Double Oak Impact Fees by Project Type
Double Oak: Single-Family Impact Fees
A new single-family home in Double Oak pays $9,780.00 per unit in impact fees (rates sourced November 25, 2026). Every line item is levied at the municipal or utility level.
The largest line items are Water Connection Fee — Cross Timbers WSC, 5/8" x 3/4" meter: $8,380 capital + $150 membership + $1,250 installation ($9,780.00).
Some fees are tiered by unit size or building type; amounts reflect the representative tier noted in the schedule below.
View the Full Double Oak Impact Fee Schedule
- Water Connection Fee — Cross Timbers WSC, 5/8" x 3/4" meter: $8,380 capital + $150 membership + $1,250 installation$9,780.00Cross Timbers Water Supply CorporationCross Timbers Water Supply Corporation serves Double Oak and charges $9,780 for a standard 5/8 inch x 3/4 inch residential meter: $8,380 capital fee, $150 membership and $1,250 installation (prices effective July 1, 2025). A road bore costs extra.
- Sewer (Town of Double Oak) — Septic (OSSF)$0.00Town of Double OakLots more than 150 feet from a town sewer line use a private septic or aerobic system and pay no sewer connection fee.
- City Impact Fee (Town of Double Oak)$0.00The Town of Double Oak does not levy municipal impact fees or a park fee on new homes.
- County Impact Fee (Denton County)$0.00Denton CountyTexas law lets a county charge an impact fee only for drainage, and only where the county has at least 3.3 million residents or borders one that does. Denton County does not qualify, so no county impact fee applies.
Where in Denton County Are You Building?
Each jurisdiction applies its own fee schedule. Pick yours. = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.
Double Oak: Multifamily Impact Fees
A new multifamily unit in Double Oak pays $9,780.00 per unit in impact fees (rates sourced November 25, 2026). Every line item is levied at the municipal or utility level.
The largest line items are Water Connection Fee (Cross Timbers WSC, MF) — $8,380 capital + $150 membership + $1,250 installation ($9,780.00).
Some fees are tiered by unit size or building type; amounts reflect the representative tier noted in the schedule below.
View the Full Double Oak Impact Fee Schedule
- Water Connection Fee (Cross Timbers WSC, MF) — $8,380 capital + $150 membership + $1,250 installation$9,780.00Cross Timbers Water Supply CorporationCross Timbers Water Supply Corporation charges $9,780 per 5/8 inch x 3/4 inch meter ($8,380 capital fee, $150 membership, $1,250 installation; prices effective July 1, 2025). A building served by one meter pays once.
- Sewer (Town of Double Oak, MF) — Septic (OSSF)$0.00Town of Double OakLots more than 150 feet from a town sewer line use a private septic or aerobic system and pay no sewer connection fee.
- City Impact Fee (Town of Double Oak, MF)$0.00The Town of Double Oak does not levy municipal impact fees or a park fee on new homes.
- County Impact Fee (Denton County, MF)$0.00Denton CountyTexas law lets a county charge an impact fee only for drainage, and only where the county has at least 3.3 million residents or borders one that does. Denton County does not qualify, so no county impact fee applies.
Where in Denton County Are You Building?
Each jurisdiction applies its own fee schedule. Pick yours. = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.
Double Oak: Commercial Impact Fees
Commercial development in Double Oak pays no per-square-foot impact fees, but owes $22,600.00 in one-time water and sewer connection fees (rates sourced November 25, 2026).
For a 50,000 sq ft building, that comes to at least $22,600.00. The calculator below adjusts to your exact square footage.
Water and sewer connection fees assume a 1-inch meter; larger services pay more. See the meter-size tiers in the source schedules.
Water Connection Fee — Cross Timbers WSC, 1" meter: $20,950 capital + $150 membership + $1,500 installation is shown at the last published amount but has not been confirmed with the jurisdiction; it is included in the totals here. Verify before budgeting.
Sewer Tap Fee (Town of Double Oak) is set by the utility and not published online. Contact the levying jurisdiction or utility to verify before budgeting; it is not included as a dollar figure here.
View the Full Double Oak Impact Fee Schedule
- Water Connection Fee — Cross Timbers WSC, 1" meter: $20,950 capital + $150 membership + $1,500 installation$22,600.00 one-timeRequires confirmationCross Timbers Water Supply CorporationCross Timbers Water Supply Corporation, which serves Double Oak, charges $22,600 for a new 1 inch meter: a $20,950 capital improvement fee, the $150 membership fee and $1,500 for installation, effective July 1, 2025. A road bore adds about $750 to $1,500. Its published pricing covers 5/8 inch and 1 inch meters only; larger meters are priced by the corporation.
- Sewer Tap Fee (Town of Double Oak)Requires confirmationTown of Double OakDouble Oak operates a town sanitary sewer system for connected businesses, with treatment by the Upper Trinity Regional Water District; a sewer tap fee applies, larger taps are billed at actual cost, and main extensions are at the developer's cost. Properties off the system use permitted septic systems.
