Weston Impact Fees by Project Type
Weston: Single-Family Impact Fees
A new single-family home in Weston pays $10,446.00 per unit in impact fees (rates sourced July 14, 2026). Of that, Broward County-levied fees account for $8,809.00 and municipal or utility fees for $1,637.00.
The largest line items are School Impact Fee (Broward County) ($8,809.00), Sewer Connection Fee (Indian Trace Development District) ($913.00) and Water Connection Fee (Indian Trace Development District) ($724.00).
Some fees are tiered by unit size or building type; amounts reflect the representative tier noted in the schedule below.
View the Full Weston Impact Fee Schedule
- Water Connection Fee (Indian Trace Development District)$724.00City of Weston / Indian Trace Development DistrictIndian Trace Development District water connection fee, collected by the City of Weston: $724 per single-family home (FY2026-27 Schedule of Fees, effective October 1, 2026). A separate meter installation fee applies.
- Sewer Connection Fee (Indian Trace Development District)$913.00City of Weston / Indian Trace Development DistrictIndian Trace Development District wastewater connection fee, collected by the City of Weston: $913 per single-family home (FY2026-27 Schedule of Fees, effective October 1, 2026). Estate areas without sewer pay no wastewater fee.
- City Impact Fees (City of Weston)$0.00City of WestonThe City of Weston levies no municipal impact fees; its fee schedule has no impact, capacity, or mobility fee. Broward County fees are listed separately.
- School Impact Fee (Broward County)$8,809.00Single Family, 3 or fewer BRBroward County / School Board of Broward CountyBroward County school impact fee, charged on every new residential unit countywide, including inside cities. Rates effective January 1, 2022 (Ord. 2020-36) with no annual index. Since November 2025 it is paid directly to the School Board of Broward County, no later than building permit issuance. This is the single-family rate for 3 or fewer bedrooms, which covers the typical 3-bedroom house; homes with 4 or more bedrooms pay $11,070.
- Road Impact / Transportation Concurrency Fee (Broward County)$0.00Road / Transportation ConcurrencyBroward CountyBroward County road impact fees and transportation concurrency assessments are suspended: none are collected on or after October 1, 2024 (Ord. 2024-34) unless the County Commission accepts a new impact fee study meeting state law. No study has been accepted as of the county code current through June 2026, so nothing is payable.
- Park/Recreational Impact Fee (Broward County)$0.00Broward CountyBroward County regional park and local park impact fees are suspended: none are collected on or after October 1, 2024 (Ord. 2024-34) unless the County Commission accepts a new impact fee study meeting state law. No study has been accepted as of the county code current through June 2026, so nothing is payable.
Where in Broward County Are You Building?
Each jurisdiction applies its own fee schedule. Pick yours. = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.
Weston: Multifamily Impact Fees
A new multifamily unit in Weston pays $2,703.00 per unit in impact fees (rates sourced July 14, 2026). Of that, Broward County-levied fees account for $1,475.00 and municipal or utility fees for $1,228.00.
The largest line items are School Impact Fee (Broward County, MF) ($1,475.00), Sewer Connection Fee (Indian Trace Development District, MF) ($685.00) and Water Connection Fee (Indian Trace Development District, MF) ($543.00).
Some fees are tiered by unit size or building type; amounts reflect the representative tier noted in the schedule below.
View the Full Weston Impact Fee Schedule
- Water Connection Fee (Indian Trace Development District, MF)$543.00City of Weston / Indian Trace Development DistrictIndian Trace Development District water connection fee, collected by the City of Weston: $543 per multifamily unit (FY2026-27 Schedule of Fees, effective October 1, 2026). A separate meter installation fee applies.
- Sewer Connection Fee (Indian Trace Development District, MF)$685.00City of Weston / Indian Trace Development DistrictIndian Trace Development District wastewater connection fee, collected by the City of Weston: $685 per multifamily unit (FY2026-27 Schedule of Fees, effective October 1, 2026).
- City Impact Fees (City of Weston, MF)$0.00City of WestonThe City of Weston levies no municipal impact fees; its fee schedule has no impact, capacity, or mobility fee. Broward County fees are listed separately.
- School Impact Fee (Broward County, MF)$1,475.00Mid-Rise, 2 or more BRBroward County / School Board of Broward CountyBroward County school impact fee, charged on every new residential unit countywide, including inside cities. Rates effective January 1, 2022 (Ord. 2020-36) with no annual index. Since November 2025 it is paid directly to the School Board of Broward County, no later than building permit issuance. This tier (mid-rise, 2 or more bedrooms) covers the typical 2-bedroom unit in a 4-story building. Multifamily rates depend on building type and bedrooms: garden apartment (2 to 3 stories) 1 or fewer bedrooms $480, 2 bedrooms $4,918, 3 or more $5,901; mid-rise (4 to 8 stories) 1 or fewer bedrooms $375, 2 or more $1,475; high-rise (9 or more stories) $461 for all units.
