 26, 2026. It is charged in addition to the wastewater impact fee.
    $1,700.00 one-time
City$10.73/sq ft
  • Roadway Impact Fee (City of Aubrey, Commercial) — Service Area 2
    City of Aubrey
    Aubrey's roadway impact fee for a shopping center is 7.24 vehicle-miles per 1,000 sq ft of gross floor area at $1,481.50 per vehicle-mile in Service Area 2, the highest of 2 rate districts (Service Area 1: $7,536.84 per 1,000 sq ft). Rates come from the Roadway Impact Fee Update 2024-2034 (Ordinance 897-25) and the FY2026 fee schedule adopted February 26, 2026. Assessed at plat and collected at building permit.
    $10.73/sq ft
County$0.00
  • County Impact Fee (Denton County, Commercial)
    Denton County
    Texas counties cannot levy impact fees under Local Government Code Chapter 395, so Denton County charges no county impact fee on commercial, office or industrial development.
    $0.00
Total (Aubrey): $10.73/sq ft + $19,886.00 one-time (≈ $556,189.00 at 50,000 sq ft)
Sources last checked Official fee schedules:City of Aubrey Denton County
Water/sewer connection fees assume a 1-inch meter; larger services pay more.

Where in Denton County Are You Building?

Each jurisdiction applies its own fee schedule. Pick yours. Totals shown are for a 50,000 sq ft building, including water/sewer fees (one-time connection fees assume a 1-inch meter). * = one-time water/sewer connection charges only; no per-sq-ft impact fee schedule sourced for that jurisdiction. = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.

Aubrey: Industrial Impact Fees

Industrial development in Aubrey pays $2.89 per square foot in impact fees, plus $19,886.00 in one-time water and sewer connection fees (rates sourced November 25, 2026).

For a 50,000 sq ft building, that comes to about $164,332.50. The calculator below adjusts to your exact square footage.

The largest line items are Wastewater Impact Fee (City of Aubrey) — under 2" simple meter ($10,586.00 one-time), Water Impact Fee (City of Aubrey) — under 2" simple meter ($5,820.00 one-time) and Sewer Tap Fee (City of Aubrey) — 4" line ($1,700.00 one-time).

Water and sewer connection fees assume a 1-inch meter; larger services pay more. See the meter-size tiers in the source schedules.

View the Full Aubrey Impact Fee Schedule
Water$7,600.00 one-time
  • Water Impact Fee (City of Aubrey) — under 2" simple meter
    City of Aubrey
    Aubrey's water impact fee is collected at 50% of the maximum, $5,820 per living unit equivalent, and is set by meter size and type. A commercial simple meter under 2 inches (including the 1 inch meter) pays 1 LUE. The rate is in the FY2026 fee schedule adopted February 26, 2026; a separate water tap fee and meter fee are also charged.
    $5,820.00 one-time
  • Water Tap Fee (City of Aubrey) — 1" meter
    City of Aubrey
    Aubrey's water connection (tapping) fee for a 1 inch service is $1,300 under the FY2026 fee schedule adopted February 26, 2026, charged in addition to the water impact fee and the meter fee.
    $1,300.00 one-time
  • Water Meter Fee (City of Aubrey) — 1" meter
    City of Aubrey
    Aubrey's water meter fee for a 1 inch meter is $480 under the FY2026 fee schedule adopted February 26, 2026, charged with the water tap fee.
    $480.00 one-time
Sewer$12,286.00 one-time
  • Wastewater Impact Fee (City of Aubrey) — under 2" simple meter
    City of Aubrey
    Aubrey's wastewater impact fee is collected at 50% of the maximum, $10,586 per living unit equivalent, and is set by meter size and type. A commercial simple meter under 2 inches (including the 1 inch meter) pays 1 LUE. The rate is in the FY2026 fee schedule adopted February 26, 2026; a separate sewer tap fee is also charged.
    $10,586.00 one-time
  • Sewer Tap Fee (City of Aubrey) — 4" line
    City of Aubrey
    Aubrey's sewer connection (tapping) fee is set by line size: $1,700 for a 4 inch line, up to $2,050 for a 10 inch line, under the FY2026 fee schedule adopted February 26, 2026. It is charged in addition to the wastewater impact fee.
    $1,700.00 one-time
City$2.89/sq ft
  • Roadway Impact Fee (City of Aubrey, Industrial) — Service Area 2
    City of Aubrey
    Aubrey's roadway impact fee for industrial use is 1.95 vehicle-miles per 1,000 sq ft of gross floor area at $1,481.50 per vehicle-mile in Service Area 2, the highest of 2 rate districts (Service Area 1: $2,029.95 per 1,000 sq ft). Rates come from the Roadway Impact Fee Update 2024-2034 (Ordinance 897-25) and the FY2026 fee schedule adopted February 26, 2026.
    $2.89/sq ft
County$0.00
  • County Impact Fee (Denton County, Industrial)
    Denton County
    Texas counties cannot levy impact fees under Local Government Code Chapter 395, so Denton County charges no county impact fee on commercial, office or industrial development.
    $0.00
Total (Aubrey): $2.89/sq ft + $19,886.00 one-time (≈ $164,332.50 at 50,000 sq ft)
Sources last checked Official fee schedules:City of Aubrey Denton County
Water/sewer connection fees assume a 1-inch meter; larger services pay more.