- City Impact Fee (Town of Double Oak, Commercial)$0.00Town of Double OakThe Town of Double Oak has not adopted impact fees, so no town impact fee applies to commercial, office or industrial development.
- County Impact Fee (Denton County, Commercial)$0.00Denton CountyTexas counties cannot levy impact fees under Local Government Code Chapter 395, so Denton County charges no county impact fee on commercial, office or industrial development.
Where in Denton County Are You Building?
Each jurisdiction applies its own fee schedule. Pick yours. Totals shown are for a 50,000 sq ft building, including water/sewer fees (one-time connection fees assume a 1-inch meter). * = one-time water/sewer connection charges only; no per-sq-ft impact fee schedule sourced for that jurisdiction. = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.
Double Oak: Industrial Impact Fees
Industrial development in Double Oak pays no per-square-foot impact fees, but owes $22,600.00 in one-time water and sewer connection fees (rates sourced November 25, 2026).
For a 50,000 sq ft building, that comes to at least $22,600.00. The calculator below adjusts to your exact square footage.
Water and sewer connection fees assume a 1-inch meter; larger services pay more. See the meter-size tiers in the source schedules.
Water Connection Fee — Cross Timbers WSC, 1" meter: $20,950 capital + $150 membership + $1,500 installation is shown at the last published amount but has not been confirmed with the jurisdiction; it is included in the totals here. Verify before budgeting.
Sewer Tap Fee (Town of Double Oak) is set by the utility and not published online. Contact the levying jurisdiction or utility to verify before budgeting; it is not included as a dollar figure here.
View the Full Double Oak Impact Fee Schedule
- Water Connection Fee — Cross Timbers WSC, 1" meter: $20,950 capital + $150 membership + $1,500 installation$22,600.00 one-timeRequires confirmationCross Timbers Water Supply CorporationCross Timbers Water Supply Corporation, which serves Double Oak, charges $22,600 for a new 1 inch meter: a $20,950 capital improvement fee, the $150 membership fee and $1,500 for installation, effective July 1, 2025. A road bore adds about $750 to $1,500. Its published pricing covers 5/8 inch and 1 inch meters only; larger meters are priced by the corporation.
- Sewer Tap Fee (Town of Double Oak)Requires confirmationTown of Double OakDouble Oak operates a town sanitary sewer system for connected businesses, with treatment by the Upper Trinity Regional Water District; a sewer tap fee applies, larger taps are billed at actual cost, and main extensions are at the developer's cost. Properties off the system use permitted septic systems.
- City Impact Fee (Town of Double Oak, Industrial)$0.00Town of Double OakThe Town of Double Oak has not adopted impact fees, so no town impact fee applies to commercial, office or industrial development.
- County Impact Fee (Denton County, Industrial)$0.00Denton CountyTexas counties cannot levy impact fees under Local Government Code Chapter 395, so Denton County charges no county impact fee on commercial, office or industrial development.
Where in Denton County Are You Building?
Each jurisdiction applies its own fee schedule. Pick yours. Totals shown are for a 50,000 sq ft building, including water/sewer fees (one-time connection fees assume a 1-inch meter). * = one-time water/sewer connection charges only; no per-sq-ft impact fee schedule sourced for that jurisdiction. = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.
Double Oak: Office Impact Fees
Office development in Double Oak pays no per-square-foot impact fees, but owes $22,600.00 in one-time water and sewer connection fees (rates sourced November 25, 2026).
For a 25,000 sq ft building, that comes to at least $22,600.00. The calculator below adjusts to your exact square footage.
Water and sewer connection fees assume a 1-inch meter; larger services pay more. See the meter-size tiers in the source schedules.
Water Connection Fee — Cross Timbers WSC, 1" meter: $20,950 capital + $150 membership + $1,500 installation is shown at the last published amount but has not been confirmed with the jurisdiction; it is included in the totals here. Verify before budgeting.
Sewer Tap Fee (Town of Double Oak) is set by the utility and not published online. Contact the levying jurisdiction or utility to verify before budgeting; it is not included as a dollar figure here.
View the Full Double Oak Impact Fee Schedule
- Water Connection Fee — Cross Timbers WSC, 1" meter: $20,950 capital + $150 membership + $1,500 installation$22,600.00 one-timeRequires confirmationCross Timbers Water Supply CorporationCross Timbers Water Supply Corporation, which serves Double Oak, charges $22,600 for a new 1 inch meter: a $20,950 capital improvement fee, the $150 membership fee and $1,500 for installation, effective July 1, 2025. A road bore adds about $750 to $1,500. Its published pricing covers 5/8 inch and 1 inch meters only; larger meters are priced by the corporation.
