Homestead, Florida Impact Fees

Homestead applies its own fee schedule: municipal fees plus the Miami-Dade County-levied fees that apply inside city limits. Combined, a new single-family home pays at least $12,250.55 per unit (rates sourced July 14, 2026). 4 additional fees have no published standard amounts and are not included, so the full cost may be higher; verify before budgeting. The full breakdown is below.

Homestead impact fees by project type

Homestead: Single-Family Impact Fees

A new single-family home in Homestead pays at least $12,250.55 per unit in impact fees (rates sourced July 14, 2026). All of it is levied by Miami-Dade County.

The largest line items are Road (Mobility) Impact Fee (Miami-Dade County) ($9,275.00), Educational Facilities (School) Impact Fee (Miami-Dade County) ($2,448.00) and Fire-Rescue Impact Fee (Miami-Dade County) ($527.55).

Sewer Connection/Capacity Fee (Homestead Public Services) and Water Connection/Capacity Fee (Homestead Public Services) are set by the utility and not published online. Parks & Recreation Impact Fee (City of Homestead) and Police Impact Fee (City of Homestead) are set by the city and have no published standard rate. Contact the levying jurisdiction or utility to verify before budgeting; they are not included as dollar figures here.

View the full fee schedule
Water$0.00
  • Water Connection/Capacity Fee (Homestead Public Services)
    Homestead Public Services (HPS)
    Homestead operates its OWN water utility (Homestead Public Services / HPS; not WASD). Water connection/capacity fee (City Code Ch. 28) provided via fee sheet on request; not in an accessible published schedule (rate PDF is image-based). Amount pending. Email publicworks@cityofhomestead.com / Parks & Public Works 305-224-4570.
    Requires confirmation
Sewer$0.00
  • Sewer Connection/Capacity Fee (Homestead Public Services)
    Homestead Public Services (HPS)
    Homestead operates its OWN sewer utility (HPS; not WASD). Sewer capacity fee / Sewer Capacity Certification required before permit; City Code Ch. 28. Amount pending (rate PDF image-based). Email publicworks@cityofhomestead.com / Parks & Public Works 305-224-4570.
    Requires confirmation
City$0.00
  • Parks & Recreation Impact Fee (City of Homestead)
    City of Homestead
    Park impact fee collected by the city, not the county. Homestead responsible for any park impact fee; amount pending city fee schedule. Contact City of Homestead 305-224-4500.
    Requires confirmation
  • Police Impact Fee (City of Homestead)
    City of Homestead
    Police impact fee collected by the city, not the county. Homestead has its own police dept; amount pending city fee schedule. Contact City of Homestead 305-224-4500.
    Requires confirmation
County$12,250.55
  • Road (Mobility) Impact Fee (Miami-Dade County)
    Miami-Dade County
    County Road/Mobility, SF Detached, Context Zone 2 (representative). Z1 $9,633 / Z2 $9,275 / Z3 $10,179 / Z4 $10,625. Paid countywide to Miami-Dade County. Sched eff. Dec 31 2023–Dec 30 2027. Verify context zone per parcel.
    $9,275.00
  • Educational Facilities (School) Impact Fee (Miami-Dade County)
    Miami-Dade County Public Schools
    County Educational Facilities = $612/unit + $0.918/gsf (cap 3,800 gsf). Example 2,000 gsf SFR = $2,448. Countywide. Sched eff. Dec 31 2024–Dec 30 2027.
    $2,448.00
  • Fire-Rescue Impact Fee (Miami-Dade County)
    Miami-Dade County
    County Fire-Rescue, SFR $527.55. Homestead served by Miami-Dade Fire Rescue → county fire applies. Sched eff. Dec 31 2024–Dec 30 2027.
    $527.55
Total (Homestead): $12,250.55
Fees flagged "Requires confirmation" have no confirmed published amount. Confirm them with the jurisdiction or utility before budgeting.

Where in Miami-Dade County are you building?

Each jurisdiction applies its own fee schedule. Pick yours. = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.