Where in Denton County Are You Building?

Each jurisdiction applies its own fee schedule. Pick yours. Totals shown are for a 50,000 sq ft building, including water/sewer fees (one-time connection fees assume a 1-inch meter). * = one-time water/sewer connection charges only; no per-sq-ft impact fee schedule sourced for that jurisdiction. = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.

Aubrey: Office Impact Fees

Office development in Aubrey pays $6.40 per square foot in impact fees, plus $19,886.00 in one-time water and sewer connection fees (rates sourced November 25, 2026).

For a 25,000 sq ft building, that comes to about $179,888.00. The calculator below adjusts to your exact square footage.

The largest line items are Wastewater Impact Fee (City of Aubrey) — under 2" simple meter ($10,586.00 one-time), Water Impact Fee (City of Aubrey) — under 2" simple meter ($5,820.00 one-time) and Sewer Tap Fee (City of Aubrey) — 4" line ($1,700.00 one-time).

Water and sewer connection fees assume a 1-inch meter; larger services pay more. See the meter-size tiers in the source schedules.

View the Full Aubrey Impact Fee Schedule
Water$7,600.00 one-time
  • Water Impact Fee (City of Aubrey) — under 2" simple meter
    City of Aubrey
    Aubrey's water impact fee is collected at 50% of the maximum, $5,820 per living unit equivalent, and is set by meter size and type. A commercial simple meter under 2 inches (including the 1 inch meter) pays 1 LUE. The rate is in the FY2026 fee schedule adopted February 26, 2026; a separate water tap fee and meter fee are also charged.
    $5,820.00 one-time
  • Water Tap Fee (City of Aubrey) — 1" meter
    City of Aubrey
    Aubrey's water connection (tapping) fee for a 1 inch service is $1,300 under the FY2026 fee schedule adopted February 26, 2026, charged in addition to the water impact fee and the meter fee.
    $1,300.00 one-time
  • Water Meter Fee (City of Aubrey) — 1" meter
    City of Aubrey
    Aubrey's water meter fee for a 1 inch meter is $480 under the FY2026 fee schedule adopted February 26, 2026, charged with the water tap fee.
    $480.00 one-time
Sewer$12,286.00 one-time
  • Wastewater Impact Fee (City of Aubrey) — under 2" simple meter
    City of Aubrey
    Aubrey's wastewater impact fee is collected at 50% of the maximum, $10,586 per living unit equivalent, and is set by meter size and type. A commercial simple meter under 2 inches (including the 1 inch meter) pays 1 LUE. The rate is in the FY2026 fee schedule adopted February 26, 2026; a separate sewer tap fee is also charged.
    $10,586.00 one-time
  • Sewer Tap Fee (City of Aubrey) — 4" line
    City of Aubrey
    Aubrey's sewer connection (tapping) fee is set by line size: $1,700 for a 4 inch line, up to $2,050 for a 10 inch line, under the FY2026 fee schedule adopted February 26, 2026. It is charged in addition to the wastewater impact fee.
    $1,700.00 one-time
City$6.40/sq ft
  • Roadway Impact Fee (City of Aubrey, Office) — Service Area 2
    City of Aubrey
    Aubrey's roadway impact fee for an office building is 4.32 vehicle-miles per 1,000 sq ft of gross floor area at $1,481.50 per vehicle-mile in Service Area 2, the highest of 2 rate districts (Service Area 1: $4,497.12 per 1,000 sq ft). Rates come from the Roadway Impact Fee Update 2024-2034 (Ordinance 897-25) and the FY2026 fee schedule adopted February 26, 2026.
    $6.40/sq ft
County$0.00
  • County Impact Fee (Denton County, Office)
    Denton County
    Texas counties cannot levy impact fees under Local Government Code Chapter 395, so Denton County charges no county impact fee on commercial, office or industrial development.
    $0.00
Total (Aubrey): $6.40/sq ft + $19,886.00 one-time (≈ $179,888.00 at 25,000 sq ft)
Sources last checked Official fee schedules:City of Aubrey Denton County
Water/sewer connection fees assume a 1-inch meter; larger services pay more.