- Sewer Tap Fee (Town of Double Oak)Requires confirmationTown of Double OakDouble Oak operates a town sanitary sewer system for connected businesses, with treatment by the Upper Trinity Regional Water District; a sewer tap fee applies, larger taps are billed at actual cost, and main extensions are at the developer's cost. Properties off the system use permitted septic systems.
- City Impact Fee (Town of Double Oak, Office)$0.00Town of Double OakThe Town of Double Oak has not adopted impact fees, so no town impact fee applies to commercial, office or industrial development.
- County Impact Fee (Denton County, Office)$0.00Denton CountyTexas counties cannot levy impact fees under Local Government Code Chapter 395, so Denton County charges no county impact fee on commercial, office or industrial development.
Where in Denton County Are You Building?
Each jurisdiction applies its own fee schedule. Pick yours. Totals shown are for a 25,000 sq ft building, including water/sewer fees (one-time connection fees assume a 1-inch meter). * = one-time water/sewer connection charges only; no per-sq-ft impact fee schedule sourced for that jurisdiction. = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.
Double Oak Impact Fee Calculator
Estimate impact fees for your project. Set to single-family. Drop a pin or search an address for site-specific fees.
Location
Select a location to begin
Once you select an address or drop a pin, we'll identify the responsible city and county and generate a fee breakdown.
How Impact Fees Work in Texas
Texas cities, and certain special districts and authorities, assess impact fees under Chapter 395 of the Local Government Code and, with narrow exceptions, may charge one only by following it. A fee rests on adopted land use assumptions and a capital improvements plan, and imposing one takes the votes of two-thirds of the governing body's members.
Impact fees may fund only water supply, treatment and distribution; wastewater collection and treatment; storm water, drainage and flood control; and roadway facilities. Parks, schools, police and fire facilities are not on the chapter's list. The chapter does not treat park land dedication, or a payment in its place, as an impact fee, so a city can require that separately. The fee per service unit is capped at the plan's growth-related cost, less a required credit, divided by the projected service units. Counties generally cannot charge impact fees: the chapter gives that authority only to counties of 3.3 million or more people and the counties bordering them, and only for storm water, drainage and flood control. Since September 2025 a city also may not charge an impact fee where an office, retail or warehouse building at least five years old is converted to multifamily or mixed-use residential use (at least 65 percent of the building and of each usable floor), unless the land was already subject to an impact fee before the conversion's building permit was filed (Section 218.204).
For land platted after a fee is adopted, the fee is assessed no later than when the plat is recorded, which fixes the most that can be charged per service unit. Where water and wastewater capacity is available, it is generally collected when the building permit is issued, or when a water or wastewater meter connection is applied for on land outside city limits or where the entity charging the fee issues no building permits. A fee not spent as the chapter allows within 10 years of payment must generally be refunded with interest, and the land use assumptions and capital improvements plan are updated at least every five years unless the governing body formally determines that no update is needed.
A city may charge water, wastewater and drainage impact fees in its extraterritorial jurisdiction as well as inside its limits, but roadway impact fees stop at the city limits. Where a utility district or another provider supplies water or sewer instead of the city, its charges are separate from the city's, so the total can differ between a city, its neighbors and the unincorporated land around it.
If you're still asking what are impact fees, start with our guide to the definition, common categories, and legal basis.
Summary current as of November 2026. This is an editorial summary, not legal advice; see the official statute text and our terms of use.
Double Oak Impact Fee FAQs
What are the total impact fees for a single-family home in Double Oak, Texas?
A new single-family home in Double Oak pays $9,780.00 per unit in combined impact fees (rates sourced November 25, 2026).
How much are commercial impact fees in Double Oak?
Commercial development in Double Oak pays no per-square-foot impact fees, but owes $22,600.00 in one-time water and sewer connection fees (assuming a 1-inch meter). This figure includes amounts that have not been confirmed and excludes fees with no published standard amount, so the full cost may be higher; verify before budgeting.
Does Double Oak charge its own impact fees?
Yes. Double Oak levies its own municipal impact or utility fees. Denton County does not currently add county-level impact fees inside Double Oak. The schedule on this page shows every fee that applies to development in Double Oak.
Can a Texas impact fee increase at any time?
No. Under Section 395.0515 of the Local Government Code, added in 2025, a city or district may not increase an impact fee for three years from the later of the date the fee was adopted or last increased, although it may phase in collection up to the adopted maximum over no more than ten years. An increase also needs an independent financial audit and a public hearing on its results first (Section 395.059), and the measure approving it cannot be adopted as an emergency measure (Section 395.057). Once a fee is assessed on a tract, it cannot be raised for that tract unless the number of service units increases (Section 395.017). Charges set by a separate water or sewer provider may follow different rules.
Fee amounts on this page are compiled from official published schedules and are provided for planning purposes only. Rates change, and project specifics (unit size, meter size, location within special districts) can alter what applies. Always verify current fees with the jurisdiction and utility before relying on them.
Compare unincorporated rates and every other city on the Denton County impact fees page.