Unincorporated Miami-Dade County$17,866.55Aventura$13,718.45Includes unconfirmed feesBal Harbour$13,718.45Includes unconfirmed feesBay Harbor Islands$13,718.45Includes unconfirmed feesBiscayne Park$13,718.45Includes unconfirmed feesCoral Gables$11,859.90Cutler Bay$13,718.45Includes unconfirmed feesDoral$13,718.45Includes unconfirmed feesEl Portal$13,718.45Includes unconfirmed feesFlorida City$12,250.55Includes unconfirmed feesGolden Beach$13,426.55Includes unconfirmed feesHialeah$13,190.90Includes unconfirmed feesHialeah Gardens$12,250.55Includes unconfirmed fees
Homestead$12,250.55this pageIncludes unconfirmed fees
Indian Creek$13,718.45Includes unconfirmed feesKey Biscayne$13,190.90Includes unconfirmed feesMedley$13,718.45Includes unconfirmed feesMiami$13,190.90Includes unconfirmed feesMiami Beach$13,190.90Includes unconfirmed feesMiami Gardens$13,718.45Includes unconfirmed feesMiami Lakes$17,866.55Includes unconfirmed feesMiami Shores$13,718.45Includes unconfirmed feesMiami Springs$13,718.45Includes unconfirmed feesNorth Bay Village$13,718.45Includes unconfirmed feesNorth Miami$21,979.55Includes unconfirmed feesNorth Miami Beach$15,041.45Includes unconfirmed feesOpa-locka$13,718.45Includes unconfirmed feesPalmetto Bay$17,866.55Includes unconfirmed feesPinecrest$13,718.45Includes unconfirmed feesSouth Miami$13,718.45Includes unconfirmed feesSunny Isles Beach$13,718.45Includes unconfirmed feesSurfside$13,718.45Includes unconfirmed feesSweetwater$13,718.45Includes unconfirmed feesVirginia Gardens$13,718.45Includes unconfirmed feesWest Miami$13,718.45Includes unconfirmed fees

Homestead: Multifamily Impact Fees

A new multifamily unit in Homestead pays at least $5,604.55 per unit in impact fees (rates sourced July 14, 2026). All of it is levied by Miami-Dade County.

The largest line items are Road (Mobility) Impact Fee - Mid/High-Rise (Miami-Dade County) (MF) ($4,465.00), Educational Facilities (School) Impact Fee (Miami-Dade County) (MF) ($612.00) and Fire-Rescue Impact Fee (Miami-Dade County) (MF) ($527.55).

Sewer Connection/Capacity Fee (Homestead Public Services, MF) and Water Connection/Capacity Fee (Homestead Public Services, MF) are set by the utility and not published online. Police Impact Fee (City of Homestead, MF) and Parks & Recreation Impact Fee (City of Homestead, MF) are set by the city and have no published standard rate. Contact the levying jurisdiction or utility to verify before budgeting; they are not included as dollar figures here.

Some fees are tiered by unit size or building type; amounts reflect the representative tier noted in the schedule below.

View the full fee schedule
Water$0.00
  • Water Connection/Capacity Fee (Homestead Public Services, MF)
    Homestead Public Services (HPS)
    Homestead operates its OWN water utility (HPS; not WASD). MF connection/capacity fee via fee sheet on request; rate PDF image-based. Amount pending. Email publicworks@cityofhomestead.com / 305-224-4570.
    Requires confirmation
Sewer$0.00
  • Sewer Connection/Capacity Fee (Homestead Public Services, MF)
    Homestead Public Services (HPS)
    Homestead operates its OWN sewer utility (HPS; not WASD). MF sewer capacity fee; Sewer Capacity Certification required pre-permit. Amount pending (PDF image-based). Email publicworks@cityofhomestead.com / 305-224-4570.
    Requires confirmation
City$0.00
County$5,604.55
Total (Homestead): $5,604.55
Fees flagged "Requires confirmation" have no confirmed published amount. Confirm them with the jurisdiction or utility before budgeting.

Where in Miami-Dade County are you building?

Each jurisdiction applies its own fee schedule. Pick yours. = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.