- Road Impact / Transportation Concurrency Fee (Broward County, MF)$0.00Road / Transportation ConcurrencyBroward CountyBroward County road impact fees and transportation concurrency assessments are suspended: none are collected on or after October 1, 2024 (Ord. 2024-34) unless the County Commission accepts a new impact fee study meeting state law. No study has been accepted as of the county code current through June 2026, so nothing is payable.
- Park/Recreational Impact Fee (Broward County, MF)$0.00Broward CountyBroward County regional park and local park impact fees are suspended: none are collected on or after October 1, 2024 (Ord. 2024-34) unless the County Commission accepts a new impact fee study meeting state law. No study has been accepted as of the county code current through June 2026, so nothing is payable.
Where in Broward County Are You Building?
Each jurisdiction applies its own fee schedule. Pick yours. = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.
Weston: Commercial Impact Fees
Commercial development in Weston pays $0.75 per square foot in impact fees (rates sourced July 14, 2026).
For a 50,000 sq ft building, that comes to about $37,500.00. The calculator below adjusts to your exact square footage.
The largest line items are Wastewater Connection Fee (Indian Trace Development District, City of Weston) ($0.40/sq ft) and Water Connection Fee (Indian Trace Development District, City of Weston) ($0.35/sq ft).
Some fees are tiered by use or building size; amounts reflect the representative tier noted in the schedule below.
View the Full Weston Impact Fee Schedule
- Water Connection Fee (Indian Trace Development District, City of Weston)$0.35/sq ftIndian Trace Development District (City of Weston)Water connection fee for the Indian Trace Development District, which serves most of the City of Weston, charged per square foot of building area: $0.35 per sq ft for commercial and office development and $0.25 per sq ft for industrial (Resolution 2026-133, effective October 1, 2026).
- Wastewater Connection Fee (Indian Trace Development District, City of Weston)$0.40/sq ftIndian Trace Development District (City of Weston)Wastewater connection fee for the Indian Trace Development District, which serves most of the City of Weston, charged per square foot of building area: $0.40 per sq ft for commercial and office development and $0.30 per sq ft for industrial (Resolution 2026-133, effective October 1, 2026).
- City Impact Fees (City of Weston, Commercial)$0.00City of WestonThe City of Weston does not levy any impact fees; its adopted fee schedule contains no impact fee. Utility connection fees are administered separately.
- County Impact / Transportation Concurrency Fees (Broward County, Commercial)$0.00Broward CountyBroward County collects no nonresidential impact fees. Ord. No. 2026-39 (enacted September 22, 2026) eliminated the county road impact fees and transportation concurrency assessments for development applications filed on or after September 25, 2026; collection had already been suspended since October 1, 2024 (Ord. No. 2024-34). The county park and school impact fees apply to dwelling units only.
Where in Broward County Are You Building?
Each jurisdiction applies its own fee schedule. Pick yours. Totals shown are for a 50,000 sq ft building, including one-time water/sewer fees (assuming a 1-inch meter). * = one-time water/sewer connection charges only; no per-sq-ft impact fee schedule sourced for that jurisdiction. = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.
Weston: Industrial Impact Fees
Industrial development in Weston pays $0.75 per square foot in impact fees (rates sourced July 14, 2026).
For a 50,000 sq ft building, that comes to about $37,500.00. The calculator below adjusts to your exact square footage.
The largest line items are Wastewater Connection Fee (Indian Trace Development District, City of Weston) ($0.40/sq ft) and Water Connection Fee (Indian Trace Development District, City of Weston) ($0.35/sq ft).
Some fees are tiered by use or building size; amounts reflect the representative tier noted in the schedule below.
View the Full Weston Impact Fee Schedule
- Water Connection Fee (Indian Trace Development District, City of Weston)$0.35/sq ftIndian Trace Development District (City of Weston)Water connection fee for the Indian Trace Development District, which serves most of the City of Weston, charged per square foot of building area: $0.35 per sq ft for commercial and office development and $0.25 per sq ft for industrial (Resolution 2026-133, effective October 1, 2026).
- Wastewater Connection Fee (Indian Trace Development District, City of Weston)$0.40/sq ftIndian Trace Development District (City of Weston)Wastewater connection fee for the Indian Trace Development District, which serves most of the City of Weston, charged per square foot of building area: $0.40 per sq ft for commercial and office development and $0.30 per sq ft for industrial (Resolution 2026-133, effective October 1, 2026).
- City Impact Fees (City of Weston, Industrial)$0.00City of WestonThe City of Weston does not levy any impact fees; its adopted fee schedule contains no impact fee. Utility connection fees are administered separately.
- County Impact / Transportation Concurrency Fees (Broward County, Industrial)$0.00Broward CountyBroward County collects no nonresidential impact fees. Ord. No. 2026-39 (enacted September 22, 2026) eliminated the county road impact fees and transportation concurrency assessments for development applications filed on or after September 25, 2026; collection had already been suspended since October 1, 2024 (Ord. No. 2024-34). The county park and school impact fees apply to dwelling units only.