Where in Denton County Are You Building?

Each jurisdiction applies its own fee schedule. Pick yours. Totals shown are for a 25,000 sq ft building, including water/sewer fees (one-time connection fees assume a 1-inch meter). * = one-time water/sewer connection charges only; no per-sq-ft impact fee schedule sourced for that jurisdiction. = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.

Aubrey Impact Fee Calculator

Estimate impact fees for your project. Set to single-family. Drop a pin or search an address for site-specific fees.

Location

Select a location to begin

Once you select an address or drop a pin, we'll identify the responsible city and county and generate a fee breakdown.

Water & Sewer
Transportation
Parks
Schools
Fire & Police
General

How Impact Fees Work in Texas

Texas cities, and certain special districts and authorities, assess impact fees under Chapter 395 of the Local Government Code and, with narrow exceptions, may charge one only by following it. A fee rests on adopted land use assumptions and a capital improvements plan, and imposing one takes the votes of two-thirds of the governing body's members.

Impact fees may fund only water supply, treatment and distribution; wastewater collection and treatment; storm water, drainage and flood control; and roadway facilities. Parks, schools, police and fire facilities are not on the chapter's list. The chapter does not treat park land dedication, or a payment in its place, as an impact fee, so a city can require that separately. The fee per service unit is capped at the plan's growth-related cost, less a required credit, divided by the projected service units. Counties generally cannot charge impact fees: the chapter gives that authority only to counties of 3.3 million or more people and the counties bordering them, and only for storm water, drainage and flood control. Since September 2025 a city also may not charge an impact fee where an office, retail or warehouse building at least five years old is converted to multifamily or mixed-use residential use (at least 65 percent of the building and of each usable floor), unless the land was already subject to an impact fee before the conversion's building permit was filed (Section 218.204).

For land platted after a fee is adopted, the fee is assessed no later than when the plat is recorded, which fixes the most that can be charged per service unit. Where water and wastewater capacity is available, it is generally collected when the building permit is issued, or when a water or wastewater meter connection is applied for on land outside city limits or where the entity charging the fee issues no building permits. A fee not spent as the chapter allows within 10 years of payment must generally be refunded with interest, and the land use assumptions and capital improvements plan are updated at least every five years unless the governing body formally determines that no update is needed.

A city may charge water, wastewater and drainage impact fees in its extraterritorial jurisdiction as well as inside its limits, but roadway impact fees stop at the city limits. Where a utility district or another provider supplies water or sewer instead of the city, its charges are separate from the city's, so the total can differ between a city, its neighbors and the unincorporated land around it.

New to impact fees? Our plain-English guide explains what they cover, who pays them, and why they exist.

Summary current as of November 2026. This is an editorial summary, not legal advice; see the official statute text and our terms of use.

Aubrey Impact Fee FAQs

What are the total impact fees for a single-family home in Aubrey, Texas?

A new single-family home in Aubrey pays $28,333.83 per unit in combined impact fees (rates sourced November 25, 2026). This figure includes amounts that have not been confirmed with the jurisdiction; verify before budgeting.

How much are commercial impact fees in Aubrey?

Commercial development in Aubrey pays $10.73 per square foot in impact fees, plus $19,886.00 in one-time water and sewer connection fees (assuming a 1-inch meter), about $556,189.00 for a 50,000 sq ft building.

Does Aubrey charge its own impact fees?

Yes. Aubrey levies its own municipal impact or utility fees. Denton County does not currently add county-level impact fees inside Aubrey. The schedule on this page shows every fee that applies to development in Aubrey.

Can a Texas impact fee increase at any time?

No. Under Section 395.0515 of the Local Government Code, added in 2025, a city or district may not increase an impact fee for three years from the later of the date the fee was adopted or last increased, although it may phase in collection up to the adopted maximum over no more than ten years. An increase also needs an independent financial audit and a public hearing on its results first (Section 395.059), and the measure approving it cannot be adopted as an emergency measure (Section 395.057). Once a fee is assessed on a tract, it cannot be raised for that tract unless the number of service units increases (Section 395.017). Charges set by a separate water or sewer provider may follow different rules.

Fee amounts on this page are compiled from official published schedules and are provided for planning purposes only. Rates change, and project specifics (unit size, meter size, location within special districts) can alter what applies. Always verify current fees with the jurisdiction and utility before relying on them.

Compare unincorporated rates and every other city on the Denton County impact fees page.