Unincorporated Miami-Dade County$9,405.62Aventura$6,548.20Includes unconfirmed feesBal Harbour$6,548.20Includes unconfirmed feesBay Harbor Islands$6,548.20Includes unconfirmed feesBiscayne Park$6,548.20Includes unconfirmed feesCoral Gables$7,647.65Cutler Bay$6,548.20Includes unconfirmed feesDoral$6,548.20Includes unconfirmed feesEl Portal$6,548.20Includes unconfirmed feesFlorida City$5,604.55Includes unconfirmed feesGolden Beach$6,360.55Includes unconfirmed feesHialeah$6,020.65Includes unconfirmed feesHialeah Gardens$5,604.55Includes unconfirmed fees
Homestead$5,604.55this pageIncludes unconfirmed fees
Indian Creek$6,548.20Includes unconfirmed feesKey Biscayne$6,020.65Includes unconfirmed feesMedley$6,548.20Includes unconfirmed feesMiami$6,020.65Includes unconfirmed feesMiami Beach$6,020.65Includes unconfirmed feesMiami Gardens$6,548.20Includes unconfirmed feesMiami Lakes$9,405.62Includes unconfirmed feesMiami Shores$6,548.20Includes unconfirmed feesMiami Springs$6,548.20Includes unconfirmed feesNorth Bay Village$6,548.20Includes unconfirmed feesNorth Miami$15,778.55Includes unconfirmed feesNorth Miami Beach$7,398.70Includes unconfirmed feesOpa-locka$6,548.20Includes unconfirmed feesPalmetto Bay$9,405.62Includes unconfirmed feesPinecrest$6,548.20Includes unconfirmed feesSouth Miami$6,548.20Includes unconfirmed feesSunny Isles Beach$6,548.20Includes unconfirmed feesSurfside$6,548.20Includes unconfirmed feesSweetwater$6,548.20Includes unconfirmed feesVirginia Gardens$6,548.20Includes unconfirmed feesWest Miami$6,548.20Includes unconfirmed fees

Homestead: Commercial Impact Fees

Commercial development in Homestead pays $14.26 per square foot in impact fees, plus $1,659.56 in one-time water and sewer connection fees (rates sourced July 14, 2026).

For a 50,000 sq ft building, that comes to at least $714,669.56. The calculator below adjusts to your exact square footage.

The largest line items are Water Minimum Connection Charge (Homestead Public Services) — 1" meter ($887.68 one-time), Minimum Commercial/Industrial Sewer Connection Charge (Homestead Public Services) — 1" meter ($771.88 one-time) and Road (Mobility) Impact Fee (Miami-Dade County, Commercial) ($13.22/sq ft).

Public Works Impact Fee (City of Homestead, Commercial) and Police Protection Impact Fee (City of Homestead, Commercial) are shown at the last published amount but have not been confirmed with the jurisdiction; they are included in the totals here. Verify before budgeting.

Water Use Charge (Homestead Public Services) and Sewer Use Charge (Homestead Public Services) are set by the utility and not published online. Contact the levying jurisdiction or utility to verify before budgeting; they are not included as dollar figures here.