Where in Broward County Are You Building?
Each jurisdiction applies its own fee schedule. Pick yours. Totals shown are for a 50,000 sq ft building, including one-time water/sewer fees (assuming a 1-inch meter). * = one-time water/sewer connection charges only; no per-sq-ft impact fee schedule sourced for that jurisdiction. = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.
Weston: Office Impact Fees
Office development in Weston pays $0.75 per square foot in impact fees (rates sourced July 14, 2026).
For a 25,000 sq ft building, that comes to about $18,750.00. The calculator below adjusts to your exact square footage.
The largest line items are Wastewater Connection Fee (Indian Trace Development District, City of Weston) ($0.40/sq ft) and Water Connection Fee (Indian Trace Development District, City of Weston) ($0.35/sq ft).
Some fees are tiered by use or building size; amounts reflect the representative tier noted in the schedule below.
View the Full Weston Impact Fee Schedule
- Water Connection Fee (Indian Trace Development District, City of Weston)$0.35/sq ftIndian Trace Development District (City of Weston)Water connection fee for the Indian Trace Development District, which serves most of the City of Weston, charged per square foot of building area: $0.35 per sq ft for commercial and office development and $0.25 per sq ft for industrial (Resolution 2026-133, effective October 1, 2026).
- Wastewater Connection Fee (Indian Trace Development District, City of Weston)$0.40/sq ftIndian Trace Development District (City of Weston)Wastewater connection fee for the Indian Trace Development District, which serves most of the City of Weston, charged per square foot of building area: $0.40 per sq ft for commercial and office development and $0.30 per sq ft for industrial (Resolution 2026-133, effective October 1, 2026).
- City Impact Fees (City of Weston, Office)$0.00City of WestonThe City of Weston does not levy any impact fees; its adopted fee schedule contains no impact fee. Utility connection fees are administered separately.
- County Impact / Transportation Concurrency Fees (Broward County, Office)$0.00Broward CountyBroward County collects no nonresidential impact fees. Ord. No. 2026-39 (enacted September 22, 2026) eliminated the county road impact fees and transportation concurrency assessments for development applications filed on or after September 25, 2026; collection had already been suspended since October 1, 2024 (Ord. No. 2024-34). The county park and school impact fees apply to dwelling units only.
Where in Broward County Are You Building?
Each jurisdiction applies its own fee schedule. Pick yours. Totals shown are for a 25,000 sq ft building, including one-time water/sewer fees (assuming a 1-inch meter). * = one-time water/sewer connection charges only; no per-sq-ft impact fee schedule sourced for that jurisdiction. = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.
Weston Impact Fee Calculator
Estimate impact fees for your project. Set to single-family. Drop a pin or search an address for site-specific fees.
Location
Select a location to begin
Once you select an address or drop a pin, we'll identify the responsible city and county and generate a fee breakdown.
How Impact Fees Work in Florida
Florida impact fees are one-time charges on new development, governed by Section 163.31801, Florida Statutes (the Florida Impact Fee Act). The statute requires fees to be based on the most recent and localized data, spent on the infrastructure category they were collected for, and adopted by ordinance.
Since a 2021 amendment (Ch. 2021-63, Laws of Florida), the law also limits how fast fees can rise: increases up to 25% phase in over two years, increases of 25–50% phase in over four years, and increases above 50% are allowed only with a demonstrated extraordinary-circumstances study and at least a two-thirds vote of the governing body.
Counties and cities can both levy impact fees. Inside an incorporated city, a project typically pays the county's countywide fees plus any municipal fees the city has adopted, which is why totals differ between a city and the unincorporated county around it.
Brush up on impact fee basics before you budget your next project.
Summary current as of September 2026. This is an editorial summary, not legal advice; see the official statute text and our terms of use.
Weston Impact Fee FAQs
What are the total impact fees for a single-family home in Weston, Florida?
A new single-family home in Weston pays $10,446.00 per unit in combined impact fees (rates sourced July 14, 2026).
How much are commercial impact fees in Weston?
Commercial development in Weston pays $0.75 per square foot in impact fees, about $37,500.00 for a 50,000 sq ft building.
Does Weston charge its own impact fees?
Yes. Weston levies its own municipal impact or utility fees, and county-levied fees also apply inside city limits. The schedule on this page shows every fee that applies to development in Weston, with the combined total.
Can Florida impact fees increase at any time?
No. Section 163.31801, Florida Statutes limits increases to 50% at most, phased in over two to four years, unless the local government makes extraordinary-circumstances findings and approves the increase by at least a two-thirds vote.
Fee amounts on this page are compiled from official published schedules and are provided for planning purposes only. Rates change, and project specifics (unit size, meter size, location within special districts) can alter what applies. Always verify current fees with the jurisdiction and utility before relying on them.
Compare unincorporated rates and every other city on the Broward County impact fees page.