View the full fee schedule
Water$887.68 one-time
  • Water Minimum Connection Charge (Homestead Public Services) — 1" meter
    Homestead Public Services (City of Homestead)
    Code Sec. 28-182(a). Canonical 1" meter tier. One shared ladder for all customer classes. +25% surcharge if city crews perform the connection (Sec. 28-182(b)). Paid in addition to the Sec. 28-44 water use charge ($2.22/gal ADF).
    $887.68 one-time
  • Water Use Charge (Homestead Public Services)
    Homestead Public Services (City of Homestead)
    Homestead runs its own water utility (HPS), not WASD. Code Sec. 28-44 (Ord. 2025-09-29, adopted 9-9-2025): water use charge = $2.22 PER GALLON of average daily flow, computed per Miami-Dade DERM's published gallonage schedule, paid at the time of connection. This is the capacity/impact component. Expansions and changes of use are recharged on the increment. PER-GALLON basis — no meter ladder for this charge; the separate Sec. 28-182 minimum connection charge IS meter-based (entered separately).
    Contact jurisdiction/utility to verify
Sewer$771.88 one-time
  • Minimum Commercial/Industrial Sewer Connection Charge (Homestead Public Services) — 1" meter
    Homestead Public Services (City of Homestead)
    Code Sec. 28-185(a), canonical 1" meter tier. Dedicated commercial/industrial/institutional ladder (Sec. 28-183 is the separate residential ladder). 'Or time and material, whichever is greater.' In addition to the Sec. 28-142 sewer use charge ($6.69/gal ADF).
    $771.88 one-time
  • Sewer Use Charge (Homestead Public Services)
    Homestead Public Services (City of Homestead)
    Homestead runs its own sewer utility (HPS), not WASD. Code Sec. 28-142 (Ord. 2025-09-29, adopted 9-9-2025): sewer use charge = $6.69 PER GALLON of average daily flow, computed per Miami-Dade DERM's published gallonage schedule, paid at connection. This is the capacity/impact component; Sec. 28-185 calls it 'any impact fee imposed by section 28-142.' Expansions/changes of use are recharged on the increment. Paid IN ADDITION TO the Sec. 28-185 commercial meter-ladder minimum connection charge (entered separately).
    Contact jurisdiction/utility to verify
City$0.48/sq ft
  • Police Protection Impact Fee (City of Homestead, Commercial)
    City of Homestead
    Code Sec. 6-52(1)a.4 (Ord. 2025-09-25, adopted 9-9-2025), 'Impact fee for new and/or increased footage of existing habitable structure', per square foot. Verified verbatim against the adopted Building Division Fee Schedule PDF (homesteadfl.gov DocumentCenter/View/5861, p.3): Police Protection 0.47 / 0.38; Parks & Recreation 2.17 / —; Public Works 0.10 / 0.10; Total 2.74 / 0.48. UNCONFIRMED — COLUMN-HEADER WORDING: the two columns are headed 'Fee (Resident)' and 'Fee (Non-Resident)', not 'Residential/Nonresidential'. Read as residential vs nonresidential (the only coherent reading: Parks has NO figure in the second column, and a residency-of-owner distinction would not zero out a parks fee). $0.38/sf entered as the nonres police rate. Single nonres rate — no category split in the schedule. Confirm the column meaning with Development Services, (305) 224-4500.
    $0.38/sq ftRequires confirmation
  • Public Works Impact Fee (City of Homestead, Commercial)
    City of Homestead
    Code Sec. 6-52(1)a.4 (Ord. 2025-09-25), per sq ft of new/increased footage. $0.10/sf — same figure in both columns. Single nonres rate, no category split. Unconfirmed only as to the 'Resident'/'Non-Resident' column wording (see the Police Protection record). Call (305) 224-4500.
    $0.10/sq ftRequires confirmation
  • Parks & Recreation Impact Fee (City of Homestead, Commercial)
    City of Homestead
    $0 — nonres exempt. Code Sec. 6-52(1)a.4 (Ord. 2025-09-25) prints Parks & Recreation at 2.17 in the first column and a DASH in the second (nonresidential) column, and the nonres Total ($0.48) equals Police ($0.38) + Public Works ($0.10) exactly — so parks is not charged to nonres. Consistent with the FL norm that park/rec fees exempt nonresidential development.
    $0.00
County$13.78/sq ft
  • Road (Mobility) Impact Fee (Miami-Dade County, Commercial)
    Miami-Dade County
    Multimodal Mobility Impact Fee, Code Ch. 33E (Ord. 23-68). Countywide incl. all municipalities. Schedule row: 'Shopping Plaza (40-150 kgsf) w/o Supermarket', Context Zone 4 ($13.216/sf). ZONE CONFIRMED: Code Sec. 33E-7.1(b)(4) NAMES Homestead in Zone 4 (Outer Ring). Excludes 2% admin fee. (Zone 1 SMART-corridor overlay could still reach individual parcels on the South Dade TransitWay.)
    $13.22/sq ft
  • Fire-Rescue Impact Fee (Miami-Dade County, Commercial)
    Miami-Dade County Fire Rescue District
    Code Sec. 33J-1(b): applies throughout the Fire Rescue District incl. all municipalities served. Homestead is served by MDFR (no municipal fire dept; its Code Ch. 22.5 Firefighters' Retirement Plan is a legacy closed plan). Single rate per category.
    $0.56/sq ft
  • Police Impact Fee (Miami-Dade County, Commercial)
    Miami-Dade County
    CONFIRMED $0. Code Sec. 33I-1(b) limits the county police impact fee to unincorporated Miami-Dade County. Homestead has its own PD and levies its own police impact fee (Code Sec. 6-52).
    $0.00
Total (Homestead): $14.26/sq ft + $1,659.56 one-time (≈ $714,669.56 at 50,000 sq ft)
Amounts flagged "Requires confirmation" are the last published figures, included in the totals. Confirm them with the jurisdiction or utility before budgeting.

Where in Miami-Dade County are you building?

Each jurisdiction applies its own fee schedule. Pick yours. Totals shown are for a 50,000 sq ft building, including one-time water/sewer fees (assuming a 1-inch meter). = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.

Unincorporated Miami-Dade County$685,145.00Includes unconfirmed feesAventura$661,260.00Includes unconfirmed feesBal Harbour$661,812.00Includes unconfirmed feesBay Harbor Islands$606,360.00Includes unconfirmed feesBiscayne Park$662,135.00Includes unconfirmed feesCoral Gables$810,570.00Cutler Bay$697,760.00Includes unconfirmed feesDoral$669,960.00El Portal$661,260.00Includes unconfirmed feesFlorida City$953,330.00Includes unconfirmed feesGolden Beach$661,260.00Includes unconfirmed feesHialeah$675,201.50Hialeah Gardens$661,260.00Includes unconfirmed fees
Homestead$714,669.56this pageIncludes unconfirmed fees
Indian Creek$605,060.00Includes unconfirmed feesKey Biscayne$576,850.00Medley$667,560.00Includes unconfirmed feesMiami$836,040.00Includes unconfirmed feesMiami Beach$1,253,000.00Miami Gardens$816,260.00Includes unconfirmed feesMiami Lakes$1,514,283.50Includes unconfirmed feesMiami Shores$605,060.00Includes unconfirmed feesMiami Springs$605,060.00Includes unconfirmed feesNorth Bay Village$606,982.03Includes unconfirmed feesNorth Miami$1,001,308.00Includes unconfirmed feesNorth Miami Beach$808,323.00Includes unconfirmed feesOpa-locka$729,448.00Includes unconfirmed feesPalmetto Bay$948,310.00Includes unconfirmed feesPinecrest$661,260.00Includes unconfirmed feesSouth Miami$661,260.00Includes unconfirmed feesSunny Isles Beach$929,410.00Includes unconfirmed feesSurfside$605,060.00Includes unconfirmed feesSweetwater$877,110.00Includes unconfirmed feesVirginia Gardens$661,260.00Includes unconfirmed feesWest Miami$661,260.00Includes unconfirmed fees

Homestead: Industrial Impact Fees

Industrial development in Homestead pays $7.64 per square foot in impact fees, plus $1,659.56 in one-time water and sewer connection fees (rates sourced July 14, 2026).

For a 50,000 sq ft building, that comes to at least $383,739.56. The calculator below adjusts to your exact square footage.

The largest line items are Water Minimum Connection Charge (Homestead Public Services) — 1" meter ($887.68 one-time), Minimum Commercial/Industrial Sewer Connection Charge (Homestead Public Services) — 1" meter ($771.88 one-time) and Road (Mobility) Impact Fee (Miami-Dade County, Industrial) ($5.45/sq ft).

Police Protection Impact Fee (City of Homestead, Industrial) and Public Works Impact Fee (City of Homestead, Industrial) are shown at the last published amount but have not been confirmed with the jurisdiction; they are included in the totals here. Verify before budgeting.

Water Use Charge (Homestead Public Services) and Sewer Use Charge (Homestead Public Services) are set by the utility and not published online. Contact the levying jurisdiction or utility to verify before budgeting; they are not included as dollar figures here.

View the full fee schedule
Water$887.68 one-time
  • Water Minimum Connection Charge (Homestead Public Services) — 1" meter
    Homestead Public Services (City of Homestead)
    Code Sec. 28-182(a). Canonical 1" meter tier. One shared ladder for all customer classes. +25% surcharge if city crews perform the connection (Sec. 28-182(b)). Paid in addition to the Sec. 28-44 water use charge ($2.22/gal ADF).
    $887.68 one-time
  • Water Use Charge (Homestead Public Services)
    Homestead Public Services (City of Homestead)
    Homestead runs its own water utility (HPS), not WASD. Code Sec. 28-44 (Ord. 2025-09-29, adopted 9-9-2025): water use charge = $2.22 PER GALLON of average daily flow, computed per Miami-Dade DERM's published gallonage schedule, paid at the time of connection. This is the capacity/impact component. Expansions and changes of use are recharged on the increment. PER-GALLON basis — no meter ladder for this charge; the separate Sec. 28-182 minimum connection charge IS meter-based (entered separately).
    Contact jurisdiction/utility to verify
Sewer$771.88 one-time
  • Minimum Commercial/Industrial Sewer Connection Charge (Homestead Public Services) — 1" meter
    Homestead Public Services (City of Homestead)
    Code Sec. 28-185(a), canonical 1" meter tier. Dedicated commercial/industrial/institutional ladder (Sec. 28-183 is the separate residential ladder). 'Or time and material, whichever is greater.' In addition to the Sec. 28-142 sewer use charge ($6.69/gal ADF).
    $771.88 one-time
  • Sewer Use Charge (Homestead Public Services)
    Homestead Public Services (City of Homestead)
    Homestead runs its own sewer utility (HPS), not WASD. Code Sec. 28-142 (Ord. 2025-09-29, adopted 9-9-2025): sewer use charge = $6.69 PER GALLON of average daily flow, computed per Miami-Dade DERM's published gallonage schedule, paid at connection. This is the capacity/impact component; Sec. 28-185 calls it 'any impact fee imposed by section 28-142.' Expansions/changes of use are recharged on the increment. Paid IN ADDITION TO the Sec. 28-185 commercial meter-ladder minimum connection charge (entered separately).
    Contact jurisdiction/utility to verify
City$0.48/sq ft
County$7.16/sq ft
Total (Homestead): $7.64/sq ft + $1,659.56 one-time (≈ $383,739.56 at 50,000 sq ft)
Amounts flagged "Requires confirmation" are the last published figures, included in the totals. Confirm them with the jurisdiction or utility before budgeting.

Where in Miami-Dade County are you building?

Each jurisdiction applies its own fee schedule. Pick yours. Totals shown are for a 50,000 sq ft building, including one-time water/sewer fees (assuming a 1-inch meter). = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.

Unincorporated Miami-Dade County$370,565.00Includes unconfirmed feesAventura$346,680.00Includes unconfirmed feesBal Harbour$347,232.00Includes unconfirmed feesBay Harbor Islands$324,730.00Includes unconfirmed feesBiscayne Park$347,555.00Includes unconfirmed feesCoral Gables$326,620.00Cutler Bay$366,680.00Includes unconfirmed feesDoral$355,380.00El Portal$346,680.00Includes unconfirmed feesFlorida City$467,140.00Includes unconfirmed feesGolden Beach$346,680.00Includes unconfirmed feesHialeah$313,199.00Hialeah Gardens$346,680.00Includes unconfirmed fees
Homestead$383,739.56this pageIncludes unconfirmed fees
Indian Creek$323,430.00Includes unconfirmed feesKey Biscayne$238,000.00Medley$352,980.00Includes unconfirmed feesMiami$282,670.00Includes unconfirmed feesMiami Beach$349,150.00Miami Gardens$501,680.00Includes unconfirmed feesMiami Lakes$368,670.00Includes unconfirmed feesMiami Shores$323,430.00Includes unconfirmed feesMiami Springs$323,430.00Includes unconfirmed feesNorth Bay Village$325,352.03Includes unconfirmed feesNorth Miami$488,778.00Includes unconfirmed feesNorth Miami Beach$485,583.00Includes unconfirmed feesOpa-locka$375,018.00Includes unconfirmed feesPalmetto Bay$466,430.00Includes unconfirmed feesPinecrest$346,680.00Includes unconfirmed feesSouth Miami$346,680.00Includes unconfirmed feesSunny Isles Beach$483,180.00Includes unconfirmed feesSurfside$323,430.00Includes unconfirmed feesSweetwater$408,580.00Includes unconfirmed feesVirginia Gardens$346,680.00Includes unconfirmed feesWest Miami$346,680.00Includes unconfirmed fees

Homestead: Office Impact Fees

Office development in Homestead pays $20.32 per square foot in impact fees, plus $1,659.56 in one-time water and sewer connection fees (rates sourced July 14, 2026).

For a 25,000 sq ft building, that comes to at least $509,687.06. The calculator below adjusts to your exact square footage.

The largest line items are Water Minimum Connection Charge (Homestead Public Services) — 1" meter ($887.68 one-time), Minimum Commercial/Industrial Sewer Connection Charge (Homestead Public Services) — 1" meter ($771.88 one-time) and Road (Mobility) Impact Fee (Miami-Dade County, Office) ($19.42/sq ft).

Public Works Impact Fee (City of Homestead, Office) and Police Protection Impact Fee (City of Homestead, Office) are shown at the last published amount but have not been confirmed with the jurisdiction; they are included in the totals here. Verify before budgeting.

Water Use Charge (Homestead Public Services) and Sewer Use Charge (Homestead Public Services) are set by the utility and not published online. Contact the levying jurisdiction or utility to verify before budgeting; they are not included as dollar figures here.

View the full fee schedule
Water$887.68 one-time
  • Water Minimum Connection Charge (Homestead Public Services) — 1" meter
    Homestead Public Services (City of Homestead)
    Code Sec. 28-182(a). Canonical 1" meter tier. One shared ladder for all customer classes. +25% surcharge if city crews perform the connection (Sec. 28-182(b)). Paid in addition to the Sec. 28-44 water use charge ($2.22/gal ADF).
    $887.68 one-time
  • Water Use Charge (Homestead Public Services)
    Homestead Public Services (City of Homestead)
    Homestead runs its own water utility (HPS), not WASD. Code Sec. 28-44 (Ord. 2025-09-29, adopted 9-9-2025): water use charge = $2.22 PER GALLON of average daily flow, computed per Miami-Dade DERM's published gallonage schedule, paid at the time of connection. This is the capacity/impact component. Expansions and changes of use are recharged on the increment. PER-GALLON basis — no meter ladder for this charge; the separate Sec. 28-182 minimum connection charge IS meter-based (entered separately).
    Contact jurisdiction/utility to verify
Sewer$771.88 one-time
  • Minimum Commercial/Industrial Sewer Connection Charge (Homestead Public Services) — 1" meter
    Homestead Public Services (City of Homestead)
    Code Sec. 28-185(a), canonical 1" meter tier. Dedicated commercial/industrial/institutional ladder (Sec. 28-183 is the separate residential ladder). 'Or time and material, whichever is greater.' In addition to the Sec. 28-142 sewer use charge ($6.69/gal ADF).
    $771.88 one-time
  • Sewer Use Charge (Homestead Public Services)
    Homestead Public Services (City of Homestead)
    Homestead runs its own sewer utility (HPS), not WASD. Code Sec. 28-142 (Ord. 2025-09-29, adopted 9-9-2025): sewer use charge = $6.69 PER GALLON of average daily flow, computed per Miami-Dade DERM's published gallonage schedule, paid at connection. This is the capacity/impact component; Sec. 28-185 calls it 'any impact fee imposed by section 28-142.' Expansions/changes of use are recharged on the increment. Paid IN ADDITION TO the Sec. 28-185 commercial meter-ladder minimum connection charge (entered separately).
    Contact jurisdiction/utility to verify
City$0.48/sq ft
County$19.84/sq ft
Total (Homestead): $20.32/sq ft + $1,659.56 one-time (≈ $509,687.06 at 25,000 sq ft)
Amounts flagged "Requires confirmation" are the last published figures, included in the totals. Confirm them with the jurisdiction or utility before budgeting.

Where in Miami-Dade County are you building?

Each jurisdiction applies its own fee schedule. Pick yours. Totals shown are for a 25,000 sq ft building, including one-time water/sewer fees (assuming a 1-inch meter). = one or more fees are unconfirmed or have no published amount; the figure shown may not be the complete cost.

Unincorporated Miami-Dade County$487,595.00Includes unconfirmed feesAventura$475,652.50Includes unconfirmed feesBal Harbour$476,204.50Includes unconfirmed feesBay Harbor Islands$435,627.50Includes unconfirmed feesBiscayne Park$476,527.50Includes unconfirmed feesCoral Gables$569,620.00Cutler Bay$487,652.50Includes unconfirmed feesDoral$480,002.50El Portal$475,652.50Includes unconfirmed feesFlorida City$690,247.50Includes unconfirmed feesGolden Beach$475,652.50Includes unconfirmed feesHialeah$493,483.00Hialeah Gardens$475,652.50Includes unconfirmed fees
Homestead$509,687.06this pageIncludes unconfirmed fees
Indian Creek$434,327.50Includes unconfirmed feesKey Biscayne$423,850.00Medley$481,952.50Includes unconfirmed feesMiami$485,405.00Includes unconfirmed feesMiami Beach$543,500.00Miami Gardens$553,152.50Includes unconfirmed feesMiami Lakes$530,854.00Includes unconfirmed feesMiami Shores$434,327.50Includes unconfirmed feesMiami Springs$434,327.50Includes unconfirmed feesNorth Bay Village$436,249.53Includes unconfirmed feesNorth Miami$648,200.50Includes unconfirmed feesNorth Miami Beach$546,424.50Includes unconfirmed feesOpa-locka$486,590.50Includes unconfirmed feesPalmetto Bay$687,177.50Includes unconfirmed feesPinecrest$475,652.50Includes unconfirmed feesSouth Miami$475,652.50Includes unconfirmed feesSunny Isles Beach$570,427.50Includes unconfirmed feesSurfside$434,327.50Includes unconfirmed feesSweetwater$565,502.50Includes unconfirmed feesVirginia Gardens$475,652.50Includes unconfirmed feesWest Miami$475,652.50Includes unconfirmed fees

Estimate your project in Homestead

Set to single-family. Drop a pin or search an address for site-specific fees.

Location

Loading map…
Search an address or click anywhere on the map to begin.

Select a location to begin

Once you select an address or drop a pin, we'll identify the responsible city and county and generate a fee breakdown.

Water & Sewer
Transportation
Parks
Schools
Fire & Police
General

How impact fees work in Florida

Florida impact fees are one-time charges on new development, governed by Section 163.31801, Florida Statutes (the Florida Impact Fee Act). The statute requires fees to be based on the most recent and localized data, spent on the infrastructure category they were collected for, and adopted by ordinance.

Since 2021, the law also limits how fast fees can rise: increases up to 25% phase in over two years, increases of 25–50% phase in over four years, and increases above 50% are allowed only with a demonstrated extraordinary-circumstances study and at least a two-thirds vote of the governing body.

Counties and cities can both levy impact fees. Inside an incorporated city, a project typically pays the county's countywide fees plus any municipal fees the city has adopted, which is why totals differ between a city and the unincorporated county around it.

Frequently asked questions

What are the total impact fees for a single-family home in Homestead, Florida?

A new single-family home in Homestead pays at least $12,250.55 per unit in combined impact fees (rates sourced July 14, 2026). 4 additional fees have no published standard amounts and are not included, so the full cost may be higher; verify before budgeting.

How much are commercial impact fees in Homestead?

Commercial development in Homestead pays $14.26 per square foot in impact fees, plus $1,659.56 in one-time water and sewer connection fees, at least $714,669.56 for a 50,000 sq ft building. This figure includes amounts that have not been confirmed and excludes fees with no published standard amount, so the full cost may be higher; verify before budgeting.

Does Homestead charge its own impact fees?

Yes. Homestead levies its own municipal impact or utility fees, and county-levied fees also apply inside city limits. The schedule on this page shows every fee that applies to development in Homestead, with the combined total.

Can Florida impact fees increase at any time?

No. Section 163.31801, Florida Statutes limits increases to 50% at most, phased in over two to four years, unless the local government makes extraordinary-circumstances findings and approves the increase by at least a two-thirds vote.

Fee amounts on this page are compiled from official published schedules and are provided for planning purposes only. Rates change, and project specifics (unit size, meter size, location within special districts) can alter what applies. Always verify current fees with the jurisdiction and utility before relying on them.

Compare unincorporated rates and every other city on the Miami-Dade County impact fees page.